11122 W LEADWELL ST 91352

Certificate Information: 11122 W LEADWELL ST 91352

Application / Permit
24014-20000-04379
Plan Check / Job No.
B24VN18197
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN CONVERT (E) DETACHED GARAGE AND STORAGE ROOM INTO ADU WITH (N) ADDITION PER LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 11/9/2024
Issuing Office
Current Status
CofO Issued on 8/29/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/1/2024 APPLICANT
Assigned to Plan Check Engineer 10/4/2024 JOHNPAUL ISIP
Corrections Issued 10/8/2024 JOHNPAUL ISIP
Plan Check Approved 11/6/2024 JOHNPAUL ISIP
Issued 11/9/2024 APPLICANT
CofO in Progress 8/20/2025 ROBERTO PALACIOS-LOPEZ
Permit Finaled 8/29/2025 RUBEN SALAS
CofO Issued 8/29/2025 RUBEN SALAS
Permit Finaled 8/29/2025 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 10/19/2024 CARLOS AGUILERA
Address approval Cleared 10/22/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 10/23/2024 CARLOS AGUILERA
Sewer availability Cleared 10/23/2024 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Maalouf,, Sami; Lic. No.: NA53210       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 3/6/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 3/13/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 3/13/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Deputy Drilled-In Anchors 3/19/2025 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 3/21/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 3/25/2025 Approved ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 3/25/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 5/7/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Rough 5/7/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 5/7/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 5/8/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
HVAC-Rough 5/8/2025 Approved ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 5/8/2025 Approved ROBERTO PALACIOS-LOPEZ
Sewer 5/8/2025 Approved ROBERTO PALACIOS-LOPEZ
Underground Mechanical 5/8/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 5/9/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Rough 5/9/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 5/15/2025 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 5/20/2025 Conditional Approval ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 5/20/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 5/22/2025 Approved ROBERTO PALACIOS-LOPEZ
Green Building Rough 5/22/2025 Approved ROBERTO PALACIOS-LOPEZ
Insulation 5/22/2025 Approved ROBERTO PALACIOS-LOPEZ
Underground Mechanical 5/22/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Drywall Nailing 6/2/2025 Approved MICHAEL CORTEZ
Shower Pan 6/2/2025 Corrections Issued MICHAEL CORTEZ
Shower Pan 6/6/2025 Approved MICHAEL CORTEZ
Interior/Exterior Lathing 6/13/2025 Approved ROBERTO PALACIOS-LOPEZ
Final 8/4/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 8/4/2025 Approved ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 8/4/2025 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Smoke Detectors 8/4/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 8/7/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 8/7/2025 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Service/Power Release 8/7/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Smoke Detectors 8/7/2025 Approved ROBERTO PALACIOS-LOPEZ
Final 8/19/2025 OK to Issue CofO ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 8/19/2025 SGSOV Approved ROBERTO PALACIOS-LOPEZ
Service/Power Release 8/19/2025 Approved ROBERTO PALACIOS-LOPEZ