4500 N CALHOUN AVE 91423
Certificate Information: 4500 N CALHOUN AVE 91423
- Application / Permit
- 24014-20000-04637
- Plan Check / Job No.
- B24VN19988
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMOVE ALL EXTERIOR AND INTERIOR WALLS OF AN EXISTING ONE STORY DWELLING EXCEPT FOR 3 LINEAR FT AT WEST PORTION OF THE LOT AND BUILD 69'11-3/4" X 38' TWO STORY DWELLING WITH ATTACHED TWO CAR GARAGE , NFPA-13D FIRE SPRINKLERS REQUIRED THROUGHOUT, ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 1/6/2025
- Issuing Office
- Current Status
- CofO Issued on 9/5/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/16/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/17/2024 | RARES BODEA |
| Corrections Issued | 10/22/2024 | RARES BODEA |
| Quality Review Completed | 10/22/2024 | STEVEN KIM |
| Building Plans Picked Up | 10/23/2024 | APPLICANT |
| Plan Check Approved | 1/6/2025 | RARES BODEA |
| Issued | 1/6/2025 | APPLICANT |
| CofO in Progress | 8/20/2025 | RAUL OLAGI |
| CofO Issued | 9/5/2025 | RUBEN SALAS |
| Permit Finaled | 9/5/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Permit | Cleared | 10/21/2024 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 10/21/2024 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 10/22/2024 | LEE GUILBEAUX |
| Sewer availability | Cleared | 10/22/2024 | LEE GUILBEAUX |
| Low Impact Development (LID) | Cleared | 10/24/2024 | SARAH YOUSSEF |
| ZI | Cleared | 10/30/2024 | DORIAN AGUILAR |
| Roof/Waste drainage to street | Cleared | 11/14/2024 | BIAINA HARITUNIAN |
| Trees in Parkway | Cleared | 11/14/2024 | MIGUEL ORNELAS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 2/19/2025 | Conditional Approval | ROBERT GOLD |
| Excavation/Setback/Form/Re-Bar | 2/19/2025 | Approved | JACK KARGODORIAN |
| Underground Mechanical | 2/19/2025 | Approved | JACK KARGODORIAN |
| Excavation/Setback/Form/Re-Bar | 2/20/2025 | Partial Inspection | MISAEL ESPARZA |
| Sewer | 2/20/2025 | Approved | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 2/24/2025 | Approved | MISAEL ESPARZA |
| Footing/Foundation/Slab | 2/24/2025 | Approved | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 3/5/2025 | Partial Approval | MISAEL ESPARZA |
| Deputy Steel/Welding | 3/17/2025 | Conditional Approval | JUAN VALENZUELA |
| Deputy Wood Construction | 3/18/2025 | Conditional Approval | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 3/19/2025 | Corrections Issued | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 3/21/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 3/26/2025 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 4/1/2025 | Corrections Issued | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2025 | Order to Comply Issued | MISAEL ESPARZA |
| HVAC-Rough | 4/1/2025 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 4/1/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Rough | 4/2/2025 | Conditional Approval | MISAEL ESPARZA |
| HVAC-Rough | 4/2/2025 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 4/2/2025 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Rough | 4/3/2025 | Corrections Issued | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 4/3/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Rough | 4/3/2025 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 4/3/2025 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Rough | 4/4/2025 | Approved | MISAEL ESPARZA |
| HVAC-Rough | 4/4/2025 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 4/4/2025 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 4/9/2025 | Corrections Issued | MISAEL ESPARZA |
| Green Building Rough | 4/9/2025 | Approved | MISAEL ESPARZA |
| MERV13>=Rough | 4/9/2025 | Approved | MISAEL ESPARZA |
| Shower Pan | 4/10/2025 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 4/15/2025 | Partial Approval | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 4/21/2025 | Approved | JUAN VALENZUELA |
| Verify Sprinkler Sign Off | 4/21/2025 | Approved | JUAN VALENZUELA |
| Insulation | 4/23/2025 | Approved | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 4/23/2025 | Approved | MICHAEL CORTEZ |
| Insulation | 4/24/2025 | Not Ready for Inspection | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 4/24/2025 | Approved | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 4/25/2025 | No Access for Inspection | JAVIER RAMOS JR |
| Drywall Nailing | 4/28/2025 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 7/18/2025 | SGSOV Not Ready | MISAEL ESPARZA |
| ELECTRICAL-Final | 8/1/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Final | 8/1/2025 | Corrections Issued | MISAEL ESPARZA |
| HVAC-Final | 8/6/2025 | Approved | MISAEL ESPARZA |
| PLUMBING-Final | 8/6/2025 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Final | 8/8/2025 | Corrections Issued | MISAEL ESPARZA |
| HVAC-Final | 8/8/2025 | Approved | MISAEL ESPARZA |
| PLUMBING-Final | 8/8/2025 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Final | 8/12/2025 | Approved | MISAEL ESPARZA |
| Final | 8/14/2025 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 8/14/2025 | Approved | MISAEL ESPARZA |
| MERV13>=Final | 8/14/2025 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 8/14/2025 | SGSOV Approved | MISAEL ESPARZA |
| Smoke Detectors | 8/14/2025 | Approved | MISAEL ESPARZA |
| Final | 8/15/2025 | OK to Issue CofO | MISAEL ESPARZA |