6651-6653 N DELCO AVE 91306

Certificate Information: 6651-6653 N DELCO AVE 91306

Application / Permit
24014-20000-04071
Plan Check / Job No.
B24VN16124
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
EPLAN: add 2-story Dwelling per SB9 attached to existing dwelling per Ca Govt Code 65852.21
Permit Issued
Issued on 2/5/2025
Issuing Office
Current Status
Issued on 2/5/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/11/2024 APPLICANT
Assigned to Plan Check Engineer 9/12/2024 SAM CHANG
Corrections Issued 10/2/2024 SAM CHANG
Quality Review Completed 10/3/2024 EUGENE BARBEAU
Applicant returned to address corrections 11/27/2024 SAM CHANG
Applicant returned to address corrections 1/22/2025 SAM CHANG
Plan Check Approved 1/27/2025 SAM CHANG
Issued 2/5/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 10/11/2024 RYAN CASTRO
Roof/Waste drainage to street Cleared 10/11/2024 RYAN CASTRO
Construction near power lines Cleared 10/18/2024 TINA MIRANDA
Senate Bill 9 Cleared 11/5/2024 NATHAN ROMINE
Hydrant and Access approval Cleared 12/15/2024 PATRICK PEREZ
Eng Process Fee Ord 176,300 Cleared 1/3/2025 RYAN CASTRO
Sewer availability Cleared 1/3/2025 RYAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Sheppard,, Kayse Rose; Lic. No.: NA95444       ,

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/10/2025 Partial Approval JON MCHUGH
Footing/Foundation/Slab 2/21/2025 Approved ALEXANDER HANDY
Floor/Roof Diaphrgm/Shear Wall 3/5/2025 Partial Approval ALEXANDER HANDY
Floor/Roof Diaphrgm/Shear Wall 5/9/2025 Partial Approval ALEXANDER HANDY
Special/Order Compliance 5/9/2025 Corrections Issued ALEXANDER HANDY
Deputy Wood Construction 5/30/2025 Conditional Approval ROBERT GOLD
ELECTRICAL-Rough 6/5/2025 Approved ALEXANDER HANDY
HVAC-Rough 6/5/2025 Approved ALEXANDER HANDY
PLUMBING-Rough 6/5/2025 Corrections Issued ALEXANDER HANDY
Interior/Exterior Lathing 8/7/2025 Partial Approval JOHN HAYES
Shower Pan 8/7/2025 Approved JOHN HAYES
BUILDING-Rough-Frame 8/15/2025 Approved ALEXANDER HANDY
Green Building Rough 8/15/2025 Approved ALEXANDER HANDY
Interior/Exterior Lathing 8/15/2025 Approved ALEXANDER HANDY
PLUMBING-Rough 8/15/2025 Approved ALEXANDER HANDY
Verify Sprinkler Sign Off 8/15/2025 Approved ALEXANDER HANDY
Insulation 8/19/2025 Conditional Approval SCOTT SOBEL
Drywall Nailing 8/22/2025 Corrections Issued ARUTYUN MADATYAN
Sewer 1/14/2026 Approved ALEXANDER HANDY
Underground Mechanical 1/14/2026 Approved ALEXANDER HANDY
ELECTRICAL-Final 4/24/2026 Not Ready for Inspection JACK KARGODORIAN
Final 4/24/2026 Corrections Issued JACK KARGODORIAN
Green Building Final 4/24/2026 Not Ready for Inspection JACK KARGODORIAN
HVAC-Final 4/24/2026 Approved JACK KARGODORIAN
PLUMBING-Final 4/24/2026 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 4/24/2026 SGSOV Approved JACK KARGODORIAN
Smoke Detectors 4/24/2026 Not Ready for Inspection JACK KARGODORIAN
Footing/Foundation/Slab 5/20/2026 Corrections Issued ALEXANDER HANDY
Insulation 5/20/2026 Partial Approval ALEXANDER HANDY
Drywall Nailing 5/22/2026 Approved ROBERT GOLD
ELECTRICAL-Final 5/22/2026 Not Ready for Inspection ROBERT GOLD
Final 5/22/2026 Corrections Issued ROBERT GOLD
Green Building Final 5/22/2026 Approved ROBERT GOLD
HVAC-Final 5/22/2026 Approved ROBERT GOLD
PLUMBING-Final 5/22/2026 Approved ROBERT GOLD
Smoke Detectors 5/22/2026 Approved ROBERT GOLD