1362 W 29TH ST 90007
Certificate Information: 1362 W 29TH ST 90007
- Application / Permit
- 24014-20000-04215
- Plan Check / Job No.
- B24VN16984
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- [ePlan] Addition of 2-story ADU to (E) detached garage.
- Permit Issued
- Issued on 2/24/2025
- Issuing Office
- Current Status
- CofO Issued on 10/1/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/18/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/19/2024 | ARSALAN SHABESTARI |
| Corrections Issued | 9/25/2024 | ARSALAN SHABESTARI |
| Quality Review Completed | 10/4/2024 | YOUNG KIM |
| Applicant returned to address corrections | 1/16/2025 | ARSALAN SHABESTARI |
| Plan Check Approved | 2/21/2025 | ARSALAN SHABESTARI |
| Issued | 2/24/2025 | APPLICANT |
| CofO in Progress | 9/26/2025 | WILLIAM SIERRA |
| No Progress | 9/29/2025 | DEROLD HAUFF |
| CofO in Progress | 9/29/2025 | DEROLD HAUFF |
| Permit Finaled | 10/1/2025 | DEROLD HAUFF |
| CofO Issued | 10/1/2025 | DEROLD HAUFF |
| Permit Finaled | 10/1/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| HPOZ | Cleared | 11/19/2024 | ERIK VAN BREENE |
| Specific Plan | Cleared | 11/19/2024 | ERIK VAN BREENE |
| ZI | Cleared | 11/19/2024 | ERIK VAN BREENE |
| Address approval | Cleared | 11/22/2024 | ABEL CASILLAS |
| Roof/Waste drainage to street | Cleared | 11/22/2024 | ABEL CASILLAS |
| Eng Process Fee Ord 176,300 | Cleared | 12/6/2024 | ABEL CASILLAS |
| Sewer availability | Cleared | 12/6/2024 | ABEL CASILLAS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| WILLIAM SIERRA, (213) 202-3122 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| METHANE-Subgrade | 3/28/2025 | Approved | WILLIAM SIERRA |
| PLUMBING-Rough | 3/28/2025 | Partial Approval | WILLIAM SIERRA |
| Excavation/Setback/Form/Re-Bar | 4/4/2025 | Partial Inspection | WILLIAM SIERRA |
| Footing/Foundation/Slab | 4/4/2025 | Partial Inspection | WILLIAM SIERRA |
| METHANE-Barrier | 4/4/2025 | Corrections Issued | WILLIAM SIERRA |
| Excavation/Setback/Form/Re-Bar | 4/8/2025 | Approved | WILLIAM SIERRA |
| METHANE-Barrier | 4/8/2025 | Approved | WILLIAM SIERRA |
| Floor/Roof Diaphrgm/Shear Wall | 4/14/2025 | Partial Approval | WILLIAM SIERRA |
| Floor/Roof Diaphrgm/Shear Wall | 5/21/2025 | Corrections Issued | WILLIAM SIERRA |
| Special/Order Compliance | 5/21/2025 | Partial Inspection | OSVALDO PARAMO |
| HVAC-Rough | 5/29/2025 | Corrections Issued | WILLIAM SIERRA |
| PLUMBING-Rough | 5/29/2025 | Corrections Issued | WILLIAM SIERRA |
| ELECTRICAL-Rough | 5/30/2025 | Corrections Issued | WILLIAM SIERRA |
| Floor/Roof Diaphrgm/Shear Wall | 5/30/2025 | Approved | WILLIAM SIERRA |
| Wood Frame | 5/30/2025 | Partial Inspection | WILLIAM SIERRA |
| BUILDING-Rough-Frame | 6/3/2025 | Partial Approval | WILLIAM SIERRA |
| ELECTRICAL-Rough | 6/3/2025 | Approved | WILLIAM SIERRA |
| HVAC-Rough | 6/3/2025 | Conditional Approval | WILLIAM SIERRA |
| Interior/Exterior Lathing | 6/3/2025 | Partial Approval | WILLIAM SIERRA |
| METHANE-Rough | 6/3/2025 | Corrections Issued | WILLIAM SIERRA |
| PLUMBING-Rough | 6/3/2025 | Approved | WILLIAM SIERRA |
| Insulation | 6/9/2025 | Partial Approval | ALEX COLIN |
| METHANE-Rough | 6/9/2025 | Approved | ALEX COLIN |
| BUILDING-Rough-Frame | 6/12/2025 | Approved | WILLIAM SIERRA |
| Drywall Nailing | 6/12/2025 | Corrections Issued | WILLIAM SIERRA |
| Drywall Nailing | 6/16/2025 | Approved | WILLIAM SIERRA |
| Sewer | 8/1/2025 | Approved | WILLIAM SIERRA |
| ELECTRICAL-Final | 8/8/2025 | Approved | OSVALDO PARAMO |
| Final | 8/8/2025 | Not Ready for Inspection | OSVALDO PARAMO |
| Footing/Foundation/Slab | 8/8/2025 | Approved | OSVALDO PARAMO |
| HVAC-Final | 8/8/2025 | Approved | OSVALDO PARAMO |
| PLUMBING-Final | 8/8/2025 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 8/8/2025 | SGSOV Not Ready | OSVALDO PARAMO |
| Smoke Detectors | 8/8/2025 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Final | 8/12/2025 | Approved | WILLIAM SIERRA |
| HVAC-Final | 8/12/2025 | Approved | WILLIAM SIERRA |
| PLUMBING-Final | 8/12/2025 | Approved | WILLIAM SIERRA |
| Final | 8/13/2025 | Corrections Issued | WILLIAM SIERRA |
| SGSOV-Seismic Gas S/O Valve | 8/13/2025 | SGSOV Not Required | WILLIAM SIERRA |
| ELECTRICAL-Final | 9/25/2025 | Approved | WILLIAM SIERRA |
| Final | 9/25/2025 | OK to Issue CofO | WILLIAM SIERRA |
| HVAC-Final | 9/25/2025 | Approved | WILLIAM SIERRA |
| PLUMBING-Final | 9/25/2025 | Approved | WILLIAM SIERRA |