9815 N PENFIELD AVE 91311
Certificate Information: 9815 N PENFIELD AVE 91311
- Application / Permit
- 24014-20000-04652
- Plan Check / Job No.
- B24VN20089
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan: SINGLE STORY RESIDENTIAL ADDITION AND REMODEL TO INCLUDE 44 SQ. FT. LAUNDRY ROOM ADDITION TO FRONT OF HOUSE, 114 SQ. FT. ADDITION TO REAR OF HOUSE, CONVERT 408 SQ. FT. OF EXISTING ATTACHED GARAGE TO HABITABLE SPACE AND ADD 339 SQ. FT. OF NEW ATTACHED GARAGE TO REMAINING PORTION OF EXISTING GARAGE.
- Permit Issued
- Issued on 2/10/2025
- Issuing Office
- Current Status
- CofO Issued on 4/10/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/17/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/22/2024 | MINA HABILI |
| Corrections Issued | 10/23/2024 | MINA HABILI |
| Applicant returned to address corrections | 1/29/2025 | MINA HABILI |
| Applicant returned to address corrections | 2/4/2025 | ISIS ARGUETA |
| Plan Check Approved | 2/9/2025 | ISIS ARGUETA |
| Issued | 2/10/2025 | APPLICANT |
| CofO in Progress | 4/10/2026 | JACK KARGODORIAN |
| Permit Finaled | 4/10/2026 | JOHN JANSON |
| CofO Issued | 4/10/2026 | JOHN JANSON |
| Permit Finaled | 4/10/2026 | JOHN JANSON |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 1/10/2025 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 1/14/2025 | RYAN CASTRO |
| Sewer availability | Cleared | 1/14/2025 | RYAN CASTRO |
Contact Information
| Architect | Gelfat,, James Evan; Lic. No.: NA19847 | , |
| Contractor | Owner-Builder | , |
| Engineer | Resnick,, Bruce Daniel; Lic. No.: NA3293 | , |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/20/2025 | Partial Approval | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 6/2/2025 | Partial Approval | JEFFREY HARTLINE |
| Green Building Rough | 6/2/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 6/16/2025 | Partial Approval | KRISTEN CAUSEY |
| PLUMBING-Rough | 6/20/2025 | Not Ready for Inspection | KRISTEN CAUSEY |
| Footing/Foundation/Slab | 9/18/2025 | Approved | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 10/30/2025 | Approved | DAVID SCANTLIN |
| PLUMBING-Rough | 10/30/2025 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 12/5/2025 | Approved | DAVID SCANTLIN |
| Green Building Rough | 12/5/2025 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 12/5/2025 | Partial Approval | DAVID SCANTLIN |
| Insulation | 12/16/2025 | Approved | DAVID SCANTLIN |
| Shower Pan | 12/16/2025 | Approved | DAVID SCANTLIN |
| Drywall Nailing | 12/24/2025 | Approved | DAVID SCANTLIN |
| Final | 3/31/2026 | Corrections Issued | JACK KARGODORIAN |
| Green Building Final | 3/31/2026 | Not Ready for Inspection | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 3/31/2026 | SGSOV Approved | JACK KARGODORIAN |
| Smoke Detectors | 3/31/2026 | Approved | JACK KARGODORIAN |
| Final | 4/9/2026 | OK to Issue CofO | JACK KARGODORIAN |
| Green Building Final | 4/9/2026 | Approved | JACK KARGODORIAN |