4026 W GARDEN AVE 90039
Certificate Information: 4026 W GARDEN AVE 90039
- Application / Permit
- 24014-20000-04525
- Plan Check / Job No.
- B24VN19219
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT EXISTING DUPLEX TO NEW SINGLE FAMILY DWELLING AND ADD 31'-6" X 29' TO ENLARGE SFD; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 2/27/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/19/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/8/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/10/2024 | SELLA BENYAMIN |
| Corrections Issued | 10/17/2024 | SELLA BENYAMIN |
| Quality Review Completed | 10/24/2024 | STEVEN KIM |
| Building Plans Picked Up | 10/28/2024 | APPLICANT |
| Plan Check Approved | 2/27/2025 | SELLA BENYAMIN |
| Issued | 2/27/2025 | APPLICANT |
| CofO in Progress | 11/18/2025 | NICHOLAS LOPEZ |
| Permit Finaled | 11/19/2025 | DEROLD HAUFF |
| CofO Issued | 11/19/2025 | DEROLD HAUFF |
| Permit Finaled | 11/19/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 11/7/2024 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 11/12/2024 | CELINA MORENO |
| Sewer availability | Cleared | 11/12/2024 | CELINA MORENO |
| Address approval | Cleared | 11/13/2024 | CELINA MORENO |
| Demo/Removal of Rental Units | Cleared | 1/7/2025 | RUZENKA BENEDETTO |
| Tenant Habitability Plan | Cleared | 1/7/2025 | RICARDO BOHORQUEZ |
| SB8 RUD | Cleared | 2/21/2025 | ASHLEY MEDINA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Tangonan,, Jeffrey Tolentino; Lic. No.: C83522 | 17770 CAPE JASMINE RD CANYON COUNTRY, CA 91387 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/7/2025 | Partial Inspection | NICHOLAS LOPEZ |
| Underground Mechanical | 3/20/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| Deputy Drilled-In Anchors | 3/24/2025 | Conditional Approval | NICHOLAS LOPEZ |
| Excavation/Setback/Form/Re-Bar | 3/24/2025 | Approved | NICHOLAS LOPEZ |
| Footing/Foundation/Slab | 3/24/2025 | Approved | NICHOLAS LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/7/2025 | Partial Approval | NICHOLAS LOPEZ |
| Deputy Wood Construction | 4/9/2025 | Conditional Approval | NICHOLAS LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/9/2025 | Partial Approval | NICHOLAS LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/7/2025 | Conditional Approval | NICHOLAS LOPEZ |
| Deputy Wood Construction | 5/12/2025 | Conditional Approval | NICHOLAS LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/13/2025 | Approved | NICHOLAS LOPEZ |
| BUILDING-Rough-Frame | 6/5/2025 | Approved | NICHOLAS LOPEZ |
| Green Building Rough | 6/5/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Rough-Elec/Plmb/HVAC | 6/5/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Interior/Exterior Lathing | 6/11/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| Rough-Elec/Plmb/HVAC | 6/11/2025 | Approved | NICHOLAS LOPEZ |
| Gas Test | 6/12/2025 | Approved | NICHOLAS LOPEZ |
| Green Building Rough | 6/12/2025 | Approved | NICHOLAS LOPEZ |
| Interior/Exterior Lathing | 6/12/2025 | Partial Approval | NICHOLAS LOPEZ |
| Sewer | 6/12/2025 | Approved | NICHOLAS LOPEZ |
| Underground Mechanical | 6/12/2025 | Approved | NICHOLAS LOPEZ |
| Insulation | 6/23/2025 | Approved | REGINA MENDEZ |
| Drywall Nailing | 6/30/2025 | Approved | REGINA MENDEZ |
| Shower Pan | 7/8/2025 | Approved | ANTHONY RAMOS |
| Interior/Exterior Lathing | 7/15/2025 | Approved | NICHOLAS LOPEZ |
| Service/Power Release | 9/19/2025 | Corrections Issued | NICHOLAS LOPEZ |
| ELECTRICAL-Final | 10/9/2025 | Corrections Issued | NICHOLAS LOPEZ |
| HVAC-Final | 10/9/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| PLUMBING-Final | 10/9/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| Service/Power Release | 10/9/2025 | Not Required | NICHOLAS LOPEZ |
| ELECTRICAL-Final | 11/14/2025 | Approved | NICHOLAS LOPEZ |
| Final | 11/14/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Green Building Final | 11/14/2025 | Approved | NICHOLAS LOPEZ |
| HVAC-Final | 11/14/2025 | Approved | NICHOLAS LOPEZ |
| PLUMBING-Final | 11/14/2025 | Approved | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 11/14/2025 | SGSOV Not Ready | NICHOLAS LOPEZ |
| Smoke Detectors | 11/14/2025 | Approved | NICHOLAS LOPEZ |
| Final | 11/18/2025 | OK to Issue CofO | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 11/18/2025 | SGSOV Approved | NICHOLAS LOPEZ |