6052 N EL ESCORPION ROAD 91367
Certificate Information: 6052 N EL ESCORPION ROAD 91367
- Application / Permit
- 24014-20000-04624
- Plan Check / Job No.
- B24VN19899
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: 483 SF ADDITION TO AND INTERIOR REMODEL TO (E) SFD, ALL WORK PER ENG NFPA -13D FIRE SPRINKLERES REQUIRED THROUGH OUT
- Permit Issued
- Issued on 11/7/2024
- Issuing Office
- Current Status
- Issued on 11/7/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/16/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/21/2024 | LUISANGEL VALENZUELA |
| Corrections Issued | 10/22/2024 | LUISANGEL VALENZUELA |
| Plan Check Approved | 11/5/2024 | LUISANGEL VALENZUELA |
| Issued | 11/7/2024 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/25/2024 | RYAN CASTRO |
| Roof/Waste drainage to street | Cleared | 10/25/2024 | RYAN CASTRO |
| Sewer availability | Cleared | 10/25/2024 | RYAN CASTRO |
| Grading Pre-Inspection | Cleared | 10/25/2024 | CHARLES POWELL |
| GPI Written Notices | Cleared | 11/4/2024 | LUISANGEL VALENZUELA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mirpoor,, Waheed Ahmad; Lic. No.: C94801 | 555 ROSEWOOD AVE APT#308 CAMARILLO, CA 93010 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/28/2025 | Approved | TROY SANDERS |
| Footing/Foundation/Slab | 4/28/2025 | Approved | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 5/14/2025 | Partial Approval | TROY SANDERS |
| PLUMBING-Rough | 5/19/2025 | Partial Approval | TROY SANDERS |
| Deputy Wood Construction | 6/27/2025 | Conditional Approval | TROY SANDERS |
| ELECTRICAL-Rough | 8/27/2025 | Approved | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 8/27/2025 | Partial Approval | TROY SANDERS |
| PLUMBING-Rough | 8/27/2025 | Approved | TROY SANDERS |
| Service/Power Release | 8/27/2025 | Approved | TROY SANDERS |
| HVAC-Rough | 9/11/2025 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 9/24/2025 | Approved | TROY SANDERS |
| Drywall Nailing | 10/1/2025 | Approved | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 10/1/2025 | Partial Approval | ARUTYUN MADATYAN |
| Shower Pan | 10/21/2025 | Approved | TROY SANDERS |