2159 1/2 W 29TH PL 90018
Certificate Information: 2159 1/2 W 29TH PL 90018
- Application / Permit
- 24014-20000-04163
- Plan Check / Job No.
- B24VN16653
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE AND (N) ADDITION TO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). WORK DONE PER ENGINEER DESIGN.
- Permit Issued
- Issued on 3/19/2025
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/18/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/16/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/23/2024 | JEROME MAGAT PALMA |
| Corrections Issued | 9/24/2024 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 9/30/2024 | APPLICANT |
| Plan Check Approved | 1/23/2025 | MADISON O'DELL |
| Issued | 3/19/2025 | APPLICANT |
| CofO in Progress | 11/18/2025 | SABAS ALONSO |
| Permit Finaled | 11/18/2025 | DEROLD HAUFF |
| CofO Issued | 11/18/2025 | DEROLD HAUFF |
| Permit Finaled | 11/18/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/3/2024 | JESSICA OPINION |
| Roof/Waste drainage to street | Cleared | 10/9/2024 | JUSTIN BICOL |
| Eng Process Fee Ord 176,300 | Cleared | 10/28/2024 | TREVOR QUAN |
| Sewer availability | Cleared | 10/28/2024 | TREVOR QUAN |
| Construction near power lines | Cleared | 12/26/2024 | RIDWAN HARDY |
| HPOZ | Cleared | 1/16/2025 | DANIEL MATA |
Contact Information
| Contractor | Gomez H & F Construction Inc; Lic. No.: 967768-B | 417 E LOS AMIGOS AVE MONTEBELLO, CA 90640 |
| Engineer | Tan,, Henreik; Lic. No.: C65723 | 5100 LLANO DRIVE WOODLAND HILLS, CA 91364 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/7/2025 | Partial Inspection | SABAS ALONSO |
| ELECTRICAL-Rough | 4/21/2025 | Not Ready for Inspection | BARRY HACHE |
| Underground Mechanical | 4/21/2025 | Conditional Approval | BARRY HACHE |
| Footing/Foundation/Slab | 5/7/2025 | Partial Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 5/16/2025 | Approved | SABAS ALONSO |
| Sewer | 5/22/2025 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 5/28/2025 | Approved | JOHN QUINTANILLA |
| Green Building Rough | 6/13/2025 | Corrections Issued | SABAS ALONSO |
| Interior/Exterior Lathing | 6/13/2025 | Partial Approval | SABAS ALONSO |
| Green Building Rough | 6/16/2025 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 6/16/2025 | Approved | SABAS ALONSO |
| Shower Pan | 6/16/2025 | Approved | SABAS ALONSO |
| Underground Mechanical | 6/16/2025 | Approved | SABAS ALONSO |
| ELECTRICAL-Rough | 6/18/2025 | Corrections Issued | SABAS ALONSO |
| HVAC-Rough | 6/18/2025 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 6/23/2025 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Rough | 6/23/2025 | Not Ready for Inspection | SABAS ALONSO |
| BUILDING-Rough-Frame | 6/25/2025 | Approved | SABAS ALONSO |
| ELECTRICAL-Rough | 6/25/2025 | Approved | SABAS ALONSO |
| Insulation | 7/9/2025 | Approved | ALEX COLIN |
| Drywall Nailing | 7/21/2025 | Partial Approval | RONNIE MEDINA |
| Drywall Nailing | 8/6/2025 | Approved | DEVON JACKSON |
| Interior/Exterior Lathing | 8/20/2025 | Approved | BRENDAN MORELLI |
| ELECTRICAL-Final | 10/2/2025 | Approved | SABAS ALONSO |
| Final | 10/2/2025 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 10/2/2025 | Approved | SABAS ALONSO |
| HVAC-Final | 10/2/2025 | Approved | SABAS ALONSO |
| PLUMBING-Final | 10/2/2025 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 10/2/2025 | SGSOV Approved | SABAS ALONSO |
| Smoke Detectors | 10/2/2025 | Approved | SABAS ALONSO |
| Final | 11/13/2025 | Corrections Issued | SABAS ALONSO |
| Final | 11/17/2025 | OK to Issue CofO | SABAS ALONSO |