5210 E GRANADA ST 90042
Certificate Information: 5210 E GRANADA ST 90042
- Application / Permit
- 24014-20000-04517
- Plan Check / Job No.
- B24VN19174
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED INT/EXT REMODEL WITH ADDITIONS: @ 2ND FLR - 11' X 9'7" ADDITION TO EXPAND EX DINING AREA, NEW VAULTED CEILING/ROOF OVER THE ADDN & EX BEDROOM PER PLAN. ENCLOSE FRONT 7'9" X 4'10" PORCH. @ 1ST FLR - PROPOSED 11' X 9"7" REC RM ADDITION (NOT INTER-CONNECTED).
- Permit Issued
- Issued on 2/3/2025
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 3/7/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/8/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/16/2024 | HAYATO TSUCHIYA |
| Corrections Issued | 10/16/2024 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 10/18/2024 | APPLICANT |
| Plan Check Approved | 1/30/2025 | GIOVANNY CHAVEZ |
| Issued | 2/3/2025 | APPLICANT |
| CofO in Progress | 3/5/2026 | NICHOLAS LOPEZ |
| No Progress | 3/5/2026 | CHARLES BOGHOSKHAN |
| CofO in Progress | 3/5/2026 | CHARLES BOGHOSKHAN |
| Permit Finaled | 3/7/2026 | DEROLD HAUFF |
| CofO Issued | 3/7/2026 | DEROLD HAUFF |
| Permit Finaled | 3/7/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| CPC | Cleared | 10/22/2024 | BRENNEN OBETO |
| Miscellaneous | Cleared | 10/22/2024 | BRENNEN OBETO |
| Roof/Waste drainage to street | Cleared | 10/25/2024 | ABEL CASILLAS |
| Eng Process Fee Ord 176,300 | Cleared | 10/29/2024 | ABEL CASILLAS |
| HPOZ | Cleared | 1/14/2025 | NATHALY DE LA PAZ |
| ZI | Cleared | 1/14/2025 | NATHALY DE LA PAZ |
| Grading Pre-Inspection | Cleared | 1/30/2025 | MICHAEL TEMPLE |
Contact Information
| Contractor | High Touch Inc; Lic. No.: 860365-B | 10917 WEST PICO BOULEVARD LOS ANGELES, CA 90064 |
| Engineer | Nirattisai,, Preston; Lic. No.: C85115 | 28411 ASCENT WAY SANTA CLARITA, CA 91350 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/4/2025 | Conditional Approval | NICHOLAS LOPEZ |
| Excavation/Setback/Form/Re-Bar | 6/9/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Deputy Drilled-In Anchors | 6/26/2025 | Conditional Approval | REGINA MENDEZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/28/2025 | Conditional Approval | NICHOLAS LOPEZ |
| Deputy Wood Construction | 7/29/2025 | Conditional Approval | NICHOLAS LOPEZ |
| Deputy Wood Construction | 8/7/2025 | Conditional Approval | NICHOLAS LOPEZ |
| BUILDING-Rough-Frame | 8/29/2025 | Approved | NICHOLAS LOPEZ |
| ELECTRICAL-Rough | 8/29/2025 | Approved | NICHOLAS LOPEZ |
| Green Building Rough | 8/29/2025 | Approved | NICHOLAS LOPEZ |
| HVAC-Rough | 8/29/2025 | Approved | NICHOLAS LOPEZ |
| Interior/Exterior Lathing | 8/29/2025 | Partial Approval | NICHOLAS LOPEZ |
| PLUMBING-Rough | 8/29/2025 | Approved | NICHOLAS LOPEZ |
| Insulation | 9/9/2025 | No Access for Inspection | REGINA MENDEZ |
| Insulation | 9/17/2025 | Corrections Issued | ANTHONY RAMOS |
| Insulation | 9/26/2025 | Approved | GEM DE OCAMPO |
| Drywall Nailing | 10/6/2025 | Approved | NICHOLAS LOPEZ |
| Interior/Exterior Lathing | 10/17/2025 | Approved | REGINA MENDEZ |
| Shower Pan | 10/17/2025 | Approved | REGINA MENDEZ |
| Footing/Foundation/Slab | 2/18/2026 | Approved | NICHOLAS LOPEZ |
| Green Building Final | 2/18/2026 | Not Ready for Inspection | NICHOLAS LOPEZ |
| Pre-Inspection | 2/18/2026 | Partial Inspection | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 2/18/2026 | SGSOV Not Ready | NICHOLAS LOPEZ |
| Smoke Detectors | 2/18/2026 | Not Ready for Inspection | NICHOLAS LOPEZ |
| Final | 2/26/2026 | Corrections Issued | NICHOLAS LOPEZ |
| Green Building Final | 2/26/2026 | Not Ready for Inspection | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 2/26/2026 | SGSOV Approved | NICHOLAS LOPEZ |
| Smoke Detectors | 2/26/2026 | Approved | NICHOLAS LOPEZ |
| Final | 3/4/2026 | OK to Issue CofO | NICHOLAS LOPEZ |
| Green Building Final | 3/4/2026 | Approved | NICHOLAS LOPEZ |