6529 N COLBATH AVE 91401
Certificate Information: 6529 N COLBATH AVE 91401
- Application / Permit
- 24014-20000-04712
- Plan Check / Job No.
- B24VN20489
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: ADDITION AND CONVERSION OF UTILITY BUILDING TO ADU PER LAMC 12.22A.33 (c)(d) WORK DONE PER WFPP **13D SPRINKLER REQUIRED*** 1 OF 2
- Permit Issued
- Issued on 1/30/2025
- Issuing Office
- Current Status
- CofO Issued on 8/14/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/22/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/31/2024 | KHUONG TRUONG |
| Corrections Issued | 11/1/2024 | KHUONG TRUONG |
| Quality Review Completed | 11/5/2024 | GARO TELMI |
| Applicant returned to address corrections | 1/21/2025 | KHUONG TRUONG |
| Plan Check Approved | 1/30/2025 | KHUONG TRUONG |
| Issued | 1/30/2025 | APPLICANT |
| CofO in Progress | 8/12/2025 | RYAN SALAZAR |
| Permit Finaled | 8/14/2025 | RUBEN SALAS |
| CofO Issued | 8/14/2025 | RUBEN SALAS |
| Permit Finaled | 8/14/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 11/7/2024 | RYAN CASTRO |
| Roof/Waste drainage to street | Cleared | 11/7/2024 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 11/8/2024 | RYAN CASTRO |
| Sewer availability | Cleared | 11/8/2024 | RYAN CASTRO |
| Construction near power lines | Cleared | 1/30/2025 | EDGAR PASCUA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/4/2025 | Conditional Approval | ROBERT GOLD |
| Excavation/Setback/Form/Re-Bar | 3/5/2025 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 3/5/2025 | Partial Approval | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 3/11/2025 | Approved | RYAN SALAZAR |
| ELECTRICAL-Rough | 3/14/2025 | Not Ready for Inspection | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 3/14/2025 | Approved | RYAN SALAZAR |
| HVAC-Rough | 3/14/2025 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 3/14/2025 | Conditional Approval | RYAN SALAZAR |
| BUILDING-Rough-Frame | 4/14/2025 | Approved | RYAN SALAZAR |
| ELECTRICAL-Rough | 4/14/2025 | Approved | RYAN SALAZAR |
| Green Building Rough | 4/14/2025 | Approved | RYAN SALAZAR |
| Insulation | 4/14/2025 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 4/14/2025 | Partial Approval | RYAN SALAZAR |
| Drywall Nailing | 4/16/2025 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 4/17/2025 | Approved | RYAN SALAZAR |
| Shower Pan | 4/17/2025 | Approved | RYAN SALAZAR |
| Underground Mechanical | 5/20/2025 | Approved | RYAN SALAZAR |
| Final | 6/9/2025 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 6/9/2025 | Approved | MISAEL ESPARZA |
| Green Building Final | 6/9/2025 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 6/9/2025 | SGSOV Not Required | MISAEL ESPARZA |
| Smoke Detectors | 6/9/2025 | Corrections Issued | MISAEL ESPARZA |
| Final | 7/10/2025 | Partial Approval | RYAN SALAZAR |
| Smoke Detectors | 7/10/2025 | Approved | RYAN SALAZAR |
| Final | 8/11/2025 | OK to Issue CofO | RYAN SALAZAR |
| Service/Power Release | 8/11/2025 | Approved | RYAN SALAZAR |