3387 S HALDERMAN ST 90066

Certificate Information: 3387 S HALDERMAN ST 90066

Application / Permit
24014-20000-04164
Plan Check / Job No.
B24VN16660
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING 1ST FLOOR DETACHED GARAGE (320 SQFT) AND 2ND FLOOR RECREATION ROOM (295 SQFT) INTO AN ACCESSORY DWELLING UNIT W/(127 SQFT) ADDITION PER LAMC 12.22 A.33(c)(d)
Permit Issued
Issued on 2/7/2025
Issuing Office
West Los Angeles
Current Status
Issued on 2/7/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/16/2024 APPLICANT
Assigned to Plan Check Engineer 9/26/2024 PETER MOSESIAN
Corrections Issued 10/3/2024 PETER MOSESIAN
Quality Review Completed 10/8/2024 DAWN MC NULTY
Building Plans Picked Up 10/10/2024 APPLICANT
Plan Check Approved 11/5/2024 PETER MOSESIAN
Issued 2/7/2025 APPLICANT

Permit Application Clearance Information

Construction near power lines Cleared 10/1/2024 RIDWAN HARDY
Address approval Cleared 10/15/2024 LIAM ODONOVAN
Roof/Waste drainage to street Cleared 10/15/2024 LIAM ODONOVAN
Sewer availability Cleared 10/15/2024 LIAM ODONOVAN
Specific Plan Cleared 10/16/2024 RICHARD WOO
Grading Pre-Inspection Cleared 10/21/2024 MANUEL TEJADA
Eng Process Fee Ord 176,300 Cleared 10/28/2024 HISASHI KOBAYAKAWA
Public Works-Highway Ded. Cleared 9/11/2025 CHRISTINE REUSCH
Public Works-Open Permits Cleared 9/11/2025 CHRISTINE REUSCH
Public Works-Sewers Cleared 9/11/2025 CHRISTINE REUSCH

Contact Information

Contractor Sokolow Pandro Construction Inc; Lic. No.: 692485-B 1946 14TH STREET      SANTA MONICA, CA 90404
Engineer Lu,, Ining; Lic. No.: S3042 47 E LAS FLORES AVENUE      ARCADIA, CA 91006

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/28/2025 Corrections Issued JESUS PINEDA
PLUMBING-Rough 2/28/2025 Not Ready for Inspection JESUS PINEDA
Footing/Foundation/Slab 3/10/2025 Approved ARAM AVEDISIAN
PLUMBING-Rough 3/10/2025 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Rough 3/27/2025 Partial Approval MICHAEL ALLEN
Underground Mechanical 3/27/2025 Approved MICHAEL ALLEN
ELECTRICAL-Rough 6/27/2025 Approved MICHAEL ALLEN
HVAC-Rough 6/27/2025 Approved MICHAEL ALLEN
PLUMBING-Rough 6/27/2025 Approved MICHAEL ALLEN
Special/Order Compliance 6/27/2025 Corrections Issued MICHAEL ALLEN
BUILDING-Rough-Frame 7/14/2025 Approved MICHAEL ALLEN
Green Building Rough 7/14/2025 Approved MICHAEL ALLEN
Interior/Exterior Lathing 7/14/2025 Partial Approval MICHAEL ALLEN
Shower Pan 7/14/2025 Approved MICHAEL ALLEN
Insulation 7/17/2025 Approved MICHAEL ALLEN
Drywall Nailing 7/23/2025 Approved WILBER ROSALES
Interior/Exterior Lathing 7/23/2025 Approved WILBER ROSALES
ELECTRICAL-Final 11/18/2025 Corrections Issued WILBER ROSALES
Final 11/18/2025 Corrections Issued WILBER ROSALES
Green Building Final 11/18/2025 Not Ready for Inspection WILBER ROSALES
HVAC-Final 11/18/2025 Corrections Issued WILBER ROSALES
PLUMBING-Final 11/18/2025 Approved WILBER ROSALES
SGSOV-Seismic Gas S/O Valve 11/18/2025 SGSOV Not Ready WILBER ROSALES
Smoke Detectors 11/18/2025 Approved WILBER ROSALES
ELECTRICAL-Final 12/1/2025 Approved JESUS PINEDA
Final 12/1/2025 Corrections Issued JESUS PINEDA
Green Building Final 12/1/2025 Approved JESUS PINEDA
HVAC-Final 12/1/2025 Approved JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 12/1/2025 SGSOV Approved JESUS PINEDA