11368 N ACALA AVE 91340
Certificate Information: 11368 N ACALA AVE 91340
- Application / Permit
- 24014-20000-04416
- Plan Check / Job No.
- B24VN18578
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan: CONVERT (E) 20'x20' DETACHED GARAGE WITH 18'6" x 15' ADDITION TO NEW DETACHED ACCESSORY DWELLIMG UNIT PER PER LAMC 12.22 A.33(c) AND (d).
- Permit Issued
- Issued on 11/27/2024
- Issuing Office
- Current Status
- CofO Issued on 4/24/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/4/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/9/2024 | MIROOSH KHACHATOORIAN |
| Corrections Issued | 10/10/2024 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 11/13/2024 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 11/22/2024 | AMY GUEVARRA |
| Plan Check Approved | 11/26/2024 | AMY GUEVARRA |
| Issued | 11/27/2024 | APPLICANT |
| CofO in Progress | 4/16/2025 | JENNIFER RABUCHIN |
| Permit Finaled | 4/24/2025 | RUBEN SALAS |
| CofO Issued | 4/24/2025 | RUBEN SALAS |
| Permit Finaled | 4/24/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 10/13/2024 | RYAN CASTRO |
| Roof/Waste drainage to street | Cleared | 10/13/2024 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 10/17/2024 | RYAN CASTRO |
| Sewer availability | Cleared | 10/17/2024 | RYAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/9/2024 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 12/9/2024 | Partial Approval | JENNIFER RABUCHIN |
| Sewer | 12/9/2024 | Approved | JENNIFER RABUCHIN |
| Deputy Drilled-In Anchors | 12/11/2024 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 12/13/2024 | Partial Approval | JENNIFER RABUCHIN |
| Deputy Drilled-In Anchors | 12/17/2024 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 12/19/2024 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 12/30/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 12/30/2024 | Approved | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 12/30/2024 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 12/30/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Wood Frame | 12/30/2024 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 1/7/2025 | Approved | JOSE AVILA |
| HVAC-Rough | 1/7/2025 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 1/7/2025 | Approved | JOSE AVILA |
| PLUMBING-Rough | 1/7/2025 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 1/10/2025 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 1/10/2025 | Approved | JENNIFER RABUCHIN |
| MERV13>=Rough | 1/10/2025 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 1/14/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Insulation | 1/14/2025 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 1/14/2025 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 1/28/2025 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 1/28/2025 | Approved | JENNIFER RABUCHIN |
| Gas Test | 1/28/2025 | Partial Approval | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 1/28/2025 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 1/28/2025 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 3/18/2025 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Final | 4/10/2025 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Final | 4/10/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| MERV13>=Final | 4/10/2025 | Approved | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 4/10/2025 | SGSOV Approved | KEVIN BERBERYAN |
| Smoke Detectors | 4/10/2025 | Approved | KEVIN BERBERYAN |
| ELECTRICAL-Final | 4/15/2025 | Approved | JENNIFER RABUCHIN |
| Final | 4/15/2025 | OK to Issue CofO | JENNIFER RABUCHIN |
| Green Building Final | 4/15/2025 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 4/15/2025 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 4/15/2025 | Approved | JENNIFER RABUCHIN |