16328 W PARTHENIA ST 91343

Certificate Information: 16328 W PARTHENIA ST 91343

Application / Permit
24014-20000-04690
Plan Check / Job No.
B24VN20341
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE WITH ADDITION INTO A (N) 40'-0" x 20'-0" DWELLING UNIT TO COMPLY WITH LAMC 12.22 A.33 (c)-(d) PER WFPP
Permit Issued
Issued on 4/8/2025
Issuing Office
Valley
Current Status
CofO Issued on 11/13/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/21/2024 APPLICANT
Assigned to Plan Check Engineer 10/31/2024 ALFRED RAMIREZ
Corrections Issued 11/4/2024 ALFRED RAMIREZ
Quality Review Completed 11/7/2024 STEVEN KIM
Building Plans Picked Up 11/8/2024 APPLICANT
Applicant returned to address corrections 3/17/2025 ALFRED RAMIREZ
Plan Check Approved 4/8/2025 ALFRED RAMIREZ
Issued 4/8/2025 APPLICANT
CofO in Progress 10/31/2025 GAREN HAYRAPETYAN
CofO Issued 11/13/2025 RUBEN SALAS
Permit Finaled 11/13/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 2/25/2025 RYAN CASTRO
Roof/Waste drainage to street Cleared 2/25/2025 RYAN CASTRO
"Q" conditions Cleared 3/17/2025 RUBEN VASQUEZ
ZA Case Cleared 3/17/2025 RUBEN VASQUEZ
Eng Process Fee Ord 176,300 Cleared 4/1/2025 RYAN CASTRO
Sewer availability Cleared 4/1/2025 RYAN CASTRO

Contact Information

Contractor Cf Electrical & General Contractor; Lic. No.: 849060-B 11714 TERRA BELLA ST      SYLMAR, CA 91342

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/24/2025 Partial Approval SALVADOR MARTINEZ
Special/Order Compliance 4/24/2025 Corrections Issued SALVADOR MARTINEZ
Deputy Drilled-In Anchors 4/28/2025 Conditional Approval SALVADOR MARTINEZ
Footing/Foundation/Slab 4/30/2025 Corrections Issued SALVADOR MARTINEZ
Footing/Foundation/Slab 5/19/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 5/21/2025 Approved GAREN HAYRAPETYAN
Floor/Roof Diaphrgm/Shear Wall 6/10/2025 Corrections Issued MICHAEL CORTEZ
HVAC-Rough 7/17/2025 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Rough 7/17/2025 Corrections Issued SALVADOR MARTINEZ
Underground Mechanical 7/17/2025 Approved SALVADOR MARTINEZ
BUILDING-Rough-Frame 7/21/2025 Not Ready for Inspection SALVADOR MARTINEZ
ELECTRICAL-Rough 7/21/2025 Corrections Issued SALVADOR MARTINEZ
HVAC-Rough 7/21/2025 Approved SALVADOR MARTINEZ
PLUMBING-Rough 7/21/2025 Corrections Issued SALVADOR MARTINEZ
Sewer 7/21/2025 Corrections Issued SALVADOR MARTINEZ
ELECTRICAL-Rough 7/23/2025 Approved SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 7/23/2025 Partial Approval SALVADOR MARTINEZ
PLUMBING-Rough 7/23/2025 Approved SALVADOR MARTINEZ
Sewer 7/23/2025 Approved SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 8/4/2025 Approved VINCENT HANLEY
Wood Frame 8/4/2025 Approved VINCENT HANLEY
Insulation 8/7/2025 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 8/7/2025 Partial Approval JAVIER RAMOS JR
Drywall Nailing 8/12/2025 Approved SALVADOR MARTINEZ
Green Building Rough 8/12/2025 Approved SALVADOR MARTINEZ
Interior/Exterior Lathing 8/12/2025 Approved SALVADOR MARTINEZ
BUILDING-Rough-Frame 10/20/2025 Approved GAREN HAYRAPETYAN
Final 10/20/2025 Corrections Issued GAREN HAYRAPETYAN
Green Building Final 10/20/2025 Approved GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 10/20/2025 SGSOV Approved GAREN HAYRAPETYAN
Smoke Detectors 10/20/2025 Corrections Issued GAREN HAYRAPETYAN
Final 10/28/2025 Not Ready for Inspection WAYNE REGESTER
Service/Power Release 10/28/2025 Approved WAYNE REGESTER
Smoke Detectors 10/28/2025 Not Ready for Inspection WAYNE REGESTER
Final 10/31/2025 OK to Issue CofO GAREN HAYRAPETYAN
Smoke Detectors 10/31/2025 Approved GAREN HAYRAPETYAN