18333 W DELANO ST 91335
Certificate Information: 18333 W DELANO ST 91335
- Application / Permit
- 24014-20000-04103
- Plan Check / Job No.
- B24VN16375
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- LEGALIZE UNPERMITTED ADDITIONS AND CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.23
- Permit Issued
- Issued on 1/6/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/27/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/12/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/19/2024 | JEROME MAGAT PALMA |
| Corrections Issued | 9/21/2024 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 9/23/2024 | APPLICANT |
| Plan Check Approved | 12/13/2024 | HAYATO TSUCHIYA |
| Issued | 1/6/2025 | APPLICANT |
| CofO in Progress | 11/14/2025 | JON MCHUGH |
| Permit Finaled | 12/27/2025 | MICHAEL PELHAM |
| CofO Issued | 12/27/2025 | MICHAEL PELHAM |
| Permit Finaled | 12/27/2025 | MICHAEL PELHAM |
Permit Application Clearance Information
| Address approval | Cleared | 9/24/2024 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 9/24/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 9/25/2024 | CARLOS AGUILERA |
| ZI | Cleared | 9/25/2024 | ASHLEY RODARTE |
| Sewer availability | Cleared | 9/26/2024 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 12/11/2024 | ENRIQUE ACOSTA |
Contact Information
| Contractor | R L Remodeling Inc; Lic. No.: 885032-B | 22817 VENTURA BLVD #852 WOODLAND HILLS, CA 91364 |
| Engineer | Southerland,, Richard Charles; Lic. No.: C88965 | 16526 BLACKHAWK ST GRANADA HILLS, CA 91344 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/16/2025 | Corrections Issued | JON MCHUGH |
| Pre-Inspection | 2/10/2025 | Partial Inspection | JON MCHUGH |
| BUILDING-Rough-Frame | 3/10/2025 | Corrections Issued | JON MCHUGH |
| Green Building Rough | 3/10/2025 | Not Ready for Inspection | JON MCHUGH |
| BUILDING-Rough-Frame | 3/19/2025 | Corrections Issued | JON MCHUGH |
| Green Building Rough | 3/19/2025 | Not Ready for Inspection | JON MCHUGH |
| Pre-Inspection | 3/26/2025 | Partial Inspection | JON MCHUGH |
| Deputy Drilled-In Anchors | 4/18/2025 | Conditional Approval | ROBERT GOLD |
| Excavation/Setback/Form/Re-Bar | 4/18/2025 | Partial Approval | JON MCHUGH |
| Special/Order Compliance | 4/18/2025 | Corrections Issued | JON MCHUGH |
| Pre-Inspection | 5/9/2025 | Partial Inspection | JON MCHUGH |
| Special/Order Compliance | 5/9/2025 | Partial Inspection | SEAN WIRCH |
| Pre-Inspection | 6/10/2025 | Partial Inspection | JON MCHUGH |
| BUILDING-Rough-Frame | 7/14/2025 | Not Ready for Inspection | JON MCHUGH |
| ELECTRICAL-Rough | 7/14/2025 | Corrections Issued | JON MCHUGH |
| Green Building Rough | 7/14/2025 | Not Ready for Inspection | JON MCHUGH |
| PLUMBING-Rough | 7/14/2025 | Corrections Issued | JON MCHUGH |
| PLUMBING-Rough | 7/21/2025 | Partial Approval | JON MCHUGH |
| Sewer | 7/21/2025 | Approved | JON MCHUGH |
| BUILDING-Rough-Frame | 7/24/2025 | Not Ready for Inspection | JON MCHUGH |
| Green Building Rough | 7/24/2025 | Not Ready for Inspection | JON MCHUGH |
| HVAC-Rough | 7/24/2025 | Corrections Issued | JON MCHUGH |
| Insulation | 7/29/2025 | Partial Approval | JON MCHUGH |
| Interior/Exterior Lathing | 7/29/2025 | Partial Approval | JON MCHUGH |
| Rough-Elec/Plmb/HVAC | 7/29/2025 | Corrections Issued | JON MCHUGH |
| ELECTRICAL-Rough | 8/4/2025 | Approved | JON MCHUGH |
| HVAC-Rough | 8/4/2025 | Not Ready for Inspection | JON MCHUGH |
| BUILDING-Rough-Frame | 8/11/2025 | Approved | JON MCHUGH |
| Green Building Rough | 8/11/2025 | Approved | JON MCHUGH |
| Insulation | 8/11/2025 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 8/11/2025 | Approved | JON MCHUGH |
| Rough-Elec/Plmb/HVAC | 8/11/2025 | Approved | JON MCHUGH |
| Shower Pan | 8/11/2025 | Approved | JON MCHUGH |
| Drywall Nailing | 8/15/2025 | Approved | MORRIS JACKSON |
| ELECTRICAL-Final | 8/29/2025 | Not Ready for Inspection | JON MCHUGH |
| Final | 8/29/2025 | Corrections Issued | JON MCHUGH |
| Footing/Foundation/Slab | 8/29/2025 | Approved | JON MCHUGH |
| Green Building Final | 8/29/2025 | Not Ready for Inspection | JON MCHUGH |
| PLUMBING-Final | 8/29/2025 | Not Ready for Inspection | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 8/29/2025 | SGSOV Not Ready | JON MCHUGH |
| Smoke Detectors | 8/29/2025 | Approved | JON MCHUGH |
| Final | 9/15/2025 | Not Ready for Inspection | JON MCHUGH |
| Green Building Final | 9/15/2025 | Approved | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 9/15/2025 | SGSOV Approved | JON MCHUGH |
| ELECTRICAL-Final | 11/14/2025 | Approved | JON MCHUGH |
| Final | 11/14/2025 | OK to Issue CofO | JON MCHUGH |
| HVAC-Final | 11/14/2025 | Approved | JON MCHUGH |
| PLUMBING-Final | 11/14/2025 | Approved | JON MCHUGH |