2495 S GLENCOE AVE 90291

Certificate Information: 2495 S GLENCOE AVE 90291

Application / Permit
24014-20000-04197
Plan Check / Job No.
B24VN16919
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
9.47' X 18'-1" ADDITION TO FRONT OF (E) SFD. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 11/27/2024
Issuing Office
Valley
Current Status
CofO Issued on 7/24/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/18/2024 APPLICANT
Assigned to Plan Check Engineer 9/25/2024 ARAMIK SHAHMIRZAIAN
Corrections Issued 9/25/2024 ARAMIK SHAHMIRZAIAN
Building Plans Picked Up 9/30/2024 APPLICANT
Applicant returned to address corrections 10/22/2024 GIOVANNY CHAVEZ
Plan Check Approved 11/27/2024 ANGELICA MARTINEZ
Issued 11/27/2024 APPLICANT
CofO in Progress 7/23/2025 DAVID FEILER
CofO Issued 7/24/2025 RICHARD STEINBACH
Permit Finaled 7/24/2025 RICHARD STEINBACH

Permit Application Clearance Information

Specific Plan Cleared 10/8/2024 HAMID GHAEMMAGHAMI
Eng Process Fee Ord 176,300 Cleared 10/9/2024 ANTHONY MAINEZ
Specific Plan Cleared 10/9/2024 DAVID URITA
Roof/Waste drainage to street Cleared 10/21/2024 ANTHONY MAINEZ

Contact Information

Contractor My Home Builders Inc; Lic. No.: 1002927-B 20720 VENTURA BLVD 280      WOODLAND HILLS, CA 91364
Engineer Standley,, Craig Erick; Lic. No.: C87675 60 VIA CARATAMA      SAN CLEMENTE, CA 92673

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/3/2025 Approved JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 2/11/2025 Partial Approval JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 2/26/2025 Corrections Issued JESUS PINEDA
Interior/Exterior Lathing 3/17/2025 Partial Approval MICHAEL ALLEN
Interior/Exterior Lathing 3/20/2025 Partial Approval JAYLIN GRAVITTE
BUILDING-Rough-Frame 4/1/2025 Approved MICHAEL ALLEN
ELECTRICAL-Rough 4/1/2025 Approved MICHAEL ALLEN
Floor/Roof Diaphrgm/Shear Wall 4/1/2025 Approved MICHAEL ALLEN
Green Building Rough 4/1/2025 Approved MICHAEL ALLEN
Special/Order Compliance 4/1/2025 Corrections Issued MICHAEL ALLEN
Pre-Inspection 4/15/2025 Corrections Issued MICHAEL ALLEN
Insulation 4/22/2025 Approved MICHAEL ALLEN
Drywall Nailing 4/24/2025 Approved MICHAEL ALLEN
Final 7/7/2025 Corrections Issued MICHAEL ALLEN
Green Building Final 7/7/2025 Approved MICHAEL ALLEN
SGSOV-Seismic Gas S/O Valve 7/7/2025 SGSOV Approved MICHAEL ALLEN
Smoke Detectors 7/7/2025 No Access for Inspection MICHAEL ALLEN
ELECTRICAL-Final 7/17/2025 Approved MICHAEL ALLEN
Final 7/17/2025 Corrections Issued MICHAEL ALLEN
HVAC-Final 7/17/2025 Approved MICHAEL ALLEN
PLUMBING-Final 7/17/2025 Approved MICHAEL ALLEN
Smoke Detectors 7/17/2025 Approved MICHAEL ALLEN
Final 7/23/2025 OK to Issue CofO DAVID FEILER