3464 W GARDEN AVE 90039
Certificate Information: 3464 W GARDEN AVE 90039
- Application / Permit
- 24014-20000-04540
- Plan Check / Job No.
- B24VN19381
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD 11'-10" x 55'-8"IRREGULAR SHAPED TWO STORY TO AND REMODEL EXISTING SINGLE FAMILY DWELLING; ADD 1-CAR GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 1/27/2025
- Issuing Office
- Current Status
- Issued on 1/27/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/9/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/17/2024 | SELLA BENYAMIN |
| Corrections Issued | 10/24/2024 | SELLA BENYAMIN |
| Quality Review Completed | 10/24/2024 | STEVEN KIM |
| Building Plans Picked Up | 11/4/2024 | APPLICANT |
| Plan Check Approved | 1/23/2025 | SELLA BENYAMIN |
| Issued | 1/27/2025 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 12/30/2024 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/11/2025 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 1/11/2025 | ADRIAN SANCHEZ |
Contact Information
| Contractor | Opus Builders Inc; Lic. No.: 1059646-B | 5244 VINELAND AVENUE NORTH HOLLYWOOD, CA 91601 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Pre-Inspection | 6/8/2026 |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/14/2025 | Approved | NICHOLAS LOPEZ |
| Footing/Foundation/Slab | 4/14/2025 | Approved | NICHOLAS LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/29/2025 | Partial Approval | NICHOLAS LOPEZ |
| PLUMBING-Rough | 4/29/2025 | Partial Approval | NICHOLAS LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/1/2025 | Approved | NICHOLAS LOPEZ |
| Wood Frame | 7/2/2025 | Partial Approval | NICHOLAS LOPEZ |
| Underground Mechanical | 8/29/2025 | Approved | NICHOLAS LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 9/4/2025 | Approved | NICHOLAS LOPEZ |
| BUILDING-Rough-Frame | 9/24/2025 | Approved | NICHOLAS LOPEZ |
| ELECTRICAL-Rough | 9/24/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Green Building Rough | 9/24/2025 | Approved | NICHOLAS LOPEZ |
| HVAC-Rough | 9/24/2025 | Approved | NICHOLAS LOPEZ |
| Interior/Exterior Lathing | 9/24/2025 | Partial Approval | NICHOLAS LOPEZ |
| PLUMBING-Rough | 9/24/2025 | Approved | NICHOLAS LOPEZ |
| Insulation | 10/9/2025 | Approved | NICHOLAS LOPEZ |
| Underground Mechanical | 10/9/2025 | Approved | NICHOLAS LOPEZ |
| Drywall Nailing | 10/21/2025 | Approved | NICHOLAS LOPEZ |
| Interior/Exterior Lathing | 10/21/2025 | Approved | NICHOLAS LOPEZ |
| Shower Pan | 10/21/2025 | Approved | NICHOLAS LOPEZ |
| Final | 5/29/2026 | Not Ready for Inspection | CRAIG VAUGHAN |
| Green Building Final | 5/29/2026 | Not Ready for Inspection | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 5/29/2026 | SGSOV Not Ready | CRAIG VAUGHAN |
| Smoke Detectors | 5/29/2026 | Not Ready for Inspection | CRAIG VAUGHAN |
| Final | 6/5/2026 | Corrections Issued | NICHOLAS LOPEZ |
| Green Building Final | 6/5/2026 | Approved | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 6/5/2026 | SGSOV Approved | NICHOLAS LOPEZ |
| Smoke Detectors | 6/5/2026 | Approved | NICHOLAS LOPEZ |