16931 W LOS ALIMOS ST 91344

Certificate Information: 16931 W LOS ALIMOS ST 91344

Application / Permit
24014-20000-04156
Plan Check / Job No.
B24VN16619
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EXTERIOR ALTERATION TO REMOVE (E) PATIO COVER AND ADD TO & REMODEL (E) SFD, ALL WORK PER ENG.
Permit Issued
Issued on 11/25/2024
Issuing Office
Valley
Current Status
CofO Issued on 8/14/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/16/2024 APPLICANT
Assigned to Plan Check Engineer 9/24/2024 JESSE ARELLANO
Corrections Issued 9/25/2024 JESSE ARELLANO
Building Plans Picked Up 9/27/2024 APPLICANT
Applicant returned to address corrections 11/21/2024 LUISANGEL VALENZUELA
Issued 11/25/2024 APPLICANT
CofO in Progress 8/14/2025 CHRISTOPHER ROJAS
Permit Finaled 8/14/2025 RUBEN SALAS
CofO Issued 8/14/2025 RUBEN SALAS
Permit Finaled 8/14/2025 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/21/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 11/21/2024 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Mahaney,, James A; Lic. No.: S2444 3975 FOOTHILL OAKS DR      AUBURN, CA 95602

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/25/2025 Approved JAVIER RAMOS JR
Footing/Foundation/Slab 2/25/2025 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 3/12/2025 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Rough 3/12/2025 Partial Approval SALVADOR MARTINEZ
Deputy Wood Construction 3/17/2025 Conditional Approval ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 3/20/2025 Partial Approval JAVIER RAMOS JR
Insulation 3/20/2025 Partial Inspection JAVIER RAMOS JR
BUILDING-Rough-Frame 4/3/2025 Corrections Issued CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 4/3/2025 Partial Inspection CHRISTOPHER ROJAS
Green Building Rough 4/3/2025 Partial Inspection CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 4/7/2025 Partial Approval CHRISTOPHER ROJAS
ELECTRICAL-Rough 4/17/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Interior/Exterior Lathing 4/17/2025 Partial Approval NICHOLAS TROWBRIDGE
PLUMBING-Rough 4/17/2025 Corrections Issued NICHOLAS TROWBRIDGE
Wood Frame 4/17/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
BUILDING-Rough-Frame 4/28/2025 Corrections Issued NICHOLAS TROWBRIDGE
ELECTRICAL-Rough 4/28/2025 Approved NICHOLAS TROWBRIDGE
Green Building Rough 4/28/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
PLUMBING-Rough 4/28/2025 Approved NICHOLAS TROWBRIDGE
Rough-Elec/Plmb/HVAC 4/28/2025 Approved NICHOLAS TROWBRIDGE
BUILDING-Rough-Frame 5/1/2025 Approved CHRISTOPHER ROJAS
Green Building Rough 5/1/2025 Approved CHRISTOPHER ROJAS
Structural Steel Frame 5/1/2025 Partial Inspection CHRISTOPHER ROJAS
Insulation 5/5/2025 Approved LOUIS ESCOTO
Drywall Nailing 5/7/2025 Approved LOUIS ESCOTO
Final 7/16/2025 Corrections Issued CHRISTOPHER ROJAS
Green Building Final 7/16/2025 Not Ready for Inspection CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 7/16/2025 SGSOV Not Ready CHRISTOPHER ROJAS
Smoke Detectors 7/16/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Final 8/13/2025 OK to Issue CofO CHRISTOPHER ROJAS
Green Building Final 8/13/2025 Approved CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 8/13/2025 SGSOV Approved CHRISTOPHER ROJAS
Smoke Detectors 8/13/2025 Approved CHRISTOPHER ROJAS