7611 N BEN AVE 91605
Certificate Information: 7611 N BEN AVE 91605
- Application / Permit
- 24014-20000-04279
- Plan Check / Job No.
- B24VN17392
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMOVE AND REBUILD 6'-9" X 33'-7" PORTION OF DWELLING; ADD 26 SQ FT COVERED BALCONIES IN FRONT OF DWELLING; REVISE ROOF PITCH AND INCREASE HEIGHT; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 11/21/2024
- Issuing Office
- Current Status
- Issued on 11/21/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/23/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/3/2024 | SELLA BENYAMIN |
| Corrections Issued | 10/10/2024 | SELLA BENYAMIN |
| Quality Review Completed | 10/17/2024 | STEVEN KIM |
| Building Plans Picked Up | 10/18/2024 | APPLICANT |
| Plan Check Approved | 11/21/2024 | SELLA BENYAMIN |
| Issued | 11/21/2024 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 10/15/2024 | CARLOS RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 10/22/2024 | CARLOS RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/14/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Footing/Foundation/Slab | 5/15/2025 | Approved | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Rough | 8/8/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Footing/Foundation/Slab | 8/8/2025 | Approved | NICHOLAS TROWBRIDGE |
| HVAC-Rough | 8/8/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| PLUMBING-Rough | 8/8/2025 | Approved | NICHOLAS TROWBRIDGE |
| Underground Mechanical | 8/8/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| Wood Frame | 8/8/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 9/5/2025 | Corrections Issued | MATTHEW NELSON |
| ELECTRICAL-Rough | 9/5/2025 | Approved | MATTHEW NELSON |
| HVAC-Rough | 9/5/2025 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/9/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 9/24/2025 | Corrections Issued | MATTHEW NELSON |
| Wood Frame | 9/24/2025 | Corrections Issued | MATTHEW NELSON |
| Interior/Exterior Lathing | 10/10/2025 | Partial Approval | DAVID MATSON |
| BUILDING-Rough-Frame | 10/15/2025 | Approved | MATTHEW NELSON |
| Insulation | 10/21/2025 | Approved | MICHAEL CORTEZ |
| Drywall Nailing | 10/30/2025 | Approved | MATTHEW NELSON |
| Shower Pan | 12/12/2025 | Approved | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 12/24/2025 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 3/16/2026 | Approved | JAVIER RAMOS JR |
| Final | 3/16/2026 | Corrections Issued | JAVIER RAMOS JR |
| HVAC-Final | 3/16/2026 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 3/16/2026 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 3/16/2026 | SGSOV Approved | JAVIER RAMOS JR |
| Service/Power Release | 3/16/2026 | Approved | JAVIER RAMOS JR |
| Smoke Detectors | 3/16/2026 | Approved | JAVIER RAMOS JR |