10337 W ROSCOE BLVD 91352
Certificate Information: 10337 W ROSCOE BLVD 91352
- Application / Permit
- 24014-20000-04501
- Plan Check / Job No.
- B24VN19102
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 21'4"X19'2" 2ND FLOOR ADDITION AND CONVERT (E) ADU INTO AN SB 9 UNIT
- Permit Issued
- Issued on 8/11/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/29/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/8/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/17/2024 | MARVEL DELACRUZ |
| Corrections Issued | 10/22/2024 | MARVEL DELACRUZ |
| Quality Review Completed | 10/24/2024 | JASON HEALEY |
| Building Plans Picked Up | 10/25/2024 | APPLICANT |
| Applicant returned to address corrections | 2/24/2025 | MARVEL DELACRUZ |
| Plan Check Approved | 8/11/2025 | MARVEL DELACRUZ |
| Issued | 8/11/2025 | APPLICANT |
| CofO in Progress | 4/25/2026 | DAVID ANDERSON |
| Permit Finaled | 5/29/2026 | RUBEN SALAS |
| CofO Issued | 5/29/2026 | RUBEN SALAS |
| Permit Finaled | 5/29/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 11/18/2024 | BIAINA HARITUNIAN |
| BHO/Hillside ordinance | Cleared | 11/18/2024 | BIAINA HARITUNIAN |
| BHO/Hillside ordinance | Cleared | 11/18/2024 | BIAINA HARITUNIAN |
| BHO/Hillside ordinance | Cleared | 11/18/2024 | BIAINA HARITUNIAN |
| BHO/Hillside ordinance | Cleared | 11/18/2024 | BIAINA HARITUNIAN |
| BHO/Hillside ordinance | Cleared | 11/18/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 11/18/2024 | BIAINA HARITUNIAN |
| Construction near power lines | Cleared | 12/18/2024 | GEVORK KARAPETYAN |
| Construction within easement | Cleared | 12/18/2024 | GEVORK KARAPETYAN |
| Sewer availability | Cleared | 12/24/2024 | BIAINA HARITUNIAN |
| Distance to fire station | Cleared | 2/18/2025 | KURT CORRAL |
| Eng Process Fee Ord 176,300 | Cleared | 2/18/2025 | BIAINA HARITUNIAN |
| Hydrant and Access approval | Cleared | 2/18/2025 | KURT CORRAL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Papazyan,, Andranik Karapet; Lic. No.: C56824 | 1015 VISTA GRANDE ST BURBANK, CA 91501 |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/20/2025 | Approved | DAVID ANDERSON |
| Pre-Inspection | 9/19/2025 | Partial Inspection | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/7/2025 | Corrections Issued | DAVID ANDERSON |
| Wood Frame | 10/7/2025 | Not Ready for Inspection | DAVID ANDERSON |
| ELECTRICAL-Rough | 10/15/2025 | Not Ready for Inspection | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/15/2025 | Not Ready for Inspection | DAVID ANDERSON |
| PLUMBING-Rough | 10/15/2025 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 10/28/2025 | Not Ready for Inspection | DAVID ANDERSON |
| ELECTRICAL-Rough | 10/28/2025 | Approved | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/28/2025 | Partial Approval | DAVID ANDERSON |
| Green Building Rough | 10/28/2025 | Approved | DAVID ANDERSON |
| HVAC-Rough | 10/28/2025 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 10/28/2025 | Partial Approval | DAVID ANDERSON |
| MERV13>=Rough | 10/28/2025 | Approved | DAVID ANDERSON |
| Special/Order Compliance | 10/28/2025 | Corrections Issued | DAVID ANDERSON |
| Verify Sprinkler Sign Off | 10/28/2025 | Corrections Issued | DAVID ANDERSON |
| Insulation | 12/5/2025 | Partial Approval | MATTHEW NELSON |
| BUILDING-Rough-Frame | 12/9/2025 | Approved | DAVID ANDERSON |
| Drywall Nailing | 12/9/2025 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 12/9/2025 | Approved | DAVID ANDERSON |
| Verify Sprinkler Sign Off | 12/9/2025 | Approved | DAVID ANDERSON |
| ELECTRICAL-Final | 2/10/2026 | Approved | DAVID ANDERSON |
| Final | 2/10/2026 | Corrections Issued | DAVID ANDERSON |
| Green Building Final | 2/10/2026 | Not Ready for Inspection | DAVID ANDERSON |
| MERV13>=Final | 2/10/2026 | Approved | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 2/10/2026 | SGSOV Approved | DAVID ANDERSON |
| Smoke Detectors | 2/10/2026 | Approved | DAVID ANDERSON |
| Final | 3/6/2026 | Not Ready for Inspection | DAVID ANDERSON |
| Footing/Foundation/Slab | 3/6/2026 | Approved | DAVID ANDERSON |
| Green Building Final | 3/6/2026 | Approved | DAVID ANDERSON |
| Final | 4/24/2026 | OK to Issue CofO | DAVID ANDERSON |