23337 W HARTLAND ST 91307
Certificate Information: 23337 W HARTLAND ST 91307
- Application / Permit
- 24014-20000-04311
- Plan Check / Job No.
- B24VN17569
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION AND REMODEL TO EXISTING SFD
- Permit Issued
- Issued on 10/9/2024
- Issuing Office
- Current Status
- CofO Issued on 6/5/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/24/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/27/2024 | NEHEMIAS RAMOS |
| Corrections Issued | 9/28/2024 | NEHEMIAS RAMOS |
| Plan Check Approved | 10/9/2024 | JOSE VELAZQUEZ |
| Issued | 10/9/2024 | APPLICANT |
| CofO in Progress | 5/13/2025 | TROY SANDERS |
| Permit Finaled | 6/5/2025 | JOHN JANSON |
| CofO Issued | 6/5/2025 | JOHN JANSON |
| Permit Finaled | 6/5/2025 | JOHN JANSON |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 10/2/2024 | CARLOS RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 10/3/2024 | CARLOS RAMIREZ |
| Sewer availability | Cleared | 10/3/2024 | CARLOS RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Chatsky,, German; Lic. No.: C84153 | 3876 HUNTERS GROVE CT MOORPARK, CA 93021 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/16/2024 | Partial Approval | TROY SANDERS |
| PLUMBING-Rough | 12/16/2024 | Partial Approval | TROY SANDERS |
| Sewer | 12/16/2024 | Approved | TROY SANDERS |
| Excavation/Setback/Form/Re-Bar | 12/20/2024 | Approved | TROY SANDERS |
| Footing/Foundation/Slab | 12/20/2024 | Approved | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 2/10/2025 | Partial Approval | GEVORK IPCHYAN |
| BUILDING-Rough-Frame | 2/27/2025 | Approved | GEVORK IPCHYAN |
| ELECTRICAL-Rough | 2/27/2025 | Approved | GEVORK IPCHYAN |
| Green Building Rough | 2/27/2025 | Approved | GEVORK IPCHYAN |
| HVAC-Rough | 2/27/2025 | Approved | GEVORK IPCHYAN |
| Interior/Exterior Lathing | 2/27/2025 | Partial Approval | GEVORK IPCHYAN |
| PLUMBING-Rough | 2/27/2025 | Approved | GEVORK IPCHYAN |
| Shower Pan | 2/27/2025 | Approved | GEVORK IPCHYAN |
| Insulation | 3/3/2025 | Approved | TROY SANDERS |
| Drywall Nailing | 3/12/2025 | Approved | TROY SANDERS |
| Final | 5/12/2025 | OK to Issue CofO | TROY SANDERS |
| Green Building Final | 5/12/2025 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 5/12/2025 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 5/12/2025 | Approved | TROY SANDERS |