Application / Permit
24014-20000-04562
Plan Check / Job No.
B24VN19536
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
REMOVE 1835' OF (E) SFD EXCEPT FOR 5'-9" OF WALL AND FOUNDATION. REBUILD 34'-9" X 50' 2-STORY IRREGULAR SHAPED DUPLEX PER SB 9. NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 12/20/2024
Issuing Office
Current Status
CofO Issued on 10/2/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/10/2024 APPLICANT
Assigned to Plan Check Engineer 10/17/2024 RAPHAEL ROSAS
Corrections Issued 10/22/2024 RAPHAEL ROSAS
Quality Review Completed 10/22/2024 STEVEN KIM
Building Plans Picked Up 10/22/2024 APPLICANT
Applicant returned to address corrections 12/13/2024 RAPHAEL ROSAS
Plan Check Approved 12/19/2024 RAPHAEL ROSAS
Issued 12/20/2024 APPLICANT
CofO in Progress 9/15/2025 VINCENT HANLEY
CofO Issued 10/2/2025 RUBEN SALAS
Permit Finaled 10/2/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 10/23/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 10/24/2024 CARLOS AGUILERA
Sewer availability Cleared 10/24/2024 CARLOS AGUILERA
Low Impact Development (LID) Cleared 10/29/2024 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 10/29/2024 CARLOS AGUILERA
Senate Bill 9 Cleared 10/31/2024 NATHAN ROMINE

Contact Information

Contractor Owner-Builder       ,
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/13/2025 Conditional Approval RAUL OLAGI
Excavation/Setback/Form/Re-Bar 1/14/2025 Approved VINCENT HANLEY
Footing/Foundation/Slab 1/14/2025 Approved VINCENT HANLEY
BUILDING-Rough-Frame 1/22/2025 Partial Approval VINCENT HANLEY
PLUMBING-Rough 1/22/2025 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 1/27/2025 Partial Approval VINCENT HANLEY
Insulation 1/27/2025 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 2/4/2025 Partial Approval MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 2/19/2025 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 3/20/2025 Corrections Issued VINCENT HANLEY
ELECTRICAL-Rough 3/20/2025 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 3/20/2025 Corrections Issued VINCENT HANLEY
Green Building Rough 3/20/2025 Approved VINCENT HANLEY
HVAC-Rough 3/20/2025 Approved VINCENT HANLEY
PLUMBING-Rough 3/20/2025 Approved VINCENT HANLEY
Wood Frame 3/20/2025 Corrections Issued VINCENT HANLEY
BUILDING-Rough-Frame 4/2/2025 Partial Approval VINCENT HANLEY
Insulation 4/2/2025 Approved VINCENT HANLEY
Interior/Exterior Lathing 4/2/2025 Approved VINCENT HANLEY
Shower Pan 4/2/2025 Approved VINCENT HANLEY
Verify Sprinkler Sign Off 4/2/2025 Approved VINCENT HANLEY
Drywall Nailing 4/7/2025 Approved JACK KARGODORIAN
Sewer 6/20/2025 Approved VINCENT HANLEY
Underground Mechanical 6/20/2025 Approved VINCENT HANLEY
Verify Rec and Parks Fee Memo 6/20/2025 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 8/28/2025 Approved VINCENT HANLEY
ELECTRICAL-Final 8/28/2025 Approved VINCENT HANLEY
Final 8/28/2025 Corrections Issued VINCENT HANLEY
Green Building Final 8/28/2025 Approved VINCENT HANLEY
HVAC-Final 8/28/2025 Approved VINCENT HANLEY
PLUMBING-Final 8/28/2025 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 8/28/2025 SGSOV Approved VINCENT HANLEY
Smoke Detectors 8/28/2025 Approved VINCENT HANLEY
Final 9/15/2025 OK to Issue CofO VINCENT HANLEY