13986 W TERRA BELLA ST 91331

Certificate Information: 13986 W TERRA BELLA ST 91331

Application / Permit
24014-20000-04269
Plan Check / Job No.
B24VN17308
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: CONVERT EXISTING GARAGE WITH 2-STORY ADDITION INTO A 2-STORY (36' X 23' IRREGULAR SHAPE) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 12/5/2024
Issuing Office
Current Status
CofO Issued on 7/8/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/23/2024 APPLICANT
Assigned to Plan Check Engineer 10/3/2024 VAHAN JIVALAGIAN
Corrections Issued 10/8/2024 VAHAN JIVALAGIAN
Quality Review Completed 10/10/2024 DAWN MC NULTY
Applicant returned to address corrections 12/2/2024 VAHAN JIVALAGIAN
Plan Check Approved 12/4/2024 VAHAN JIVALAGIAN
Issued 12/5/2024 APPLICANT
CofO in Progress 6/12/2025 VINCENT HANLEY
Permit Finaled 7/8/2025 RUBEN SALAS
CofO Issued 7/8/2025 RUBEN SALAS
Permit Finaled 7/8/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 10/8/2024 RYAN CASTRO
Roof/Waste drainage to street Cleared 10/8/2024 RYAN CASTRO
Construction near power lines Cleared 11/20/2024 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 12/3/2024 RYAN CASTRO
Sewer availability Cleared 12/3/2024 RYAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Shagirian,, Ashot; Lic. No.: C79415 11337 RUNNYMEDE ST      SUN VALLEY, CA 91352

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/8/2025 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 1/8/2025 Partial Approval JENNIFER RABUCHIN
Deputy Drilled-In Anchors 1/13/2025 Conditional Approval RAUL OLAGI
Excavation/Setback/Form/Re-Bar 1/14/2025 Approved VINCENT HANLEY
Footing/Foundation/Slab 1/14/2025 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 1/30/2025 Partial Approval MICHEL ABAJAN
ELECTRICAL-Rough 2/21/2025 Not Ready for Inspection DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 2/21/2025 Approved DAVID ANDERSON
HVAC-Rough 2/21/2025 Corrections Issued DAVID ANDERSON
PLUMBING-Rough 2/21/2025 Approved DAVID ANDERSON
BUILDING-Rough-Frame 2/26/2025 Approved VINCENT HANLEY
ELECTRICAL-Rough 2/26/2025 Approved VINCENT HANLEY
Green Building Rough 2/26/2025 Approved VINCENT HANLEY
HVAC-Rough 2/26/2025 Approved VINCENT HANLEY
Insulation 3/6/2025 Corrections Issued MICHAEL CORTEZ
Interior/Exterior Lathing 3/6/2025 Partial Approval MICHAEL CORTEZ
Drywall Nailing 3/11/2025 Approved LOUIS ESCOTO
Gas Test 3/11/2025 Not Ready for Inspection LOUIS ESCOTO
Insulation 3/11/2025 Approved LOUIS ESCOTO
ELECTRICAL-Final 5/22/2025 Corrections Issued VINCENT HANLEY
Final 5/22/2025 Corrections Issued VINCENT HANLEY
Green Building Final 5/22/2025 Approved VINCENT HANLEY
HVAC-Final 5/22/2025 Corrections Issued VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 5/22/2025 SGSOV Not Ready VINCENT HANLEY
Smoke Detectors 5/22/2025 Approved VINCENT HANLEY
ELECTRICAL-Final 6/11/2025 Approved VINCENT HANLEY
Final 6/11/2025 OK to Issue CofO VINCENT HANLEY
HVAC-Final 6/11/2025 Approved VINCENT HANLEY
PLUMBING-Final 6/11/2025 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 6/11/2025 SGSOV Approved VINCENT HANLEY
Service/Power Release 6/11/2025 Approved VINCENT HANLEY