8124 N WHITE OAK AVE 91325
Certificate Information: 8124 N WHITE OAK AVE 91325
- Application / Permit
- 24014-20000-04272
- Plan Check / Job No.
- B24VN17320
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: 2-STORY ACCESSORY DWELLING UNIT ADDITION TO (E) GARAGE PER LAMC 12.22.A.33.(c)-(d)
- Permit Issued
- Issued on 3/14/2025
- Issuing Office
- Current Status
- Issued on 3/14/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/24/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/3/2024 | DANIEL YIP |
| Corrections Issued | 10/7/2024 | DANIEL YIP |
| Quality Review Completed | 10/17/2024 | JOHN FRANCIA |
| Applicant returned to address corrections | 1/8/2025 | DANIEL YIP |
| Applicant returned to address corrections | 1/17/2025 | DANIEL YIP |
| Plan Check Approved | 3/6/2025 | DANIEL YIP |
| Issued | 3/14/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 12/10/2024 | EDGAR ALCARAZ |
| Roof/Waste drainage to street | Cleared | 12/10/2024 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/11/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 12/11/2024 | EDGAR ALCARAZ |
| Construction near power lines | Cleared | 3/5/2025 | GEVORK KARAPETYAN |
Contact Information
| Contractor | Speed Construction And Development Inc; Lic. No.: 1098660-B | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/21/2025 | Partial Approval | JACK KARGODORIAN |
| Deputy Drilled-In Anchors | 4/29/2025 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 5/1/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Excavation/Setback/Form/Re-Bar | 5/5/2025 | Not Ready for Inspection | RYAN SALAZAR |
| Footing/Foundation/Slab | 5/6/2025 | Approved | GAREN HAYRAPETYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/21/2025 | Partial Approval | GAREN HAYRAPETYAN |
| Green Building Rough | 5/21/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Deputy Wood Construction | 6/2/2025 | Conditional Approval | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 6/4/2025 | Approved | SALVADOR MARTINEZ |
| Green Building Rough | 6/4/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 6/10/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Green Building Rough | 6/10/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 6/25/2025 | Partial Inspection | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 6/30/2025 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 6/30/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Wood Frame | 6/30/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 8/5/2025 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 12/8/2025 | Approved | GAREN HAYRAPETYAN |
| HVAC-Rough | 12/8/2025 | Approved | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 12/8/2025 | Partial Approval | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 12/8/2025 | Approved | GAREN HAYRAPETYAN |
| BUILDING-Rough-Frame | 12/10/2025 | Approved | GAREN HAYRAPETYAN |
| Green Building Rough | 12/10/2025 | Approved | GAREN HAYRAPETYAN |
| Insulation | 12/15/2025 | Partial Approval | CHRISTOPHER MORFIN |
| Drywall Nailing | 1/6/2026 | Approved | GAREN HAYRAPETYAN |
| Sewer | 6/5/2026 | Approved | MICHAEL CORTEZ |
| Underground Mechanical | 6/5/2026 | Approved | MICHAEL CORTEZ |