13986 W TERRA BELLA ST 91331
Certificate Information: 13986 W TERRA BELLA ST 91331
- Application / Permit
- 24014-20000-04269
- Plan Check / Job No.
- B24VN17308
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: CONVERT EXISTING GARAGE WITH 2-STORY ADDITION INTO A 2-STORY (36' X 23' IRREGULAR SHAPE) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 12/5/2024
- Issuing Office
- Current Status
- CofO Issued on 7/8/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/23/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/3/2024 | VAHAN JIVALAGIAN |
| Corrections Issued | 10/8/2024 | VAHAN JIVALAGIAN |
| Quality Review Completed | 10/10/2024 | DAWN MC NULTY |
| Applicant returned to address corrections | 12/2/2024 | VAHAN JIVALAGIAN |
| Plan Check Approved | 12/4/2024 | VAHAN JIVALAGIAN |
| Issued | 12/5/2024 | APPLICANT |
| CofO in Progress | 6/12/2025 | VINCENT HANLEY |
| Permit Finaled | 7/8/2025 | RUBEN SALAS |
| CofO Issued | 7/8/2025 | RUBEN SALAS |
| Permit Finaled | 7/8/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 10/8/2024 | RYAN CASTRO |
| Roof/Waste drainage to street | Cleared | 10/8/2024 | RYAN CASTRO |
| Construction near power lines | Cleared | 11/20/2024 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 12/3/2024 | RYAN CASTRO |
| Sewer availability | Cleared | 12/3/2024 | RYAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Shagirian,, Ashot; Lic. No.: C79415 | 11337 RUNNYMEDE ST SUN VALLEY, CA 91352 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/8/2025 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 1/8/2025 | Partial Approval | JENNIFER RABUCHIN |
| Deputy Drilled-In Anchors | 1/13/2025 | Conditional Approval | RAUL OLAGI |
| Excavation/Setback/Form/Re-Bar | 1/14/2025 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 1/14/2025 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 1/30/2025 | Partial Approval | MICHEL ABAJAN |
| ELECTRICAL-Rough | 2/21/2025 | Not Ready for Inspection | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/21/2025 | Approved | DAVID ANDERSON |
| HVAC-Rough | 2/21/2025 | Corrections Issued | DAVID ANDERSON |
| PLUMBING-Rough | 2/21/2025 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 2/26/2025 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 2/26/2025 | Approved | VINCENT HANLEY |
| Green Building Rough | 2/26/2025 | Approved | VINCENT HANLEY |
| HVAC-Rough | 2/26/2025 | Approved | VINCENT HANLEY |
| Insulation | 3/6/2025 | Corrections Issued | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 3/6/2025 | Partial Approval | MICHAEL CORTEZ |
| Drywall Nailing | 3/11/2025 | Approved | LOUIS ESCOTO |
| Gas Test | 3/11/2025 | Not Ready for Inspection | LOUIS ESCOTO |
| Insulation | 3/11/2025 | Approved | LOUIS ESCOTO |
| ELECTRICAL-Final | 5/22/2025 | Corrections Issued | VINCENT HANLEY |
| Final | 5/22/2025 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 5/22/2025 | Approved | VINCENT HANLEY |
| HVAC-Final | 5/22/2025 | Corrections Issued | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 5/22/2025 | SGSOV Not Ready | VINCENT HANLEY |
| Smoke Detectors | 5/22/2025 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 6/11/2025 | Approved | VINCENT HANLEY |
| Final | 6/11/2025 | OK to Issue CofO | VINCENT HANLEY |
| HVAC-Final | 6/11/2025 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 6/11/2025 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 6/11/2025 | SGSOV Approved | VINCENT HANLEY |
| Service/Power Release | 6/11/2025 | Approved | VINCENT HANLEY |