17144 W CANTLAY ST 91406

Certificate Information: 17144 W CANTLAY ST 91406

Application / Permit
24014-20000-04323
Plan Check / Job No.
B24VN17624
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition to Single Family Residence per engineer design.
Permit Issued
Issued on 11/27/2024
Issuing Office
Current Status
CofO Issued on 11/13/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/3/2024 APPLICANT
Assigned to Plan Check Engineer 10/8/2024 JOHN MESIAS
Corrections Issued 10/9/2024 JOHN MESIAS
Applicant returned to address corrections 11/5/2024 JOHN MESIAS
Plan Check Approved 11/26/2024 NEHEMIAS RAMOS
Issued 11/27/2024 APPLICANT
CofO in Progress 10/22/2025 GAREN HAYRAPETYAN
Permit Finaled 11/13/2025 RUBEN SALAS
CofO Issued 11/13/2025 RUBEN SALAS
Permit Finaled 11/13/2025 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 10/13/2024 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 10/22/2024 RYAN CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/3/2025 Conditional Approval RAUL OLAGI
Excavation/Setback/Form/Re-Bar 2/7/2025 Corrections Issued GAREN HAYRAPETYAN
Footing/Foundation/Slab 2/7/2025 Corrections Issued GAREN HAYRAPETYAN
Excavation/Setback/Form/Re-Bar 2/21/2025 Approved GAREN HAYRAPETYAN
Footing/Foundation/Slab 2/21/2025 Approved GAREN HAYRAPETYAN
BUILDING-Rough-Frame 3/6/2025 Corrections Issued SALVADOR MARTINEZ
Green Building Rough 3/6/2025 Not Ready for Inspection SALVADOR MARTINEZ
Deputy Drilled-In Anchors 3/11/2025 Conditional Approval RAUL OLAGI
BUILDING-Rough-Frame 3/13/2025 Partial Approval SALVADOR MARTINEZ
Green Building Rough 3/13/2025 Not Ready for Inspection SALVADOR MARTINEZ
Insulation 3/17/2025 Partial Approval LOUIS ESCOTO
BUILDING-Rough-Frame 4/18/2025 Corrections Issued NICHOLAS TROWBRIDGE
Floor/Roof Diaphrgm/Shear Wall 4/18/2025 No Access for Inspection NICHOLAS TROWBRIDGE
BUILDING-Rough-Frame 5/14/2025 Corrections Issued SALVADOR MARTINEZ
ELECTRICAL-Rough 5/14/2025 Not Ready for Inspection SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 5/14/2025 Corrections Issued SALVADOR MARTINEZ
Green Building Rough 5/14/2025 Not Ready for Inspection SALVADOR MARTINEZ
HVAC-Rough 5/14/2025 Not Ready for Inspection SALVADOR MARTINEZ
PLUMBING-Rough 5/14/2025 Partial Approval SALVADOR MARTINEZ
Deputy Wood Construction 5/15/2025 Conditional Approval DAVID MATSON
ELECTRICAL-Rough 5/16/2025 Corrections Issued SALVADOR MARTINEZ
HVAC-Rough 5/16/2025 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Rough 5/16/2025 Approved SALVADOR MARTINEZ
BUILDING-Rough-Frame 5/19/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 5/19/2025 Approved ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 5/19/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Green Building Rough 5/19/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
HVAC-Rough 5/19/2025 Approved ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 5/19/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Wood Frame 5/19/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 5/21/2025 Partial Approval GAREN HAYRAPETYAN
BUILDING-Rough-Frame 5/23/2025 Corrections Issued SALVADOR MARTINEZ
Green Building Rough 5/23/2025 Not Ready for Inspection SALVADOR MARTINEZ
BUILDING-Rough-Frame 6/2/2025 Approved JOAQUIN GREENOUGH
Green Building Rough 6/2/2025 Approved JOAQUIN GREENOUGH
Insulation 6/10/2025 Approved RYAN SALAZAR
Interior/Exterior Lathing 6/10/2025 Partial Approval RYAN SALAZAR
Drywall Nailing 6/23/2025 Approved SALVADOR MARTINEZ
Interior/Exterior Lathing 6/23/2025 Approved SALVADOR MARTINEZ
Shower Pan 6/23/2025 Approved SALVADOR MARTINEZ
ELECTRICAL-Final 10/16/2025 Approved GAREN HAYRAPETYAN
Final 10/16/2025 Corrections Issued GAREN HAYRAPETYAN
Green Building Final 10/16/2025 Approved GAREN HAYRAPETYAN
HVAC-Final 10/16/2025 Corrections Issued GAREN HAYRAPETYAN
PLUMBING-Final 10/16/2025 Approved GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 10/16/2025 SGSOV Approved GAREN HAYRAPETYAN
Smoke Detectors 10/16/2025 Approved GAREN HAYRAPETYAN
ELECTRICAL-Final 10/22/2025 Approved GAREN HAYRAPETYAN
Final 10/22/2025 OK to Issue CofO GAREN HAYRAPETYAN
HVAC-Final 10/22/2025 Approved GAREN HAYRAPETYAN
PLUMBING-Final 10/22/2025 Approved GAREN HAYRAPETYAN