8546 N AMESTOY AVE 91325
Certificate Information: 8546 N AMESTOY AVE 91325
- Application / Permit
- 24014-20000-04280
- Plan Check / Job No.
- B24VN17393
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Ground floor addition with interior remodel to SFD with att Garage and convert portion of SFD to a Recreation Room.
- Permit Issued
- Issued on 2/6/2025
- Issuing Office
- Current Status
- Issued on 2/6/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/25/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/10/2024 | GEORGE JOLAKIAN |
| Corrections Issued | 10/23/2024 | GEORGE JOLAKIAN |
| Quality Review Completed | 10/24/2024 | RODOLFO ARIAS |
| Plan Check Approved | 2/6/2025 | GEORGE JOLAKIAN |
| Issued | 2/6/2025 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 12/20/2024 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 12/23/2024 | RYAN CASTRO |
| Sewer availability | Cleared | 12/23/2024 | RYAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Aklyan,, Hovhannes; Lic. No.: C95015 | 900 S. FREMONT AVENUE BUILDING & SAFETY DIVISION ALHAMBRA, CA 91803 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/18/2025 | Corrections Issued | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 9/9/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Green Building Rough | 1/22/2026 | Not Ready for Inspection | JACK KARGODORIAN |
| Wood Frame | 1/22/2026 | Corrections Issued | JACK KARGODORIAN |
| Interior/Exterior Lathing | 2/9/2026 | Not Ready for Inspection | KIRK SANDERS |
| Interior/Exterior Lathing | 2/11/2026 | Corrections Issued | RAUL OLAGI |
| Wood Frame | 2/11/2026 | Corrections Issued | RAUL OLAGI |
| Interior/Exterior Lathing | 2/17/2026 | Partial Approval | KIRK SANDERS |
| Wood Frame | 2/17/2026 | Conditional Approval | KIRK SANDERS |
| Insulation | 2/23/2026 | Corrections Issued | KEVIN BERBERYAN |
| Insulation | 3/12/2026 | Approved | JOSE AVILA |
| Drywall Nailing | 3/19/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Rough | 3/19/2026 | Approved | CHRISTOPHER ROJAS |
| Drywall Nailing | 3/25/2026 | Approved | CHRISTOPHER ROJAS |
| Special/Order Compliance | 3/31/2026 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 6/2/2026 | Approved | CHRISTOPHER ROJAS |