11314 N HAYVENHURST AVE 91344

Certificate Information: 11314 N HAYVENHURST AVE 91344

Application / Permit
24014-20000-04569
Plan Check / Job No.
B24VN19608
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 5'X15'1-1/2" BATHRM & CLOSET, AND 11'3"X6' CLOSET ADDITIONS. ALL WORK PER WFPP.
Permit Issued
Issued on 12/18/2024
Issuing Office
Valley
Current Status
CofO Issued on 5/6/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/11/2024 APPLICANT
Assigned to Plan Check Engineer 10/18/2024 HAYATO TSUCHIYA
Corrections Issued 10/19/2024 HAYATO TSUCHIYA
Building Plans Picked Up 10/22/2024 APPLICANT
Plan Check Approved 12/13/2024 YAQUB MIRZA
Issued 12/18/2024 APPLICANT
CofO in Progress 5/1/2025 NICHOLAS TROWBRIDGE
Permit Finaled 5/6/2025 RUBEN SALAS
CofO Issued 5/6/2025 RUBEN SALAS
Permit Finaled 5/6/2025 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 10/31/2024 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 11/5/2024 RYAN CASTRO
Grading Pre-Inspection Cleared 12/6/2024 MANUEL TEJADA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/20/2024 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 1/27/2025 Approved KEVIN BERBERYAN
PLUMBING-Rough 1/27/2025 Partial Approval KEVIN BERBERYAN
BUILDING-Rough-Frame 2/24/2025 Approved RAUL OLAGI
ELECTRICAL-Rough 2/24/2025 Approved RAUL OLAGI
Green Building Rough 2/24/2025 Not Ready for Inspection RAUL OLAGI
MERV13>=Rough 2/24/2025 Approved RAUL OLAGI
PLUMBING-Rough 2/24/2025 Approved RAUL OLAGI
Insulation 2/28/2025 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 2/28/2025 Partial Approval JAVIER RAMOS JR
Shower Pan 2/28/2025 Approved JAVIER RAMOS JR
Drywall Nailing 3/7/2025 Approved CHRISTOPHE COCHRAN
Green Building Rough 3/7/2025 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 3/7/2025 Approved CHRISTOPHE COCHRAN
Final 4/15/2025 Corrections Issued CHRISTOPHER ROJAS
Green Building Final 4/15/2025 Approved CHRISTOPHER ROJAS
MERV13>=Final 4/15/2025 Approved CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 4/15/2025 SGSOV Approved CHRISTOPHER ROJAS
Smoke Detectors 4/15/2025 Partial Inspection CHRISTOPHER ROJAS
Final 4/23/2025 OK to Issue CofO NICHOLAS TROWBRIDGE
Smoke Detectors 4/23/2025 Approved NICHOLAS TROWBRIDGE