7961-7963 N BALBOA BLVD 91406

Certificate Information: 7961-7963 N BALBOA BLVD 91406

Application / Permit
24014-20000-04548
Plan Check / Job No.
B24VN19437
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
ePlan Exisiting SFD with attached covered patio and attached 2 car garage to be converted to a duplex per SB9 Two unit developement. Garage to remain. Portion of covered patio to be converted to living space.
Permit Issued
Issued on 1/6/2025
Issuing Office
Current Status
Issued on 1/6/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/11/2024 APPLICANT
Assigned to Plan Check Engineer 10/24/2024 MARCELA FRANQUEZ
Corrections Issued 10/30/2024 MARCELA FRANQUEZ
Quality Review Completed 11/6/2024 TU HUA
Applicant returned to address corrections 11/26/2024 MARCELA FRANQUEZ
Plan Check Approved 12/27/2024 MARCELA FRANQUEZ
Issued 1/6/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 11/5/2024 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 11/6/2024 RYAN CASTRO
Sewer availability Cleared 11/15/2024 RYAN CASTRO
Senate Bill 9 Cleared 12/2/2024 JACQUELINE TORRES

Contact Information

Contractor Adu Rc Builders; Lic. No.: 1080967-B       ,
Contractor Ca Construction Group Inc; Lic. No.: 1080967-B       ,
Engineer Arutyunyan,, Vladimir; Lic. No.: NA92714       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/13/2025 Partial Approval RAUL OLAGI
Sewer 5/13/2025 Approved RAUL OLAGI
Footing/Foundation/Slab 6/9/2025 Corrections Issued SALVADOR MARTINEZ
Excavation/Setback/Form/Re-Bar 6/20/2025 Corrections Issued JAVIER RAMOS JR
Footing/Foundation/Slab 6/20/2025 Corrections Issued JAVIER RAMOS JR
Deputy Drilled-In Anchors 6/23/2025 Conditional Approval JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 10/6/2025 Not Ready for Inspection GAREN HAYRAPETYAN
HVAC-Rough 10/6/2025 Not Ready for Inspection GAREN HAYRAPETYAN
PLUMBING-Rough 10/6/2025 Not Ready for Inspection GAREN HAYRAPETYAN
BUILDING-Rough-Frame 10/28/2025 Not Ready for Inspection GAREN HAYRAPETYAN
ELECTRICAL-Rough 10/28/2025 Not Ready for Inspection GAREN HAYRAPETYAN
Green Building Rough 10/28/2025 Not Ready for Inspection GAREN HAYRAPETYAN
HVAC-Rough 10/28/2025 Not Ready for Inspection GAREN HAYRAPETYAN
PLUMBING-Rough 10/28/2025 Corrections Issued GAREN HAYRAPETYAN
Footing/Foundation/Slab 11/7/2025 Approved GAREN HAYRAPETYAN
BUILDING-Rough-Frame 11/12/2025 Corrections Issued GAREN HAYRAPETYAN
ELECTRICAL-Rough 11/12/2025 Corrections Issued GAREN HAYRAPETYAN
Floor/Roof Diaphrgm/Shear Wall 11/12/2025 Corrections Issued GAREN HAYRAPETYAN
Green Building Rough 11/12/2025 Not Ready for Inspection GAREN HAYRAPETYAN
HVAC-Rough 11/12/2025 Corrections Issued GAREN HAYRAPETYAN
PLUMBING-Rough 11/12/2025 Corrections Issued GAREN HAYRAPETYAN
BUILDING-Rough-Frame 11/20/2025 Not Ready for Inspection WAYNE REGESTER
ELECTRICAL-Rough 11/20/2025 Not Ready for Inspection WAYNE REGESTER
Green Building Rough 11/20/2025 Not Ready for Inspection WAYNE REGESTER
HVAC-Rough 11/20/2025 Not Ready for Inspection WAYNE REGESTER
PLUMBING-Rough 11/20/2025 Not Ready for Inspection WAYNE REGESTER
BUILDING-Rough-Frame 12/19/2025 Approved Pending GreenApproval GAREN HAYRAPETYAN
ELECTRICAL-Rough 12/19/2025 Conditional Approval GAREN HAYRAPETYAN
Green Building Rough 12/19/2025 Not Ready for Inspection GAREN HAYRAPETYAN
HVAC-Rough 12/19/2025 Approved GAREN HAYRAPETYAN
PLUMBING-Rough 12/19/2025 Conditional Approval GAREN HAYRAPETYAN
Drywall Nailing 1/20/2026 Partial Approval VINCENT HANLEY
Insulation 1/20/2026 Approved VINCENT HANLEY
Interior/Exterior Lathing 1/20/2026 Approved VINCENT HANLEY
Shower Pan 1/20/2026 Approved VINCENT HANLEY
Drywall Nailing 2/2/2026 Approved MICHAEL CORTEZ