11368 N ACALA AVE 91340

Certificate Information: 11368 N ACALA AVE 91340

Application / Permit
24014-20000-04416
Plan Check / Job No.
B24VN18578
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan: CONVERT (E) 20'x20' DETACHED GARAGE WITH 18'6" x 15' ADDITION TO NEW DETACHED ACCESSORY DWELLIMG UNIT PER PER LAMC 12.22 A.33(c) AND (d).
Permit Issued
Issued on 11/27/2024
Issuing Office
Current Status
CofO Issued on 4/24/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/4/2024 APPLICANT
Assigned to Plan Check Engineer 10/9/2024 MIROOSH KHACHATOORIAN
Corrections Issued 10/10/2024 MIROOSH KHACHATOORIAN
Applicant returned to address corrections 11/13/2024 MIROOSH KHACHATOORIAN
Applicant returned to address corrections 11/22/2024 AMY GUEVARRA
Plan Check Approved 11/26/2024 AMY GUEVARRA
Issued 11/27/2024 APPLICANT
CofO in Progress 4/16/2025 JENNIFER RABUCHIN
Permit Finaled 4/24/2025 RUBEN SALAS
CofO Issued 4/24/2025 RUBEN SALAS
Permit Finaled 4/24/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 10/13/2024 RYAN CASTRO
Roof/Waste drainage to street Cleared 10/13/2024 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 10/17/2024 RYAN CASTRO
Sewer availability Cleared 10/17/2024 RYAN CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/9/2024 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 12/9/2024 Partial Approval JENNIFER RABUCHIN
Sewer 12/9/2024 Approved JENNIFER RABUCHIN
Deputy Drilled-In Anchors 12/11/2024 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 12/13/2024 Partial Approval JENNIFER RABUCHIN
Deputy Drilled-In Anchors 12/17/2024 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 12/19/2024 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 12/30/2024 Corrections Issued JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 12/30/2024 Approved JENNIFER RABUCHIN
Footing/Foundation/Slab 12/30/2024 Approved JENNIFER RABUCHIN
PLUMBING-Rough 12/30/2024 Corrections Issued JENNIFER RABUCHIN
Wood Frame 12/30/2024 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 1/7/2025 Approved JOSE AVILA
HVAC-Rough 1/7/2025 Approved JOSE AVILA
Interior/Exterior Lathing 1/7/2025 Approved JOSE AVILA
PLUMBING-Rough 1/7/2025 Approved JOSE AVILA
BUILDING-Rough-Frame 1/10/2025 Approved JENNIFER RABUCHIN
Green Building Rough 1/10/2025 Approved JENNIFER RABUCHIN
MERV13>=Rough 1/10/2025 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 1/14/2025 Corrections Issued JENNIFER RABUCHIN
Insulation 1/14/2025 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 1/14/2025 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 1/28/2025 Approved JENNIFER RABUCHIN
Drywall Nailing 1/28/2025 Approved JENNIFER RABUCHIN
Gas Test 1/28/2025 Partial Approval JENNIFER RABUCHIN
Interior/Exterior Lathing 1/28/2025 Approved JENNIFER RABUCHIN
Shower Pan 1/28/2025 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 3/18/2025 SGSOV Not Ready JENNIFER RABUCHIN
Final 4/10/2025 Corrections Issued KEVIN BERBERYAN
Green Building Final 4/10/2025 Not Ready for Inspection KEVIN BERBERYAN
MERV13>=Final 4/10/2025 Approved KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 4/10/2025 SGSOV Approved KEVIN BERBERYAN
Smoke Detectors 4/10/2025 Approved KEVIN BERBERYAN
ELECTRICAL-Final 4/15/2025 Approved JENNIFER RABUCHIN
Final 4/15/2025 OK to Issue CofO JENNIFER RABUCHIN
Green Building Final 4/15/2025 Approved JENNIFER RABUCHIN
HVAC-Final 4/15/2025 Approved JENNIFER RABUCHIN
PLUMBING-Final 4/15/2025 Approved JENNIFER RABUCHIN