10656 N NASSAU AVE 91040
Certificate Information: 10656 N NASSAU AVE 91040
- Application / Permit
- 24014-20000-04270
- Plan Check / Job No.
- B24VN17311
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- DEMO PORTION OF GARAGE. ADDITION TO AND CONVERT GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 10/9/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/31/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/20/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/27/2024 | JEROME MAGAT PALMA |
| Corrections Issued | 9/28/2024 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 10/4/2024 | APPLICANT |
| Plan Check Approved | 10/9/2024 | SERGIO MUNIZ |
| Issued | 10/9/2024 | APPLICANT |
| CofO in Progress | 7/11/2025 | DAVID ANDERSON |
| Permit Finaled | 7/31/2025 | RUBEN SALAS |
| CofO Issued | 7/31/2025 | RUBEN SALAS |
| Permit Finaled | 7/31/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 10/1/2024 | CARLOS RAMIREZ |
| Roof/Waste drainage to street | Cleared | 10/1/2024 | CARLOS RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 10/3/2024 | CARLOS RAMIREZ |
| Sewer availability | Cleared | 10/3/2024 | CARLOS RAMIREZ |
| Grading Pre-Inspection | Cleared | 10/4/2024 | MANUEL TEJADA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/3/2025 | Partial Approval | WILLIAM WREN |
| Deputy Drilled-In Anchors | 1/8/2025 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 1/9/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 2/5/2025 | Partial Approval | WILLIAM WREN |
| BUILDING-Rough-Frame | 2/12/2025 | Approved | WILLIAM WREN |
| ELECTRICAL-Rough | 2/12/2025 | Approved | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 2/12/2025 | Approved | WILLIAM WREN |
| Green Building Rough | 2/12/2025 | Approved | WILLIAM WREN |
| HVAC-Rough | 2/12/2025 | Approved | WILLIAM WREN |
| PLUMBING-Rough | 2/12/2025 | Approved | WILLIAM WREN |
| Insulation | 2/25/2025 | Approved | WILLIAM WREN |
| Drywall Nailing | 3/4/2025 | Approved | LOUIS ESCOTO |
| Interior/Exterior Lathing | 3/4/2025 | Approved | LOUIS ESCOTO |
| Interior/Exterior Lathing | 4/4/2025 | Approved | WILLIAM WREN |
| Sewer | 4/4/2025 | Approved | WILLIAM WREN |
| Shower Pan | 4/4/2025 | Approved | WILLIAM WREN |
| Underground Mechanical | 4/4/2025 | Approved | WILLIAM WREN |
| Underground Mechanical | 4/9/2025 | Approved | WILLIAM WREN |
| ELECTRICAL-Final | 6/4/2025 | Not Ready for Inspection | WILLIAM WREN |
| ELECTRICAL-Final | 6/9/2025 | Corrections Issued | DAVID ANDERSON |
| Final | 7/2/2025 | Corrections Issued | DAVID ANDERSON |
| Footing/Foundation/Slab | 7/2/2025 | Approved | DAVID ANDERSON |
| Green Building Final | 7/2/2025 | Not Ready for Inspection | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 7/2/2025 | SGSOV Approved | DAVID ANDERSON |
| Smoke Detectors | 7/2/2025 | Approved | DAVID ANDERSON |
| PLUMBING-Final | 7/7/2025 | Approved | DAVID ANDERSON |
| Final | 7/10/2025 | OK to Issue CofO | DAVID ANDERSON |
| Green Building Final | 7/10/2025 | Approved | DAVID ANDERSON |