13200 W WARREN AVE 90066

Certificate Information: 13200 W WARREN AVE 90066

Application / Permit
24014-20000-04691
Plan Check / Job No.
B24VN20344
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMOVE AND REPLACE THE (E) CARPORT AND ATTACH TO THE (E) SINGLE FAMILY DWELLING ALL WORK PER ENGINEERING SEE COMMENTS
Permit Issued
Issued on 12/24/2024
Issuing Office
Current Status
CofO in Progress on 1/13/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/21/2024 APPLICANT
Assigned to Plan Check Engineer 10/21/2024 LUISANGEL VALENZUELA
Corrections Issued 10/21/2024 LUISANGEL VALENZUELA
Applicant returned to address corrections 11/19/2024 JESSE ARELLANO
Applicant returned to address corrections 12/17/2024 ALEC MOUSAKHANIAN
Plan Check Approved 12/24/2024 SEWADA ZADOORAN MILAGARDI
Issued 12/24/2024 APPLICANT
CofO in Progress 1/13/2026 DAVID FEILER

Permit Application Clearance Information

Specific Plan Cleared 10/24/2024 RICHARD WOO
Grading Pre-Inspection Cleared 10/25/2024 CHARLES POWELL
Eng Process Fee Ord 176,300 Cleared 11/12/2024 KIMBERLY HERNANDEZ
Roof/Waste drainage to street Cleared 11/12/2024 KIMBERLY HERNANDEZ
ZA Case Cleared 11/15/2024 DALIA MOKAYED

Contact Information

Architect Bambrough,, Patrick; Lic. No.: C34299 1590 ANDERSON AVE. APT 5J      FORT LEE, NJ 07024
Architect Cichowski,, Joel Brennan; Lic. No.: C30916 1618 OCEAN PARK BOULEVARD      SANTA MONICA, CA 90405
Contractor Warner Technologies Inc; Lic. No.: 764311-B 11693 SAN VICENTE BLVD #717      LOS ANGELES, CA 90049

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/12/2025 Partial Inspection MICHAEL ALLEN
Footing/Foundation/Slab 3/18/2025 Partial Approval JESUS RODRIGUEZ
Deputy Drilled-In Anchors 4/8/2025 Conditional Approval DAVID FEILER
ELECTRICAL-Rough 4/10/2025 Partial Approval MICHAEL ALLEN
Floor/Roof Diaphrgm/Shear Wall 4/10/2025 Approved MICHAEL ALLEN
Special/Order Compliance 4/10/2025 Corrections Issued MICHAEL ALLEN
ELECTRICAL-Rough 4/14/2025 Partial Approval MICHAEL ALLEN
Footing/Foundation/Slab 4/14/2025 Approved MICHAEL ALLEN
Insulation 4/14/2025 Approved MICHAEL ALLEN
Floor/Roof Diaphrgm/Shear Wall 5/14/2025 Partial Approval MICHAEL ALLEN
BUILDING-Rough-Frame 6/3/2025 Conditional Approval MICHAEL ALLEN
ELECTRICAL-Rough 6/3/2025 Approved MICHAEL ALLEN
Floor/Roof Diaphrgm/Shear Wall 6/3/2025 Approved MICHAEL ALLEN
Green Building Rough 6/3/2025 Conditional Approval MICHAEL ALLEN
Drywall Nailing 6/23/2025 Approved JAYLIN GRAVITTE
Green Building Rough 6/23/2025 Approved JAYLIN GRAVITTE
Interior/Exterior Lathing 6/23/2025 Approved JAYLIN GRAVITTE
BUILDING-Rough-Frame 12/17/2025 Approved ANDREW NAVE
Final 12/17/2025 Corrections Issued ANDREW NAVE
Green Building Final 12/17/2025 Approved ANDREW NAVE
SGSOV-Seismic Gas S/O Valve 12/17/2025 SGSOV Approved ANDREW NAVE
Smoke Detectors 12/17/2025 Approved ANDREW NAVE
Final 1/13/2026 OK to Issue CofO DAVID FEILER