10341 W PENROSE ST 91352
Certificate Information: 10341 W PENROSE ST 91352
- Application / Permit
- 24014-20000-04708
- Plan Check / Job No.
- B24VN20464
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan. Remove (E) Storage attached to Garage. Convert (E) Detached Garage to (N) Accessory Dwelling Unit with addition per LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 2/19/2025
- Issuing Office
- Current Status
- CofO Issued on 11/14/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/6/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/12/2024 | AMY GUEVARRA |
| Corrections Issued | 11/17/2024 | AMY GUEVARRA |
| Applicant returned to address corrections | 1/30/2025 | AMY GUEVARRA |
| Applicant returned to address corrections | 2/13/2025 | AMY GUEVARRA |
| Plan Check Approved | 2/18/2025 | AMY GUEVARRA |
| Issued | 2/19/2025 | APPLICANT |
| CofO in Progress | 10/3/2025 | DAVID ANDERSON |
| Permit Finaled | 11/14/2025 | RUBEN SALAS |
| CofO Issued | 11/14/2025 | RUBEN SALAS |
| Permit Finaled | 11/14/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 12/23/2024 | RYAN CASTRO |
| Roof/Waste drainage to street | Cleared | 12/23/2024 | RYAN CASTRO |
| Grading Pre-Inspection | Cleared | 1/24/2025 | CHARLES POWELL |
| Eng Process Fee Ord 176,300 | Cleared | 1/28/2025 | RYAN CASTRO |
| Miscellaneous | Cleared | 1/28/2025 | MAYELA VILLA |
| Sewer availability | Cleared | 1/28/2025 | RYAN CASTRO |
| Specific Plan | Cleared | 2/12/2025 | DANG NGUYEN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Castillo,, Margarito; Lic. No.: NA4808 | , |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/21/2025 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 3/24/2025 | Corrections Issued | DAVID ANDERSON |
| PLUMBING-Rough | 3/24/2025 | Conditional Approval | DAVID ANDERSON |
| Footing/Foundation/Slab | 4/1/2025 | Corrections Issued | VINCENT HANLEY |
| Pre-Inspection | 4/1/2025 | Not Ready for Inspection | VINCENT HANLEY |
| Footing/Foundation/Slab | 4/17/2025 | Not Ready for Inspection | DAVID ANDERSON |
| Pre-Inspection | 4/17/2025 | Approved | DAVID ANDERSON |
| Footing/Foundation/Slab | 4/28/2025 | Approved | DAVID ANDERSON |
| Pre-Inspection | 4/28/2025 | Approved | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/14/2025 | Corrections Issued | DAVID ANDERSON |
| ELECTRICAL-Rough | 6/11/2025 | Corrections Issued | DAVID ANDERSON |
| PLUMBING-Rough | 6/11/2025 | Corrections Issued | DAVID ANDERSON |
| Special/Order Compliance | 6/11/2025 | Corrections Issued | DAVID ANDERSON |
| Deputy Wood Construction | 6/16/2025 | Conditional Approval | DAVID MATSON |
| Deputy Wood Construction | 6/24/2025 | Conditional Approval | DAVID MATSON |
| ELECTRICAL-Rough | 6/25/2025 | Approved | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/25/2025 | Approved | DAVID ANDERSON |
| HVAC-Rough | 6/25/2025 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 6/25/2025 | Approved | DAVID ANDERSON |
| Underground Mechanical | 7/9/2025 | Partial Approval | DAVID ANDERSON |
| BUILDING-Rough-Frame | 7/16/2025 | Approved | DAVID MATSON |
| Green Building Rough | 7/16/2025 | Approved | DAVID MATSON |
| Insulation | 7/16/2025 | Approved | DAVID MATSON |
| Interior/Exterior Lathing | 7/16/2025 | Partial Approval | DAVID MATSON |
| Drywall Nailing | 7/23/2025 | Not Ready for Inspection | WILLIAM WREN |
| Sewer | 7/23/2025 | Approved | WILLIAM WREN |
| Drywall Nailing | 7/28/2025 | Approved | DAVID ANDERSON |
| Final | 9/25/2025 | Corrections Issued | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 9/25/2025 | SGSOV Not Ready | DAVID ANDERSON |
| Smoke Detectors | 9/25/2025 | Not Ready for Inspection | DAVID ANDERSON |
| Final | 10/2/2025 | OK to Issue CofO | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 10/2/2025 | SGSOV Approved | DAVID ANDERSON |
| Smoke Detectors | 10/2/2025 | Approved | DAVID ANDERSON |