283-285 E 50TH ST 90011
Certificate Information: 283-285 E 50TH ST 90011
- Application / Permit
- 24014-20000-04190
- Plan Check / Job No.
- B24VN16859
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- ePlan: MAJOR ADDITON AND REMODEL TO (E) DUPLEX TO RECREATE (N) 3-STORY DUPLEX. FIRE SPRINKLER 13D THROUGH OUT.
- Permit Issued
- Issued on 5/20/2025
- Issuing Office
- Current Status
- CofO Issued on 4/30/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/18/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/19/2024 | DANIEL YIP |
| Corrections Issued | 9/21/2024 | DANIEL YIP |
| Quality Review Completed | 9/26/2024 | PRANITA SHAH |
| Plan Check Approved | 5/12/2025 | DANIEL YIP |
| Issued | 5/20/2025 | APPLICANT |
| CofO in Progress | 4/30/2026 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 4/30/2026 | DEROLD HAUFF |
| CofO Issued | 4/30/2026 | DEROLD HAUFF |
| Permit Finaled | 4/30/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/7/2024 | JEANIE LAM |
| Low Impact Development (LID) | Cleared | 10/10/2024 | SARAH YOUSSEF |
| Permit | Cleared | 10/15/2024 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 10/15/2024 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 10/21/2024 | JEANIE LAM |
| Sewer availability | Cleared | 10/21/2024 | JEANIE LAM |
| Hydrant and Access approval | Cleared | 1/9/2025 | JOHN CONNEALLY |
Contact Information
| Contractor | J Z J B Cnst Inv; Lic. No.: 1013600-B | , |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 2543 E NORMAN AVE WEST COVINA, CA 91791 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/23/2025 | Approved | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 6/26/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 7/9/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 7/9/2025 | Approved | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 7/9/2025 | Approved | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 7/9/2025 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 7/11/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 7/15/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| Insulation | 7/15/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 7/23/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 8/4/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| Deputy Wood Construction | 9/16/2025 | Conditional Approval | ALEX COLIN |
| Floor/Roof Diaphrgm/Shear Wall | 9/18/2025 | Partial Approval | BARRY HACHE |
| PLUMBING-Rough | 9/19/2025 | Corrections Issued | BRENDAN MORELLI |
| PLUMBING-Rough | 9/22/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 9/23/2025 | Partial Approval | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 9/26/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 10/6/2025 | Corrections Issued | SABAS ALONSO |
| ELECTRICAL-Rough | 10/7/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 10/14/2025 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 10/14/2025 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 10/15/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 10/15/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 10/23/2025 | Approved | LUIS CASTRO |
| Green Building Rough | 10/23/2025 | Approved | LUIS CASTRO |
| Insulation | 10/23/2025 | Corrections Issued | LUIS CASTRO |
| Drywall Nailing | 11/3/2025 | Corrections Issued | BARRY HACHE |
| Interior/Exterior Lathing | 11/3/2025 | Corrections Issued | BARRY HACHE |
| Drywall Nailing | 11/5/2025 | Approved | BARRY HACHE |
| Interior/Exterior Lathing | 11/5/2025 | Approved | BARRY HACHE |
| Final | 11/6/2025 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| Verify Rec and Parks Fee Memo | 11/6/2025 | Approved | ALEJANDRO DE ARTOLA |
| Sewer | 1/8/2026 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 1/8/2026 | Partial Approval | MICHAEL LEWIS |
| Underground Mechanical | 1/12/2026 | Approved | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 1/14/2026 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 4/6/2026 | Corrections Issued | JOHN QUINTANILLA |
| Gas Test | 4/6/2026 | Approved | JOHN QUINTANILLA |
| ELECTRICAL-Final | 4/8/2026 | Approved | JOHN QUINTANILLA |
| PLUMBING-Final | 4/8/2026 | Approved | JOHN QUINTANILLA |
| HVAC-Final | 4/10/2026 | Corrections Issued | SABAS ALONSO |
| HVAC-Final | 4/14/2026 | Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 4/14/2026 | Approved | ALEJANDRO DE ARTOLA |
| Final | 4/21/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 4/21/2026 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 4/21/2026 | SGSOV Not Required | ALEJANDRO DE ARTOLA |
| Final | 4/27/2026 | OK to Issue CofO | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 4/27/2026 | Approved | ALEJANDRO DE ARTOLA |