8124 N WHITE OAK AVE 91325

Certificate Information: 8124 N WHITE OAK AVE 91325

Application / Permit
24014-20000-04272
Plan Check / Job No.
B24VN17320
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: 2-STORY ACCESSORY DWELLING UNIT ADDITION TO (E) GARAGE PER LAMC 12.22.A.33.(c)-(d)
Permit Issued
Issued on 3/14/2025
Issuing Office
Current Status
Issued on 3/14/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/24/2024 APPLICANT
Assigned to Plan Check Engineer 10/3/2024 DANIEL YIP
Corrections Issued 10/7/2024 DANIEL YIP
Quality Review Completed 10/17/2024 JOHN FRANCIA
Applicant returned to address corrections 1/8/2025 DANIEL YIP
Applicant returned to address corrections 1/17/2025 DANIEL YIP
Plan Check Approved 3/6/2025 DANIEL YIP
Issued 3/14/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 12/10/2024 EDGAR ALCARAZ
Roof/Waste drainage to street Cleared 12/10/2024 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 12/11/2024 EDGAR ALCARAZ
Sewer availability Cleared 12/11/2024 EDGAR ALCARAZ
Construction near power lines Cleared 3/5/2025 GEVORK KARAPETYAN

Contact Information

Contractor Speed Construction And Development Inc; Lic. No.: 1098660-B       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/21/2025 Partial Approval JACK KARGODORIAN
Deputy Drilled-In Anchors 4/29/2025 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 5/1/2025 Corrections Issued SALVADOR MARTINEZ
Excavation/Setback/Form/Re-Bar 5/5/2025 Not Ready for Inspection RYAN SALAZAR
Footing/Foundation/Slab 5/6/2025 Approved GAREN HAYRAPETYAN
Floor/Roof Diaphrgm/Shear Wall 5/21/2025 Partial Approval GAREN HAYRAPETYAN
Green Building Rough 5/21/2025 Not Ready for Inspection GAREN HAYRAPETYAN
Deputy Wood Construction 6/2/2025 Conditional Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 6/4/2025 Approved SALVADOR MARTINEZ
Green Building Rough 6/4/2025 Not Ready for Inspection SALVADOR MARTINEZ
BUILDING-Rough-Frame 6/10/2025 Not Ready for Inspection SALVADOR MARTINEZ
Green Building Rough 6/10/2025 Not Ready for Inspection SALVADOR MARTINEZ
Interior/Exterior Lathing 6/25/2025 Partial Inspection SALVADOR MARTINEZ
Interior/Exterior Lathing 6/30/2025 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Rough 6/30/2025 Corrections Issued SALVADOR MARTINEZ
Wood Frame 6/30/2025 Not Ready for Inspection SALVADOR MARTINEZ
ELECTRICAL-Rough 8/5/2025 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 12/8/2025 Approved GAREN HAYRAPETYAN
HVAC-Rough 12/8/2025 Approved GAREN HAYRAPETYAN
Interior/Exterior Lathing 12/8/2025 Partial Approval GAREN HAYRAPETYAN
PLUMBING-Rough 12/8/2025 Approved GAREN HAYRAPETYAN
BUILDING-Rough-Frame 12/10/2025 Approved GAREN HAYRAPETYAN
Green Building Rough 12/10/2025 Approved GAREN HAYRAPETYAN
Insulation 12/15/2025 Partial Approval CHRISTOPHER MORFIN
Drywall Nailing 1/6/2026 Approved GAREN HAYRAPETYAN
Sewer 6/5/2026 Approved MICHAEL CORTEZ
Underground Mechanical 6/5/2026 Approved MICHAEL CORTEZ