2828 S FIGUEROA ST 90007

Certificate Information: 2828 S FIGUEROA ST 90007

Application / Permit
24014-20000-04698
Plan Check / Job No.
B24VN20402
Group
Building
Type
Bldg-Addition
Sub-Type
Commercial
Primary Use
(17) Restaurant
Work Description
*EPLAN* TENANT IMPROVEMENT TO EXISTING RESTAURANT AND ADD FOR NEW WALK IN FREEZER AND COOLER
Permit Issued
Issued on 4/16/2026
Issuing Office
Current Status
Issued on 4/16/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/22/2024 APPLICANT
Assigned to Plan Check Engineer 10/24/2024 SELLA BENYAMIN
Assigned to Zoning Architect 10/24/2024 FRANCIS AHN
Corrections Issued 10/31/2024 SELLA BENYAMIN
Quality Review Completed 10/31/2024 STEVEN KIM
Applicant returned to address corrections 3/6/2025 SELLA BENYAMIN
Plan Check Approved 6/18/2025 SELLA BENYAMIN
Issued 4/16/2026 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 12/9/2024 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 12/11/2024 ADRIAN SANCHEZ
Historic Resource Verification Cleared 12/13/2024 YASMINE BASHIRI
Redevelopment Project Area Cleared 12/13/2024 YASMINE BASHIRI
Green Code Cleared 2/27/2025 MICHAEL AYERS
DAS Clearance Cleared 6/2/2025 Pinank Patel
Zoning Plan Check Cleared 6/12/2025 Pinank Patel

Contact Information

Architect Wang,, Gary H; Lic. No.: NA32569       ,
Contractor Craft Construction Company; Lic. No.: 790985-B       ,

Inspector Information

PAUL BAZERKANIAN, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
LUIS CCAMACHO, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
ALAN MORELOS, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Structural Steel Frame 5/27/2026 Partial Approval PAUL BAZERKANIAN
Drywall Nailing 5/29/2026 Not Ready for Inspection ALFREDO LOPEZ
Deputy Drilled-In Anchors 6/4/2026 Approved PAUL BAZERKANIAN
Deputy Reinf. Concrete 6/4/2026 Approved PAUL BAZERKANIAN
Footing/Foundation/Slab 6/4/2026 Partial Approval PAUL BAZERKANIAN
METHANE-Barrier 6/4/2026 Approved PAUL BAZERKANIAN
METHANE-Subgrade 6/4/2026 Approved PAUL BAZERKANIAN
Light Gage Steel Frame 6/12/2026 Partial Approval ALFREDO LOPEZ
Drywall Nailing 6/15/2026 Partial Approval ALFREDO LOPEZ
Drywall Nailing 6/23/2026 Partial Approval ALFREDO LOPEZ
Pre-Inspection 6/29/2026 Partial Inspection ALFREDO LOPEZ
Excavation/Setback/Form/Re-Bar 7/9/2026 Partial Approval PAUL BAZERKANIAN