11314 N HAYVENHURST AVE 91344
Certificate Information: 11314 N HAYVENHURST AVE 91344
- Application / Permit
- 24014-20000-04569
- Plan Check / Job No.
- B24VN19608
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 5'X15'1-1/2" BATHRM & CLOSET, AND 11'3"X6' CLOSET ADDITIONS. ALL WORK PER WFPP.
- Permit Issued
- Issued on 12/18/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/6/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/11/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/18/2024 | HAYATO TSUCHIYA |
| Corrections Issued | 10/19/2024 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 10/22/2024 | APPLICANT |
| Plan Check Approved | 12/13/2024 | YAQUB MIRZA |
| Issued | 12/18/2024 | APPLICANT |
| CofO in Progress | 5/1/2025 | NICHOLAS TROWBRIDGE |
| Permit Finaled | 5/6/2025 | RUBEN SALAS |
| CofO Issued | 5/6/2025 | RUBEN SALAS |
| Permit Finaled | 5/6/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 10/31/2024 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 11/5/2024 | RYAN CASTRO |
| Grading Pre-Inspection | Cleared | 12/6/2024 | MANUEL TEJADA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/20/2024 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 1/27/2025 | Approved | KEVIN BERBERYAN |
| PLUMBING-Rough | 1/27/2025 | Partial Approval | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 2/24/2025 | Approved | RAUL OLAGI |
| ELECTRICAL-Rough | 2/24/2025 | Approved | RAUL OLAGI |
| Green Building Rough | 2/24/2025 | Not Ready for Inspection | RAUL OLAGI |
| MERV13>=Rough | 2/24/2025 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 2/24/2025 | Approved | RAUL OLAGI |
| Insulation | 2/28/2025 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 2/28/2025 | Partial Approval | JAVIER RAMOS JR |
| Shower Pan | 2/28/2025 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 3/7/2025 | Approved | CHRISTOPHE COCHRAN |
| Green Building Rough | 3/7/2025 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 3/7/2025 | Approved | CHRISTOPHE COCHRAN |
| Final | 4/15/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Final | 4/15/2025 | Approved | CHRISTOPHER ROJAS |
| MERV13>=Final | 4/15/2025 | Approved | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 4/15/2025 | SGSOV Approved | CHRISTOPHER ROJAS |
| Smoke Detectors | 4/15/2025 | Partial Inspection | CHRISTOPHER ROJAS |
| Final | 4/23/2025 | OK to Issue CofO | NICHOLAS TROWBRIDGE |
| Smoke Detectors | 4/23/2025 | Approved | NICHOLAS TROWBRIDGE |