19001-19003 W CANTLAY ST 91335
Certificate Information: 19001-19003 W CANTLAY ST 91335
- Application / Permit
- 24014-20000-04063
- Plan Check / Job No.
- B24VN16073
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD TO & CONVERT ATT. GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (e) PER ENGINEER
- Permit Issued
- Issued on 9/20/2024
- Issuing Office
- Current Status
- CofO Issued on 5/29/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/10/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/16/2024 | JESSE ARELLANO |
| Corrections Issued | 9/17/2024 | JESSE ARELLANO |
| Building Plans Picked Up | 9/18/2024 | APPLICANT |
| Plan Check Approved | 9/20/2024 | ANGELICA MARTINEZ |
| Issued | 9/20/2024 | APPLICANT |
| CofO in Progress | 5/18/2026 | ARUTYUN MADATYAN |
| Permit Finaled | 5/29/2026 | JOHN JANSON |
| CofO Issued | 5/29/2026 | JOHN JANSON |
| Permit Finaled | 5/29/2026 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 9/18/2024 | CARLOS RAMIREZ |
| Roof/Waste drainage to street | Cleared | 9/18/2024 | CARLOS RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/19/2024 | CARLOS RAMIREZ |
| Sewer availability | Cleared | 9/19/2024 | CARLOS RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Ramirez, Cid, Jose Carlos; Lic. No.: C91046 | 5164 N RATON CIR LONG BEACH, CA 90807 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/25/2024 | Partial Approval | JEFFREY BULL |
| PLUMBING-Rough | 11/7/2024 | Partial Approval | ARUTYUN MADATYAN |
| Sewer | 11/7/2024 | Approved | ARUTYUN MADATYAN |
| Excavation/Setback/Form/Re-Bar | 11/20/2024 | Approved | DAVID SCANTLIN |
| Footing/Foundation/Slab | 11/20/2024 | Approved | DAVID SCANTLIN |
| Drywall Nailing | 12/5/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/5/2024 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 3/28/2025 | Approved | ARUTYUN MADATYAN |
| HVAC-Rough | 3/28/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 3/28/2025 | Partial Approval | ARUTYUN MADATYAN |
| PLUMBING-Rough | 3/28/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| HVAC-Rough | 5/1/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| PLUMBING-Rough | 5/1/2025 | Approved | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 5/9/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Green Building Rough | 5/9/2025 | Approved | JUAN ALVARADO |
| Wood Frame | 5/9/2025 | Partial Approval | JUAN ALVARADO |
| BUILDING-Rough-Frame | 6/4/2025 | Approved | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/4/2025 | Approved | ARUTYUN MADATYAN |
| HVAC-Rough | 6/4/2025 | Approved | ARUTYUN MADATYAN |
| Insulation | 6/11/2025 | Approved | ARUTYUN MADATYAN |
| Drywall Nailing | 6/27/2025 | Approved | KRISTEN CAUSEY |
| Shower Pan | 7/21/2025 | Approved | KRISTEN CAUSEY |
| ELECTRICAL-Final | 10/24/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Gas Test | 10/24/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| HVAC-Final | 10/24/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 10/24/2025 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Final | 10/24/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Pre-Inspection | 10/24/2025 | Partial Inspection | ARUTYUN MADATYAN |
| Rough-Elec/Plmb/HVAC | 10/24/2025 | Approved | ARUTYUN MADATYAN |
| Service/Power Release | 10/24/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Smoke Detectors | 10/24/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 2/5/2026 | Approved | ARUTYUN MADATYAN |
| Final | 2/5/2026 | Corrections Issued | ARUTYUN MADATYAN |
| HVAC-Final | 2/5/2026 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Final | 2/5/2026 | Approved | ARUTYUN MADATYAN |
| Final | 5/15/2026 | OK to Issue CofO | ARUTYUN MADATYAN |
| Green Building Final | 5/15/2026 | Approved | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 5/15/2026 | SGSOV Approved | ARUTYUN MADATYAN |
| Service/Power Release | 5/15/2026 | Approved | ARUTYUN MADATYAN |
| Smoke Detectors | 5/15/2026 | Approved | ARUTYUN MADATYAN |