10200 N SALOMA AVE 91345

Certificate Information: 10200 N SALOMA AVE 91345

Application / Permit
24014-20000-04050
Plan Check / Job No.
B24VN15967
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN. ADDITION AND INTERIOR REMODEL TO (E) SFD
Permit Issued
Issued on 2/5/2025
Issuing Office
Current Status
CofO Issued on 5/21/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/20/2024 APPLICANT
Assigned to Plan Check Engineer 9/25/2024 FERNANDO FLORES
Corrections Issued 9/26/2024 FERNANDO FLORES
Applicant returned to address corrections 10/9/2024 SUNMIN LEE
Plan Check Approved 10/31/2024 SUNMIN LEE
Issued 2/5/2025 APPLICANT
CofO in Progress 4/28/2026 JENNIFER RABUCHIN
CofO Issued 5/21/2026 RUBEN SALAS
Permit Finaled 5/21/2026 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 9/26/2024 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 10/1/2024 RYAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Sivushenka,, Mikita; Lic. No.: C87698 22814 DOLOROSA ST      WOODLAND HILLS, CA 91367

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/27/2025 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 6/9/2025 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 6/9/2025 Not Ready for Inspection JENNIFER RABUCHIN
Insulation 6/11/2025 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 7/1/2025 Partial Approval JENNIFER RABUCHIN
Green Building Rough 7/1/2025 Not Ready for Inspection JENNIFER RABUCHIN
ELECTRICAL-Rough 8/11/2025 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 9/12/2025 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 9/12/2025 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 9/29/2025 Partial Approval MICHAEL CORTEZ
Interior/Exterior Lathing 10/3/2025 Partial Approval JENNIFER RABUCHIN
Insulation 10/21/2025 Approved JENNIFER RABUCHIN
Drywall Nailing 11/12/2025 Approved CHRISTOPHER MORFIN
Green Building Rough 11/12/2025 Approved CHRISTOPHER MORFIN
Floor/Roof Diaphrgm/Shear Wall 1/14/2026 Approved JENNIFER RABUCHIN
Smoke Detectors 1/14/2026 Not Ready for Inspection JENNIFER RABUCHIN
BUILDING-Rough-Frame 3/12/2026 Approved JENNIFER RABUCHIN
Final 3/12/2026 Corrections Issued JENNIFER RABUCHIN
Green Building Final 3/12/2026 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 3/12/2026 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 3/12/2026 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Final 4/10/2026 Approved JENNIFER RABUCHIN
Final 4/10/2026 OK to Issue CofO JENNIFER RABUCHIN
HVAC-Final 4/10/2026 Approved JENNIFER RABUCHIN
Smoke Detectors 4/10/2026 Approved JENNIFER RABUCHIN