5758 N MAMMOTH AVE 91401

Certificate Information: 5758 N MAMMOTH AVE 91401

Application / Permit
24014-20000-04657
Plan Check / Job No.
B24VN20141
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Eplan. Addition and remodel to existing single family for new bedrooms and bathroom, replace windows at bedrooms.
Permit Issued
Issued on 12/30/2024
Issuing Office
Current Status
CofO Issued on 5/27/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/22/2024 APPLICANT
Assigned to Plan Check Engineer 10/25/2024 SAMUEL GONZALEZ
Corrections Issued 10/26/2024 SAMUEL GONZALEZ
Plan Check Approved 11/13/2024 ADAM HEGAZI
Issued 12/30/2024 APPLICANT
CofO in Progress 5/22/2025 RYAN SALAZAR
Permit Finaled 5/27/2025 RUBEN SALAS
CofO Issued 5/27/2025 RUBEN SALAS
Permit Finaled 5/27/2025 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 10/28/2024 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 10/28/2024 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 11/13/2024 LEE GUILBEAUX
Sewer availability Cleared 11/13/2024 LEE GUILBEAUX

Contact Information

Architect Dembsky,, Amit; Lic. No.: NA30383       ,
Contractor Owner-Builder       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/28/2025 Conditional Approval RAUL OLAGI
Footing/Foundation/Slab 1/29/2025 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 2/4/2025 Approved RYAN SALAZAR
PLUMBING-Rough 2/4/2025 Partial Approval RYAN SALAZAR
Deputy Wood Construction 2/24/2025 Conditional Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 2/25/2025 Approved RYAN SALAZAR
Wood Frame 2/25/2025 Partial Approval RYAN SALAZAR
BUILDING-Rough-Frame 3/14/2025 Approved RYAN SALAZAR
Green Building Rough 3/14/2025 Approved RYAN SALAZAR
Rough-Elec/Plmb/HVAC 3/14/2025 Approved RYAN SALAZAR
Insulation 3/21/2025 Approved RYAN SALAZAR
Interior/Exterior Lathing 3/21/2025 Partial Approval RYAN SALAZAR
Shower Pan 3/21/2025 Approved RYAN SALAZAR
Drywall Nailing 3/27/2025 Approved RYAN SALAZAR
Interior/Exterior Lathing 3/27/2025 Approved RYAN SALAZAR
Final 5/21/2025 OK to Issue CofO RYAN SALAZAR
Green Building Final 5/21/2025 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 5/21/2025 SGSOV Approved RYAN SALAZAR
Smoke Detectors 5/21/2025 Approved RYAN SALAZAR