10846 W HUSTON ST 91601
Certificate Information: 10846 W HUSTON ST 91601
- Application / Permit
- 24014-20000-04165
- Plan Check / Job No.
- B24VN16669
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Conversion of an existing 2 car garage to a 2 story ADU per LAMC 12.22 A.33(c)-(d)
- Permit Issued
- Issued on 7/2/2025
- Issuing Office
- Current Status
- CofO Issued on 12/31/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/16/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/26/2024 | ARSALAN SHABESTARI |
| Corrections Issued | 9/30/2024 | ARSALAN SHABESTARI |
| Quality Review Completed | 10/9/2024 | YOUNG KIM |
| Plan Check Approved | 6/30/2025 | ARSALAN SHABESTARI |
| Issued | 7/2/2025 | APPLICANT |
| CofO in Progress | 12/18/2025 | JAVIER RAMOS JR |
| Permit Finaled | 12/31/2025 | RUBEN SALAS |
| CofO Issued | 12/31/2025 | RUBEN SALAS |
| Permit Finaled | 12/31/2025 | RUBEN SALAS |
Permit Application Clearance Information
| CPC | Cleared | 10/18/2024 | DORIAN AGUILAR |
| Address approval | Cleared | 10/20/2024 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 10/20/2024 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 10/20/2024 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 10/21/2024 | LEE GUILBEAUX |
| Sewer availability | Cleared | 10/21/2024 | LEE GUILBEAUX |
| Construction near power lines | Cleared | 3/21/2025 | GEVORK KARAPETYAN |
| Construction within easement | Cleared | 3/21/2025 | GEVORK KARAPETYAN |
Contact Information
| Architect | Hagobian,, Edward; Lic. No.: NA15980 | , |
| Contractor | Owner-Builder | , |
| Engineer | Pezeshkian,, Vahik; Lic. No.: NA35278 | , |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/4/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Sewer | 8/8/2025 | Approved | JUAN VALENZUELA |
| PLUMBING-Rough | 8/11/2025 | Partial Approval | JAVIER RAMOS JR |
| Underground Mechanical | 8/11/2025 | Partial Approval | JAVIER RAMOS JR |
| Deputy Drilled-In Anchors | 8/13/2025 | Conditional Approval | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 8/14/2025 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 9/2/2025 | Partial Approval | JAVIER RAMOS JR |
| Wood Frame | 9/23/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/25/2025 | Approved | JAVIER RAMOS JR |
| Wood Frame | 9/25/2025 | Partial Approval | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 10/1/2025 | Partial Approval | LOUIS ESCOTO |
| Shower Pan | 10/1/2025 | Approved | LOUIS ESCOTO |
| Rough-Elec/Plmb/HVAC | 10/8/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Rough | 10/15/2025 | Partial Approval | OGANES TARAKHCHYAN |
| HVAC-Rough | 10/15/2025 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 10/15/2025 | Corrections Issued | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 10/17/2025 | Partial Inspection | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 10/17/2025 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 10/17/2025 | Partial Approval | JAVIER RAMOS JR |
| PLUMBING-Rough | 10/17/2025 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 10/20/2025 | Partial Approval | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 10/20/2025 | Approved | JAVIER RAMOS JR |
| Insulation | 10/21/2025 | Partial Approval | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 10/24/2025 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 10/24/2025 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 10/24/2025 | Approved | JAVIER RAMOS JR |
| Insulation | 10/24/2025 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 10/30/2025 | Partial Approval | JAVIER RAMOS JR |
| Underground Mechanical | 11/5/2025 | Partial Approval | JAVIER RAMOS JR |
| Gas Test | 11/14/2025 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 12/4/2025 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 12/4/2025 | Approved | JAVIER RAMOS JR |
| HVAC-Final | 12/4/2025 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 12/4/2025 | Corrections Issued | JAVIER RAMOS JR |
| ELECTRICAL-Final | 12/11/2025 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 12/11/2025 | Approved | JAVIER RAMOS JR |
| Final | 12/17/2025 | Partial Inspection | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 12/17/2025 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 12/17/2025 | SGSOV Approved | JAVIER RAMOS JR |
| Smoke Detectors | 12/17/2025 | Approved | JAVIER RAMOS JR |
| Final | 12/18/2025 | OK to Issue CofO | JAVIER RAMOS JR |