6529 N COLBATH AVE 91401

Certificate Information: 6529 N COLBATH AVE 91401

Application / Permit
24014-20000-04712
Plan Check / Job No.
B24VN20489
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: ADDITION AND CONVERSION OF UTILITY BUILDING TO ADU PER LAMC 12.22A.33 (c)(d) WORK DONE PER WFPP **13D SPRINKLER REQUIRED*** 1 OF 2
Permit Issued
Issued on 1/30/2025
Issuing Office
Current Status
CofO Issued on 8/14/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/22/2024 APPLICANT
Assigned to Plan Check Engineer 10/31/2024 KHUONG TRUONG
Corrections Issued 11/1/2024 KHUONG TRUONG
Quality Review Completed 11/5/2024 GARO TELMI
Applicant returned to address corrections 1/21/2025 KHUONG TRUONG
Plan Check Approved 1/30/2025 KHUONG TRUONG
Issued 1/30/2025 APPLICANT
CofO in Progress 8/12/2025 RYAN SALAZAR
Permit Finaled 8/14/2025 RUBEN SALAS
CofO Issued 8/14/2025 RUBEN SALAS
Permit Finaled 8/14/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 11/7/2024 RYAN CASTRO
Roof/Waste drainage to street Cleared 11/7/2024 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 11/8/2024 RYAN CASTRO
Sewer availability Cleared 11/8/2024 RYAN CASTRO
Construction near power lines Cleared 1/30/2025 EDGAR PASCUA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/4/2025 Conditional Approval ROBERT GOLD
Excavation/Setback/Form/Re-Bar 3/5/2025 Approved RYAN SALAZAR
PLUMBING-Rough 3/5/2025 Partial Approval RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 3/11/2025 Approved RYAN SALAZAR
ELECTRICAL-Rough 3/14/2025 Not Ready for Inspection RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 3/14/2025 Approved RYAN SALAZAR
HVAC-Rough 3/14/2025 Approved RYAN SALAZAR
PLUMBING-Rough 3/14/2025 Conditional Approval RYAN SALAZAR
BUILDING-Rough-Frame 4/14/2025 Approved RYAN SALAZAR
ELECTRICAL-Rough 4/14/2025 Approved RYAN SALAZAR
Green Building Rough 4/14/2025 Approved RYAN SALAZAR
Insulation 4/14/2025 Approved RYAN SALAZAR
Interior/Exterior Lathing 4/14/2025 Partial Approval RYAN SALAZAR
Drywall Nailing 4/16/2025 Approved RYAN SALAZAR
Interior/Exterior Lathing 4/17/2025 Approved RYAN SALAZAR
Shower Pan 4/17/2025 Approved RYAN SALAZAR
Underground Mechanical 5/20/2025 Approved RYAN SALAZAR
Final 6/9/2025 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 6/9/2025 Approved MISAEL ESPARZA
Green Building Final 6/9/2025 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 6/9/2025 SGSOV Not Required MISAEL ESPARZA
Smoke Detectors 6/9/2025 Corrections Issued MISAEL ESPARZA
Final 7/10/2025 Partial Approval RYAN SALAZAR
Smoke Detectors 7/10/2025 Approved RYAN SALAZAR
Final 8/11/2025 OK to Issue CofO RYAN SALAZAR
Service/Power Release 8/11/2025 Approved RYAN SALAZAR