16059-16061 W INDEX ST 91344

Certificate Information: 16059-16061 W INDEX ST 91344

Application / Permit
24014-20000-04371
Plan Check / Job No.
B24VN18108
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
12'-6 X 5' CLOSET ADDITION TO SFD. CONVERT ATTACHED GARAGE TO JUNIOR ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) and 65852.22. ALL WORK PER WFPP
Permit Issued
Issued on 10/17/2024
Issuing Office
Valley
Current Status
CofO Issued on 9/12/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/27/2024 APPLICANT
Assigned to Plan Check Engineer 10/3/2024 JEROME MAGAT PALMA
Corrections Issued 10/5/2024 JEROME MAGAT PALMA
Building Plans Picked Up 10/7/2024 APPLICANT
Plan Check Approved 10/11/2024 ARAMIK SHAHMIRZAIAN
Issued 10/17/2024 APPLICANT
CofO in Progress 9/11/2025 CHRISTOPHER ROJAS
Permit Finaled 9/12/2025 RUBEN SALAS
CofO Issued 9/12/2025 RUBEN SALAS
Permit Finaled 9/12/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 10/9/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 10/9/2024 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 10/9/2024 BIAINA HARITUNIAN
Sewer availability Cleared 10/9/2024 BIAINA HARITUNIAN
Grading Pre-Inspection Cleared 10/11/2024 MANUEL TEJADA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/4/2024 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 11/4/2024 Partial Approval JENNIFER RABUCHIN
Sewer 11/4/2024 Approved JENNIFER RABUCHIN
Footing/Foundation/Slab 11/13/2024 Approved JAVIER RAMOS JR
ELECTRICAL-Rough 11/21/2024 Approved JAVIER RAMOS JR
HVAC-Rough 11/21/2024 Approved JAVIER RAMOS JR
PLUMBING-Rough 11/21/2024 Corrections Issued JAVIER RAMOS JR
BUILDING-Rough-Frame 11/22/2024 Corrections Issued JAVIER RAMOS JR
Green Building Rough 11/22/2024 Not Ready for Inspection JAVIER RAMOS JR
BUILDING-Rough-Frame 12/5/2024 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 12/5/2024 Approved JAVIER RAMOS JR
Green Building Rough 12/5/2024 Approved JAVIER RAMOS JR
Insulation 12/5/2024 Corrections Issued JAVIER RAMOS JR
PLUMBING-Rough 12/5/2024 Approved JAVIER RAMOS JR
Drywall Nailing 12/10/2024 Approved JAVIER RAMOS JR
Insulation 12/10/2024 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 12/10/2024 Approved JAVIER RAMOS JR
Shower Pan 12/10/2024 Approved JAVIER RAMOS JR
Final 4/25/2025 Corrections Issued CHRISTOPHER ROJAS
Green Building Final 4/25/2025 Not Ready for Inspection CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 4/25/2025 SGSOV Approved CHRISTOPHER ROJAS
Smoke Detectors 4/25/2025 Approved CHRISTOPHER ROJAS
Final 7/17/2025 Corrections Issued CHRISTOPHER ROJAS
Green Building Final 7/17/2025 Approved CHRISTOPHER ROJAS
Final 9/9/2025 OK to Issue CofO CHRISTOPHER ROJAS