7254 N JELLICO AVE 91406
Certificate Information: 7254 N JELLICO AVE 91406
- Application / Permit
- 24014-20000-04029
- Plan Check / Job No.
- B24VN15858
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- *EPLAN* GROUND FLOOR ADDITION, SECOND STORY ADDITION, AND REMODEL OF EXISTING 1-STORY SINGLE FAMILY DWELLING. NFPA 13D
- Permit Issued
- Issued on 3/25/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/27/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/9/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/19/2024 | VIVIAN LAO |
| Corrections Issued | 9/25/2024 | VIVIAN LAO |
| Quality Review Completed | 9/26/2024 | GARO TELMI |
| Applicant returned to address corrections | 2/28/2025 | VIVIAN LAO |
| Plan Check Approved | 3/12/2025 | VIVIAN LAO |
| Issued | 3/25/2025 | APPLICANT |
| CofO in Progress | 2/12/2026 | GAREN HAYRAPETYAN |
| Permit Finaled | 2/27/2026 | RUBEN SALAS |
| CofO Issued | 2/27/2026 | RUBEN SALAS |
| Permit Finaled | 2/27/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/4/2025 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 2/4/2025 | LEE GUILBEAUX |
| Sewer availability | Cleared | 2/4/2025 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 2/4/2025 | LEE GUILBEAUX |
Contact Information
| Contractor | Kendex Inc; Lic. No.: 855775-B | , |
| Engineer | Liu,, Guang Xi David; Lic. No.: NA56717 | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/28/2025 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 4/2/2025 | Partial Approval | GAREN HAYRAPETYAN |
| Deputy Drilled-In Anchors | 4/15/2025 | Conditional Approval | RAUL OLAGI |
| Footing/Foundation/Slab | 4/23/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Deputy Drilled-In Anchors | 4/24/2025 | Conditional Approval | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 5/23/2025 | Partial Approval | SALVADOR MARTINEZ |
| Deputy Reinf. Concrete | 5/27/2025 | Conditional Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 6/18/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Footing/Foundation/Slab | 6/24/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2025 | Partial Approval | SALVADOR MARTINEZ |
| Footing/Foundation/Slab | 7/1/2025 | Approved | SALVADOR MARTINEZ |
| Deputy Reinf. Concrete | 7/2/2025 | Conditional Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 8/21/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/16/2025 | Partial Approval | JAVIER RAMOS JR |
| Green Building Rough | 9/16/2025 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 9/16/2025 | Partial Approval | JAVIER RAMOS JR |
| Underground Mechanical | 9/16/2025 | Partial Approval | JAVIER RAMOS JR |
| PLUMBING-Rough | 9/24/2025 | Approved | GAREN HAYRAPETYAN |
| ELECTRICAL-Rough | 10/16/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| BUILDING-Rough-Frame | 10/21/2025 | Approved | GAREN HAYRAPETYAN |
| ELECTRICAL-Rough | 10/21/2025 | Approved | GAREN HAYRAPETYAN |
| HVAC-Rough | 10/21/2025 | Approved | GAREN HAYRAPETYAN |
| Special/Order Compliance | 10/21/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Insulation | 10/28/2025 | Approved | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 10/28/2025 | Partial Approval | GAREN HAYRAPETYAN |
| Drywall Nailing | 11/21/2025 | Approved | GAREN HAYRAPETYAN |
| Service/Power Release | 11/21/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Shower Pan | 11/21/2025 | Approved | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 11/25/2025 | Approved | GAREN HAYRAPETYAN |
| Service/Power Release | 1/7/2026 | Corrections Issued | GAREN HAYRAPETYAN |
| Final | 2/5/2026 | Corrections Issued | GAREN HAYRAPETYAN |
| Green Building Final | 2/5/2026 | Approved | GAREN HAYRAPETYAN |
| SGSOV-Seismic Gas S/O Valve | 2/5/2026 | SGSOV Not Ready | GAREN HAYRAPETYAN |
| Smoke Detectors | 2/5/2026 | Approved | GAREN HAYRAPETYAN |
| ELECTRICAL-Final | 2/10/2026 | Approved | GAREN HAYRAPETYAN |
| Final | 2/12/2026 | OK to Issue CofO | GAREN HAYRAPETYAN |
| SGSOV-Seismic Gas S/O Valve | 2/12/2026 | SGSOV Approved | GAREN HAYRAPETYAN |
| Service/Power Release | 2/12/2026 | Approved | GAREN HAYRAPETYAN |