22134 W VALERIO ST 91303
Certificate Information: 22134 W VALERIO ST 91303
- Application / Permit
- 24014-20000-04194
- Plan Check / Job No.
- B24VN16906
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Addition and convert (E) detached garage and storage to ADU per LAMC
- Permit Issued
- Issued on 11/27/2024
- Issuing Office
- Current Status
- CofO Issued on 7/1/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/18/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/23/2024 | JOSEPH RAFOLS |
| Corrections Issued | 9/24/2024 | JOSEPH RAFOLS |
| Applicant returned to address corrections | 11/6/2024 | NGHI SU |
| Plan Check Approved | 11/13/2024 | SHANGQIN XIE |
| Issued | 11/27/2024 | APPLICANT |
| CofO in Progress | 6/18/2025 | JEFFREY HARTLINE |
| Permit Finaled | 7/1/2025 | JOHN JANSON |
| CofO Issued | 7/1/2025 | JOHN JANSON |
| Permit Finaled | 7/1/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 9/27/2024 | RYAN CASTRO |
| Roof/Waste drainage to street | Cleared | 9/27/2024 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 10/1/2024 | RYAN CASTRO |
| Sewer availability | Cleared | 10/1/2024 | RYAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Tamu,, O C; Lic. No.: C29787 | P O BOX 17083 LONG BEACH, CA 90807 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/7/2025 | Approved | JEFFREY HARTLINE |
| PLUMBING-Rough | 1/7/2025 | Approved | JEFFREY HARTLINE |
| Special/Order Compliance | 1/7/2025 | Corrections Issued | JEFFREY HARTLINE |
| Floor/Roof Diaphrgm/Shear Wall | 1/28/2025 | Partial Approval | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 2/28/2025 | Partial Approval | JEFFREY HARTLINE |
| PLUMBING-Rough | 2/28/2025 | Approved | JEFFREY HARTLINE |
| Underground Mechanical | 2/28/2025 | Partial Approval | JEFFREY HARTLINE |
| ELECTRICAL-Rough | 3/26/2025 | Approved | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 3/26/2025 | Partial Approval | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 4/1/2025 | Approved | JEFFREY HARTLINE |
| Green Building Rough | 4/1/2025 | Approved | JEFFREY HARTLINE |
| HVAC-Rough | 4/1/2025 | Approved | JEFFREY HARTLINE |
| Insulation | 4/8/2025 | Corrections Issued | SCOTT SOBEL |
| Interior/Exterior Lathing | 4/8/2025 | Approved | SCOTT SOBEL |
| Drywall Nailing | 4/15/2025 | Approved | JEFFREY HARTLINE |
| Insulation | 4/15/2025 | Approved | JEFFREY HARTLINE |
| ELECTRICAL-Final | 5/23/2025 | Approved | JEFFREY HARTLINE |
| Final | 5/23/2025 | Corrections Issued | JEFFREY HARTLINE |
| SGSOV-Seismic Gas S/O Valve | 5/23/2025 | SGSOV Approved | JEFFREY HARTLINE |
| Smoke Detectors | 5/23/2025 | Approved | JEFFREY HARTLINE |
| Final | 6/17/2025 | OK to Issue CofO | JEFFREY HARTLINE |
| Green Building Final | 6/17/2025 | Approved | JEFFREY HARTLINE |
| HVAC-Final | 6/17/2025 | Approved | JEFFREY HARTLINE |
| PLUMBING-Final | 6/17/2025 | Approved | JEFFREY HARTLINE |
| Service/Power Release | 6/17/2025 | Approved | JEFFREY HARTLINE |