700-700 1/2 E 50TH ST 90011
Certificate Information: 700-700 1/2 E 50TH ST 90011
- Application / Permit
- 24014-20000-04327
- Plan Check / Job No.
- B24VN17664
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- CONVERT (E) SFD INTO (N) DUPLEX & EXPAND (E) BEDROOM (9'-11" X 5'-1") PER WFPP ** ePlan**
- Permit Issued
- Issued on 11/6/2024
- Issuing Office
- Current Status
- CofO Issued on 5/3/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/26/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/3/2024 | NILOOFAR MEHRAIN |
| Corrections Issued | 10/5/2024 | NILOOFAR MEHRAIN |
| Quality Review Completed | 10/10/2024 | JASON HEALEY |
| Plan Check Approved | 10/23/2024 | NILOOFAR MEHRAIN |
| Issued | 11/6/2024 | APPLICANT |
| CofO in Progress | 4/30/2025 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 5/3/2025 | DEROLD HAUFF |
| CofO Issued | 5/3/2025 | DEROLD HAUFF |
| Permit Finaled | 5/3/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/15/2024 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 10/15/2024 | DAVID LOPEZ |
| Roof/Waste drainage to street | Cleared | 10/15/2024 | DAVID LOPEZ |
| Sewer availability | Cleared | 10/15/2024 | DAVID LOPEZ |
Contact Information
| Contractor | So Cal Construction Enterprises Inc; Lic. No.: 832488-B | , |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/18/2024 | Approved | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 11/18/2024 | Approved | ALEJANDRO DE ARTOLA |
| Deputy Drilled-In Anchors | 11/19/2024 | Approved | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 11/20/2024 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 12/4/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 12/10/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 12/24/2024 | Not Ready for Inspection | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 12/24/2024 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Rough | 12/27/2024 | Corrections Issued | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 12/27/2024 | Partial Approval | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 12/31/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 1/6/2025 | Not Ready for Inspection | BARRY HACHE |
| HVAC-Rough | 1/6/2025 | Not Ready for Inspection | BARRY HACHE |
| PLUMBING-Rough | 1/6/2025 | Approved | BARRY HACHE |
| BUILDING-Rough-Frame | 1/7/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 1/7/2025 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 1/7/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 1/7/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 1/13/2025 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 1/13/2025 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 1/13/2025 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 1/13/2025 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 1/15/2025 | Approved | ALEJANDRO DE ARTOLA |
| Sewer | 1/28/2025 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 2/24/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Service/Power Release | 2/24/2025 | Approved | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 2/24/2025 | Approved | ALEJANDRO DE ARTOLA |
| Gas Test | 2/28/2025 | Approved | MICHAEL LEWIS |
| HVAC-Final | 2/28/2025 | Corrections Issued | MICHAEL LEWIS |
| PLUMBING-Final | 2/28/2025 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Final | 3/4/2025 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Final | 3/4/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 3/4/2025 | Approved | ALEJANDRO DE ARTOLA |
| Final | 4/29/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 4/29/2025 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 4/29/2025 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 4/29/2025 | Approved | ALEJANDRO DE ARTOLA |
| Final | 4/30/2025 | OK to Issue CofO | ALEJANDRO DE ARTOLA |