10448 N HASKELL AVE 91344

Certificate Information: 10448 N HASKELL AVE 91344

Application / Permit
24014-20000-04121
Plan Check / Job No.
B24VN16446
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
add 21 ft remodel bath
Permit Issued
Issued on 10/14/2024
Issuing Office
Current Status
CofO Issued on 2/27/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/18/2024 APPLICANT
Assigned to Plan Check Engineer 9/19/2024 NEHEMIAS RAMOS
Corrections Issued 9/19/2024 NEHEMIAS RAMOS
Applicant returned to address corrections 10/2/2024 LAWRENCE QUIRANTE
Plan Check Approved 10/11/2024 NEHEMIAS RAMOS
Issued 10/14/2024 APPLICANT
CofO in Progress 1/29/2025 JAVIER RAMOS JR
Permit Finaled 2/27/2025 RUBEN SALAS
CofO Issued 2/27/2025 RUBEN SALAS
Permit Finaled 2/27/2025 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 9/20/2024 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 9/30/2024 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 9/30/2024 LEE GUILBEAUX

Contact Information

Architect Dembsky,, Amit; Lic. No.: NA30383       ,
Contractor Preferred Home Builders Inc; Lic. No.: 773147-B       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/19/2024 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 11/22/2024 Approved KEVIN BERBERYAN
BUILDING-Rough-Frame 12/2/2024 Partial Approval ROBERT GOLD
Insulation 12/2/2024 Not Ready for Inspection ROBERT GOLD
Deputy Drilled-In Anchors 12/5/2024 Conditional Approval JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 12/17/2024 Approved JACK KARGODORIAN
Interior/Exterior Lathing 12/17/2024 Not Ready for Inspection JACK KARGODORIAN
Rough-Elec/Plmb/HVAC 12/17/2024 Approved JACK KARGODORIAN
Insulation 12/24/2024 Corrections Issued LOUIS ESCOTO
Interior/Exterior Lathing 12/24/2024 Approved LOUIS ESCOTO
Insulation 12/27/2024 Approved MICHAEL CORTEZ
Drywall Nailing 1/2/2025 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 1/6/2025 Partial Approval JACK KARGODORIAN
Interior/Exterior Lathing 1/13/2025 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 1/28/2025 Approved JAVIER RAMOS JR
ELECTRICAL-Final 1/28/2025 Approved JAVIER RAMOS JR
Final 1/28/2025 OK to Issue CofO JAVIER RAMOS JR
HVAC-Final 1/28/2025 Approved JAVIER RAMOS JR
MERV13>=Final 1/28/2025 Approved JAVIER RAMOS JR
MERV13>=Rough 1/28/2025 Approved JAVIER RAMOS JR
PLUMBING-Final 1/28/2025 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 1/28/2025 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 1/28/2025 Approved JAVIER RAMOS JR