17457 W BURTON ST 91325

Certificate Information: 17457 W BURTON ST 91325

Application / Permit
24014-20000-04414
Plan Check / Job No.
B24VN18540
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION OF A CLOSET AND DEN WITH A HALF BATHROOM TO THE (E) SFD.
Permit Issued
Issued on 10/10/2024
Issuing Office
Current Status
CofO in Progress on 3/4/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/2/2024 APPLICANT
Assigned to Plan Check Engineer 10/2/2024 MOHAMMAD ESMAILI
Corrections Issued 10/2/2024 MOHAMMAD ESMAILI
Plan Check Approved 10/10/2024 ALEC MOUSAKHANIAN
Issued 10/10/2024 APPLICANT
CofO in Progress 3/4/2026 KIRK SANDERS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/8/2024 CARLOS RAMIREZ
Roof/Waste drainage to street Cleared 10/8/2024 CARLOS RAMIREZ

Contact Information

Contractor We The People Construction Inc; Lic. No.: 1076924-B 5352 LAUREL CANYON BLVD # 200      VALLEY VILLAGE, CA 91607

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/27/2024 Partial Approval SALVADOR MARTINEZ
Sewer 11/27/2024 Not Ready for Inspection SALVADOR MARTINEZ
Excavation/Setback/Form/Re-Bar 12/2/2024 Corrections Issued SALVADOR MARTINEZ
Footing/Foundation/Slab 12/2/2024 Corrections Issued SALVADOR MARTINEZ
Deputy Drilled-In Anchors 12/4/2024 Approved RAUL OLAGI
Footing/Foundation/Slab 12/4/2024 Approved RAUL OLAGI
Deputy Drilled-In Anchors 2/20/2025 Conditional Approval RAUL OLAGI
Footing/Foundation/Slab 2/20/2025 Approved SALVADOR MARTINEZ
ELECTRICAL-Rough 2/27/2025 No Access for Inspection SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 2/27/2025 Partial Approval SALVADOR MARTINEZ
BUILDING-Rough-Frame 3/3/2025 No Access for Inspection SALVADOR MARTINEZ
ELECTRICAL-Rough 3/3/2025 No Access for Inspection SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 3/3/2025 No Access for Inspection SALVADOR MARTINEZ
Green Building Rough 3/3/2025 Not Ready for Inspection SALVADOR MARTINEZ
Wood Frame 3/3/2025 No Access for Inspection SALVADOR MARTINEZ
BUILDING-Rough-Frame 3/6/2025 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Rough 3/6/2025 Approved JAVIER RAMOS JR
Green Building Rough 3/6/2025 Approved JAVIER RAMOS JR
HVAC-Rough 3/6/2025 Approved JAVIER RAMOS JR
PLUMBING-Rough 3/6/2025 Approved JAVIER RAMOS JR
Wood Frame 3/6/2025 Partial Inspection JAVIER RAMOS JR
Insulation 3/7/2025 Corrections Issued SALVADOR MARTINEZ
Interior/Exterior Lathing 3/7/2025 Not Ready for Inspection SALVADOR MARTINEZ
Insulation 3/11/2025 Not Ready for Inspection GAREN HAYRAPETYAN
Insulation 3/17/2025 Corrections Issued LOUIS ESCOTO
Interior/Exterior Lathing 3/17/2025 Corrections Issued LOUIS ESCOTO
Floor/Roof Diaphrgm/Shear Wall 3/19/2025 Approved SALVADOR MARTINEZ
Insulation 3/19/2025 Approved SALVADOR MARTINEZ
Interior/Exterior Lathing 3/19/2025 Partial Approval SALVADOR MARTINEZ
Drywall Nailing 3/21/2025 Approved LOUIS ESCOTO
BUILDING-Rough-Frame 9/12/2025 Approved GAREN HAYRAPETYAN
Final 9/12/2025 Corrections Issued GAREN HAYRAPETYAN
Green Building Final 9/12/2025 Not Ready for Inspection GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 9/12/2025 SGSOV Not Ready GAREN HAYRAPETYAN
Smoke Detectors 9/12/2025 Not Ready for Inspection GAREN HAYRAPETYAN
ELECTRICAL-Final 2/26/2026 Approved GAREN HAYRAPETYAN
Final 2/26/2026 Corrections Issued GAREN HAYRAPETYAN
Green Building Final 2/26/2026 Approved GAREN HAYRAPETYAN
HVAC-Final 2/26/2026 Approved GAREN HAYRAPETYAN
PLUMBING-Final 2/26/2026 Approved GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 2/26/2026 SGSOV Approved GAREN HAYRAPETYAN
Smoke Detectors 2/26/2026 Approved GAREN HAYRAPETYAN
ELECTRICAL-Final 3/3/2026 Approved KIRK SANDERS
Final 3/3/2026 OK to Issue CofO KIRK SANDERS
HVAC-Final 3/3/2026 Approved KIRK SANDERS
MERV13>=Final 3/3/2026 Approved KIRK SANDERS
Service/Power Release 3/3/2026 Approved KIRK SANDERS