7007 N OSO AVE 91306
Certificate Information: 7007 N OSO AVE 91306
- Application / Permit
- 24014-20000-04020
- Plan Check / Job No.
- B24VN15763
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Proposed 1-story detached ADU per LAMC
- Permit Issued
- Issued on 12/27/2024
- Issuing Office
- Current Status
- CofO Issued on 1/7/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/6/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/11/2024 | JOSE VELAZQUEZ |
| Corrections Issued | 9/12/2024 | JOSE VELAZQUEZ |
| Applicant returned to address corrections | 10/4/2024 | NGHI SU |
| Applicant returned to address corrections | 10/15/2024 | SHANGQIN XIE |
| Applicant returned to address corrections | 10/23/2024 | NGHI SU |
| Applicant returned to address corrections | 10/31/2024 | NGHI SU |
| Applicant returned to address corrections | 11/12/2024 | NGHI SU |
| Applicant returned to address corrections | 11/14/2024 | NGHI SU |
| Plan Check Approved | 12/19/2024 | NGHI SU |
| Issued | 12/27/2024 | APPLICANT |
| CofO in Progress | 8/15/2025 | ALEXANDER HANDY |
| Permit Finaled | 1/7/2026 | JOHN JANSON |
| CofO Issued | 1/7/2026 | JOHN JANSON |
| Permit Finaled | 1/7/2026 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 9/16/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 9/16/2024 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 9/16/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 9/16/2024 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 9/17/2024 | WALTER RAMIREZ |
| ZI | Cleared | 9/18/2024 | RUBEN VASQUEZ |
Contact Information
| Contractor | Pnr Builders Inc; Lic. No.: 1028148-B | , |
| Engineer | Mroczka,, Peter J; Lic. No.: C42648 | 9301 DARBY AVE APT 1 NORTHRIDGE, CA 91325 |
Inspector Information
| DAVID FASTIGGI, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 1/28/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| PLUMBING-Rough | 1/28/2025 | Partial Approval | ALEXANDER HANDY |
| Verify Sprinkler Sign Off | 1/28/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| Excavation/Setback/Form/Re-Bar | 2/10/2025 | Partial Inspection | ALEXANDER HANDY |
| Excavation/Setback/Form/Re-Bar | 2/11/2025 | Approved | ALEXANDER HANDY |
| Deputy Wood Construction | 2/18/2025 | Conditional Approval | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 2/18/2025 | Partial Approval | MORRIS JACKSON |
| Drywall Nailing | 2/24/2025 | Partial Approval | JUAN ALVARADO |
| Interior/Exterior Lathing | 2/26/2025 | Partial Approval | ALEXANDER HANDY |
| Deputy Wood Construction | 3/6/2025 | Approved | ALEXANDER HANDY |
| Floor/Roof Diaphrgm/Shear Wall | 3/6/2025 | Partial Approval | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 4/4/2025 | Corrections Issued | JOHN HAYES |
| Green Building Rough | 4/4/2025 | Not Ready for Inspection | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 4/4/2025 | Not Ready for Inspection | JOHN HAYES |
| Verify Sprinkler Sign Off | 4/4/2025 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 4/10/2025 | Not Ready for Inspection | SCOTT SOBEL |
| ELECTRICAL-Rough | 4/10/2025 | Partial Approval | SCOTT SOBEL |
| Green Building Rough | 4/10/2025 | Not Ready for Inspection | SCOTT SOBEL |
| HVAC-Rough | 4/10/2025 | Partial Approval | SCOTT SOBEL |
| PLUMBING-Rough | 4/10/2025 | Approved | SCOTT SOBEL |
| Verify Sprinkler Sign Off | 4/10/2025 | Approved | SCOTT SOBEL |
| HVAC-Rough | 4/16/2025 | Corrections Issued | ALEXANDER HANDY |
| Interior/Exterior Lathing | 4/16/2025 | Partial Approval | ALEXANDER HANDY |
| Insulation | 4/21/2025 | Corrections Issued | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 5/1/2025 | Approved | ALEXANDER HANDY |
| Drywall Nailing | 5/1/2025 | Approved | ALEXANDER HANDY |
| Green Building Rough | 5/1/2025 | Approved | ALEXANDER HANDY |
| Interior/Exterior Lathing | 5/5/2025 | Approved | MORRIS JACKSON |
| Shower Pan | 5/5/2025 | Approved | MORRIS JACKSON |
| PLUMBING-Rough | 6/10/2025 | Approved | ARUTYUN MADATYAN |
| Sewer | 6/10/2025 | Approved | ARUTYUN MADATYAN |
| Underground Mechanical | 6/13/2025 | Approved | ALEXANDER HANDY |
| Final | 7/23/2025 | Corrections Issued | ALEXANDER HANDY |
| Footing/Foundation/Slab | 7/23/2025 | Approved | ALEXANDER HANDY |
| Green Building Final | 7/23/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 7/23/2025 | SGSOV Not Ready | ALEXANDER HANDY |
| Service/Power Release | 7/23/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| Smoke Detectors | 7/23/2025 | Approved | ALEXANDER HANDY |
| Final | 8/4/2025 | Not Ready for Inspection | KRISTEN CAUSEY |
| Green Building Final | 8/4/2025 | Not Ready for Inspection | KRISTEN CAUSEY |
| SGSOV-Seismic Gas S/O Valve | 8/4/2025 | SGSOV Not Ready | KRISTEN CAUSEY |
| Service/Power Release | 8/4/2025 | Not Ready for Inspection | KRISTEN CAUSEY |
| Final | 8/8/2025 | Corrections Issued | ALEXANDER HANDY |
| Green Building Final | 8/8/2025 | Approved | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 8/8/2025 | SGSOV Not Ready | ALEXANDER HANDY |
| Service/Power Release | 8/8/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| ELECTRICAL-Final | 8/14/2025 | Approved | ALEXANDER HANDY |
| Final | 8/14/2025 | OK to Issue CofO | ALEXANDER HANDY |
| HVAC-Final | 8/14/2025 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 8/14/2025 | Approved | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 8/14/2025 | SGSOV No Gas | ALEXANDER HANDY |
| Service/Power Release | 8/14/2025 | Approved | ALEXANDER HANDY |