17446 W SATICOY ST 91406

Certificate Information: 17446 W SATICOY ST 91406

Application / Permit
24014-20000-04124
Plan Check / Job No.
B24VN16454
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: ADDITION TO (E) DETACHED GARAGE AND CONVERT GARAGE TO ACCESSORY DWELLING UNIT W/ PORCH ADDITION PER LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 11/17/2024
Issuing Office
Current Status
CofO Issued on 7/16/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/14/2024 APPLICANT
Assigned to Plan Check Engineer 9/18/2024 GURUNATH NESARAJAH
Corrections Issued 9/19/2024 GURUNATH NESARAJAH
Applicant returned to address corrections 10/24/2024 GURUNATH NESARAJAH
Applicant returned to address corrections 10/29/2024 MOHAMMAD ESMAILI
Plan Check Approved 11/5/2024 MOHAMMAD ESMAILI
Issued 11/17/2024 APPLICANT
CofO in Progress 6/27/2025 JUAN VALENZUELA
Permit Finaled 7/16/2025 RUBEN SALAS
CofO Issued 7/16/2025 RUBEN SALAS
Permit Finaled 7/16/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 10/4/2024 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 10/4/2024 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 10/4/2024 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 10/15/2024 LEE GUILBEAUX
Sewer availability Cleared 10/15/2024 LEE GUILBEAUX
Address approval Cleared 10/28/2024 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 11 CEDARWOOD DR      POMONA, CA 91766

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/24/2024 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Rough 12/31/2024 Partial Approval SALVADOR MARTINEZ
Deputy Drilled-In Anchors 1/7/2025 Conditional Approval RAUL OLAGI
Footing/Foundation/Slab 1/8/2025 Corrections Issued SALVADOR MARTINEZ
Footing/Foundation/Slab 1/13/2025 Approved SALVADOR MARTINEZ
Deputy Wood Construction 2/25/2025 Conditional Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 2/26/2025 Approved SALVADOR MARTINEZ
BUILDING-Rough-Frame 3/11/2025 Not Ready for Inspection SALVADOR MARTINEZ
ELECTRICAL-Rough 3/11/2025 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Rough 3/11/2025 Corrections Issued SALVADOR MARTINEZ
Interior/Exterior Lathing 3/26/2025 Partial Approval GAREN HAYRAPETYAN
Rough-Elec/Plmb/HVAC 3/28/2025 Approved GAREN HAYRAPETYAN
Shower Pan 3/28/2025 Approved GAREN HAYRAPETYAN
Gas Test 4/4/2025 Approved GAREN HAYRAPETYAN
Underground Mechanical 4/4/2025 Approved GAREN HAYRAPETYAN
Wood Frame 4/4/2025 Approved GAREN HAYRAPETYAN
Insulation 4/16/2025 Partial Approval SALVADOR MARTINEZ
Interior/Exterior Lathing 4/16/2025 Not Ready for Inspection SALVADOR MARTINEZ
Insulation 4/22/2025 Approved JOAQUIN GREENOUGH
Drywall Nailing 4/29/2025 Approved GAREN HAYRAPETYAN
Interior/Exterior Lathing 4/29/2025 Approved GAREN HAYRAPETYAN
Underground Mechanical 5/22/2025 Partial Approval MISAEL ESPARZA
BUILDING-Rough-Frame 6/12/2025 Approved MICHAEL CORTEZ
ELECTRICAL-Final 6/12/2025 Partial Inspection MICHAEL CORTEZ
Final 6/12/2025 Corrections Issued MICHAEL CORTEZ
Green Building Final 6/12/2025 Approved MICHAEL CORTEZ
Green Building Rough 6/12/2025 Approved MICHAEL CORTEZ
HVAC-Final 6/12/2025 Partial Inspection MICHAEL CORTEZ
PLUMBING-Final 6/12/2025 Partial Inspection MICHAEL CORTEZ
SGSOV-Seismic Gas S/O Valve 6/12/2025 SGSOV Approved MICHAEL CORTEZ
Smoke Detectors 6/12/2025 Approved MICHAEL CORTEZ
ELECTRICAL-Final 6/23/2025 Approved JOAQUIN GREENOUGH
Final 6/23/2025 Corrections Issued JOAQUIN GREENOUGH
HVAC-Final 6/23/2025 Approved JOAQUIN GREENOUGH
PLUMBING-Final 6/23/2025 Approved JOAQUIN GREENOUGH
Final 6/26/2025 OK to Issue CofO SALVADOR MARTINEZ
Service/Power Release 6/26/2025 Approved SALVADOR MARTINEZ