10941 W WALNUT DR 91040
Certificate Information: 10941 W WALNUT DR 91040
- Application / Permit
- 24014-20000-04341
- Plan Check / Job No.
- B24VN17784
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan REMODEL OF EXISTING 838 SF SFD W/ 513 SF ADDITION
- Permit Issued
- Issued on 6/25/2025
- Issuing Office
- Current Status
- CofO Corrected on 4/21/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/25/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/30/2024 | JOHN MESIAS |
| Corrections Issued | 10/1/2024 | JOHN MESIAS |
| Applicant returned to address corrections | 6/11/2025 | JOHN MESIAS |
| Plan Check Approved | 6/25/2025 | JOHN MESIAS |
| Issued | 6/25/2025 | APPLICANT |
| CofO in Progress | 1/30/2026 | DAVID ANDERSON |
| Permit Finaled-Status Void | 2/10/2026 | RUBEN SALAS |
| CofO Issued-Status Void | 2/10/2026 | RUBEN SALAS |
| Re-Activate Permit | 4/21/2026 | RUBEN SALAS |
| CofO Corrected | 4/21/2026 | RUBEN SALAS |
| Permit Finaled | 4/21/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 10/6/2024 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 10/7/2024 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 10/7/2024 | LEE GUILBEAUX |
| Private sewage disp. approval | Cleared | 11/27/2024 | MICHAEL TEMPLE |
| Specific Plan | Cleared | 6/13/2025 | ALEX VELA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/30/2025 | Not Ready for Inspection | DAVID ANDERSON |
| Footing/Foundation/Slab | 7/30/2025 | Corrections Issued | DAVID ANDERSON |
| Excavation/Setback/Form/Re-Bar | 8/1/2025 | Approved | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/19/2025 | Partial Approval | DAVID ANDERSON |
| Underground Mechanical | 8/19/2025 | Not Ready for Inspection | DAVID ANDERSON |
| PLUMBING-Rough | 8/25/2025 | Partial Approval | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/28/2025 | Partial Approval | DAVID ANDERSON |
| Underground Mechanical | 9/3/2025 | Partial Approval | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/22/2025 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 10/14/2025 | Not Ready for Inspection | DAVID ANDERSON |
| ELECTRICAL-Rough | 10/14/2025 | Corrections Issued | DAVID ANDERSON |
| Green Building Rough | 10/14/2025 | Corrections Issued | DAVID ANDERSON |
| HVAC-Rough | 10/14/2025 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 10/14/2025 | Corrections Issued | DAVID ANDERSON |
| ELECTRICAL-Rough | 10/16/2025 | Approved | DAVID ANDERSON |
| Green Building Rough | 10/16/2025 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 10/16/2025 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 10/17/2025 | Approved | DAVID ANDERSON |
| ELECTRICAL-Rough | 10/17/2025 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 10/17/2025 | Approved | DAVID ANDERSON |
| Insulation | 10/22/2025 | Corrections Issued | DAVID ANDERSON |
| Interior/Exterior Lathing | 10/22/2025 | Partial Approval | DAVID ANDERSON |
| Insulation | 10/30/2025 | Approved | DAVID ANDERSON |
| Drywall Nailing | 11/6/2025 | Approved | LOUIS ESCOTO |
| ELECTRICAL-Final | 11/17/2025 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 11/24/2025 | Approved | DAVID ANDERSON |
| Shower Pan | 11/24/2025 | Approved | DAVID ANDERSON |
| Final | 1/22/2026 | OK to Issue CofO | DAVID ANDERSON |
| Footing/Foundation/Slab | 1/22/2026 | Approved | DAVID ANDERSON |
| Green Building Final | 1/22/2026 | Approved | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 1/22/2026 | SGSOV Approved | DAVID ANDERSON |
| Smoke Detectors | 1/22/2026 | Approved | DAVID ANDERSON |