7433-7435 N RANCHITO AVE 91405
Certificate Information: 7433-7435 N RANCHITO AVE 91405
- Application / Permit
- 24014-20000-04562
- Plan Check / Job No.
- B24VN19536
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- REMOVE 1835' OF (E) SFD EXCEPT FOR 5'-9" OF WALL AND FOUNDATION. REBUILD 34'-9" X 50' 2-STORY IRREGULAR SHAPED DUPLEX PER SB 9. NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 12/20/2024
- Issuing Office
- Current Status
- CofO Issued on 10/2/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/10/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/17/2024 | RAPHAEL ROSAS |
| Corrections Issued | 10/22/2024 | RAPHAEL ROSAS |
| Quality Review Completed | 10/22/2024 | STEVEN KIM |
| Building Plans Picked Up | 10/22/2024 | APPLICANT |
| Applicant returned to address corrections | 12/13/2024 | RAPHAEL ROSAS |
| Plan Check Approved | 12/19/2024 | RAPHAEL ROSAS |
| Issued | 12/20/2024 | APPLICANT |
| CofO in Progress | 9/15/2025 | VINCENT HANLEY |
| CofO Issued | 10/2/2025 | RUBEN SALAS |
| Permit Finaled | 10/2/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 10/23/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 10/24/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 10/24/2024 | CARLOS AGUILERA |
| Low Impact Development (LID) | Cleared | 10/29/2024 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 10/29/2024 | CARLOS AGUILERA |
| Senate Bill 9 | Cleared | 10/31/2024 | NATHAN ROMINE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/13/2025 | Conditional Approval | RAUL OLAGI |
| Excavation/Setback/Form/Re-Bar | 1/14/2025 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 1/14/2025 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 1/22/2025 | Partial Approval | VINCENT HANLEY |
| PLUMBING-Rough | 1/22/2025 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 1/27/2025 | Partial Approval | VINCENT HANLEY |
| Insulation | 1/27/2025 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 2/4/2025 | Partial Approval | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/19/2025 | Partial Approval | VINCENT HANLEY |
| BUILDING-Rough-Frame | 3/20/2025 | Corrections Issued | VINCENT HANLEY |
| ELECTRICAL-Rough | 3/20/2025 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 3/20/2025 | Corrections Issued | VINCENT HANLEY |
| Green Building Rough | 3/20/2025 | Approved | VINCENT HANLEY |
| HVAC-Rough | 3/20/2025 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 3/20/2025 | Approved | VINCENT HANLEY |
| Wood Frame | 3/20/2025 | Corrections Issued | VINCENT HANLEY |
| BUILDING-Rough-Frame | 4/2/2025 | Partial Approval | VINCENT HANLEY |
| Insulation | 4/2/2025 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 4/2/2025 | Approved | VINCENT HANLEY |
| Shower Pan | 4/2/2025 | Approved | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 4/2/2025 | Approved | VINCENT HANLEY |
| Drywall Nailing | 4/7/2025 | Approved | JACK KARGODORIAN |
| Sewer | 6/20/2025 | Approved | VINCENT HANLEY |
| Underground Mechanical | 6/20/2025 | Approved | VINCENT HANLEY |
| Verify Rec and Parks Fee Memo | 6/20/2025 | Partial Approval | VINCENT HANLEY |
| BUILDING-Rough-Frame | 8/28/2025 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 8/28/2025 | Approved | VINCENT HANLEY |
| Final | 8/28/2025 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 8/28/2025 | Approved | VINCENT HANLEY |
| HVAC-Final | 8/28/2025 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 8/28/2025 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 8/28/2025 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 8/28/2025 | Approved | VINCENT HANLEY |
| Final | 9/15/2025 | OK to Issue CofO | VINCENT HANLEY |