13200 W WARREN AVE 90066
Certificate Information: 13200 W WARREN AVE 90066
- Application / Permit
- 24014-20000-04691
- Plan Check / Job No.
- B24VN20344
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMOVE AND REPLACE THE (E) CARPORT AND ATTACH TO THE (E) SINGLE FAMILY DWELLING ALL WORK PER ENGINEERING SEE COMMENTS
- Permit Issued
- Issued on 12/24/2024
- Issuing Office
- Current Status
- CofO in Progress on 1/13/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/21/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/21/2024 | LUISANGEL VALENZUELA |
| Corrections Issued | 10/21/2024 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 11/19/2024 | JESSE ARELLANO |
| Applicant returned to address corrections | 12/17/2024 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 12/24/2024 | SEWADA ZADOORAN MILAGARDI |
| Issued | 12/24/2024 | APPLICANT |
| CofO in Progress | 1/13/2026 | DAVID FEILER |
Permit Application Clearance Information
| Specific Plan | Cleared | 10/24/2024 | RICHARD WOO |
| Grading Pre-Inspection | Cleared | 10/25/2024 | CHARLES POWELL |
| Eng Process Fee Ord 176,300 | Cleared | 11/12/2024 | KIMBERLY HERNANDEZ |
| Roof/Waste drainage to street | Cleared | 11/12/2024 | KIMBERLY HERNANDEZ |
| ZA Case | Cleared | 11/15/2024 | DALIA MOKAYED |
Contact Information
| Architect | Bambrough,, Patrick; Lic. No.: C34299 | 1590 ANDERSON AVE. APT 5J FORT LEE, NJ 07024 |
| Architect | Cichowski,, Joel Brennan; Lic. No.: C30916 | 1618 OCEAN PARK BOULEVARD SANTA MONICA, CA 90405 |
| Contractor | Warner Technologies Inc; Lic. No.: 764311-B | 11693 SAN VICENTE BLVD #717 LOS ANGELES, CA 90049 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/12/2025 | Partial Inspection | MICHAEL ALLEN |
| Footing/Foundation/Slab | 3/18/2025 | Partial Approval | JESUS RODRIGUEZ |
| Deputy Drilled-In Anchors | 4/8/2025 | Conditional Approval | DAVID FEILER |
| ELECTRICAL-Rough | 4/10/2025 | Partial Approval | MICHAEL ALLEN |
| Floor/Roof Diaphrgm/Shear Wall | 4/10/2025 | Approved | MICHAEL ALLEN |
| Special/Order Compliance | 4/10/2025 | Corrections Issued | MICHAEL ALLEN |
| ELECTRICAL-Rough | 4/14/2025 | Partial Approval | MICHAEL ALLEN |
| Footing/Foundation/Slab | 4/14/2025 | Approved | MICHAEL ALLEN |
| Insulation | 4/14/2025 | Approved | MICHAEL ALLEN |
| Floor/Roof Diaphrgm/Shear Wall | 5/14/2025 | Partial Approval | MICHAEL ALLEN |
| BUILDING-Rough-Frame | 6/3/2025 | Conditional Approval | MICHAEL ALLEN |
| ELECTRICAL-Rough | 6/3/2025 | Approved | MICHAEL ALLEN |
| Floor/Roof Diaphrgm/Shear Wall | 6/3/2025 | Approved | MICHAEL ALLEN |
| Green Building Rough | 6/3/2025 | Conditional Approval | MICHAEL ALLEN |
| Drywall Nailing | 6/23/2025 | Approved | JAYLIN GRAVITTE |
| Green Building Rough | 6/23/2025 | Approved | JAYLIN GRAVITTE |
| Interior/Exterior Lathing | 6/23/2025 | Approved | JAYLIN GRAVITTE |
| BUILDING-Rough-Frame | 12/17/2025 | Approved | ANDREW NAVE |
| Final | 12/17/2025 | Corrections Issued | ANDREW NAVE |
| Green Building Final | 12/17/2025 | Approved | ANDREW NAVE |
| SGSOV-Seismic Gas S/O Valve | 12/17/2025 | SGSOV Approved | ANDREW NAVE |
| Smoke Detectors | 12/17/2025 | Approved | ANDREW NAVE |
| Final | 1/13/2026 | OK to Issue CofO | DAVID FEILER |