222 E 65TH ST 90003

Certificate Information: 222 E 65TH ST 90003

Application / Permit
24014-20000-04502
Plan Check / Job No.
B24VN19104
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: NEW ADU PER STATE LAW. Design per WFPP.
Permit Issued
Issued on 2/24/2025
Issuing Office
Current Status
CofO in Progress on 6/4/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/8/2024 APPLICANT
Assigned to Plan Check Engineer 10/11/2024 CAROLEAN BASMA
Corrections Issued 10/12/2024 CAROLEAN BASMA
Applicant returned to address corrections 12/4/2024 AMY GUEVARRA
Applicant returned to address corrections 12/12/2024 NGHI SU
Applicant returned to address corrections 1/9/2025 NGHI SU
Applicant returned to address corrections 1/10/2025 NGHI SU
Applicant returned to address corrections 1/17/2025 NGHI SU
Applicant returned to address corrections 1/24/2025 NGHI SU
Plan Check Approved 1/31/2025 NGHI SU
Issued 2/24/2025 APPLICANT
CofO in Progress 6/4/2026 RAUL BARAJAS
CofO in Progress 6/5/2026 RAUL BARAJAS

Permit Application Clearance Information

Address approval Cleared 11/6/2024 CELINA MORENO
Roof/Waste drainage to street Cleared 11/6/2024 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 11/12/2024 CELINA MORENO
Sewer availability Cleared 11/12/2024 CELINA MORENO
Community Plan Implem. Overlay Cleared 1/24/2025 ANACANY HURTADO

Contact Information

Contractor D & A Home Renovations; Lic. No.: 808672-B       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/4/2025 Corrections Issued JOHN QUINTANILLA
Underground Mechanical 3/4/2025 Approved JOHN QUINTANILLA
Footing/Foundation/Slab 4/7/2025 Not Ready for Inspection JOHN QUINTANILLA
Footing/Foundation/Slab 4/15/2025 Approved JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 4/29/2025 Approved JOHN QUINTANILLA
ELECTRICAL-Rough 5/9/2025 Corrections Issued JOHN QUINTANILLA
PLUMBING-Rough 5/9/2025 Corrections Issued JOHN QUINTANILLA
Wood Frame 5/9/2025 Not Ready for Inspection JOHN QUINTANILLA
BUILDING-Rough-Frame 5/13/2025 Not Ready for Inspection JOHN QUINTANILLA
Green Building Rough 5/13/2025 Not Ready for Inspection JOHN QUINTANILLA
Interior/Exterior Lathing 5/13/2025 Not Ready for Inspection JOHN QUINTANILLA
Verify Sprinkler Sign Off 5/13/2025 Approved JOHN QUINTANILLA
Interior/Exterior Lathing 5/16/2025 Approved JOHN QUINTANILLA
ELECTRICAL-Rough 5/21/2025 Approved JOHN QUINTANILLA
PLUMBING-Rough 5/21/2025 Approved JOHN QUINTANILLA
BUILDING-Rough-Frame 5/23/2025 Approved JOHN QUINTANILLA
HVAC-Rough 5/23/2025 Approved JOHN QUINTANILLA
Insulation 5/27/2025 Not Ready for Inspection JOHN QUINTANILLA
Insulation 5/30/2025 Approved JOHN QUINTANILLA
Drywall Nailing 6/6/2025 Approved JOHN QUINTANILLA
BUILDING-Rough-Frame 8/15/2025 Approved JOHN QUINTANILLA
Final 8/15/2025 Corrections Issued JOHN QUINTANILLA
Green Building Rough 8/15/2025 Approved JOHN QUINTANILLA
Green Building Final 8/21/2025 Not Ready for Inspection BRENDAN MORELLI
PLUMBING-Final 8/21/2025 Approved BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 8/21/2025 SGSOV No Gas BRENDAN MORELLI
Service/Power Release 8/21/2025 Not Ready for Inspection BRENDAN MORELLI
Smoke Detectors 8/21/2025 Approved BRENDAN MORELLI
Final 8/27/2025 Not Ready for Inspection JOHN QUINTANILLA
Green Building Final 8/27/2025 Not Ready for Inspection JOHN QUINTANILLA
Service/Power Release 8/27/2025 Not Ready for Inspection JOHN QUINTANILLA
Final 9/4/2025 Conditional Approval JOHN QUINTANILLA
Green Building Final 9/4/2025 Approved JOHN QUINTANILLA
Service/Power Release 9/4/2025 Approved JOHN QUINTANILLA
Final 6/4/2026 Not Ready for Inspection RAUL BARAJAS
Final 6/5/2026 Corrections Issued RAUL BARAJAS