13623 W POLK ST 91342

Certificate Information: 13623 W POLK ST 91342

Application / Permit
24014-20000-04017
Plan Check / Job No.
B24VN15735
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 22' X 22'-0" ADU ADDITION TO DETACHED GARAGE PER LAMC 12.22 A.33(c) AND (d) AND 5'-0" X 22'-0 PATIO ADDITTION, ALL WORK PER ENG. TO REMOVE (E) CANOPY AND STABLE.
Permit Issued
Issued on 4/25/2025
Issuing Office
Current Status
Issued on 4/25/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/23/2024 APPLICANT
Assigned to Plan Check Engineer 9/25/2024 LUISANGEL VALENZUELA
Corrections Issued 9/25/2024 LUISANGEL VALENZUELA
Applicant returned to address corrections 2/28/2025 LUISANGEL VALENZUELA
Applicant returned to address corrections 3/12/2025 GIOVANNY CHAVEZ
Plan Check Approved 3/18/2025 GIOVANNY CHAVEZ
No Progress 3/18/2025 GIOVANNY CHAVEZ
Plan Check Approved 3/18/2025 GIOVANNY CHAVEZ
Plan Check Approved 4/21/2025 GIOVANNY CHAVEZ
Issued 4/25/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 10/13/2024 TAL SHEMEN
Roof/Waste drainage to street Cleared 10/13/2024 TAL SHEMEN
Eng Process Fee Ord 176,300 Cleared 11/18/2024 TAL SHEMEN
Sewer availability Cleared 11/18/2024 TAL SHEMEN
Construction near power lines Cleared 11/20/2024 RIDWAN HARDY
Hydrant and Access approval Cleared 1/28/2025 KENNETH FRASER

Contact Information

Contractor Owner-Builder       ,
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/28/2025 Partial Inspection KEVIN BERBERYAN
Excavation/Setback/Form/Re-Bar 7/23/2025 Approved KEVIN BERBERYAN
BUILDING-Rough-Frame 10/28/2025 Corrections Issued KEVIN BERBERYAN
ELECTRICAL-Rough 10/28/2025 Approved KEVIN BERBERYAN
Floor/Roof Diaphrgm/Shear Wall 10/28/2025 Not Ready for Inspection KEVIN BERBERYAN
Gas Test 10/28/2025 Approved KEVIN BERBERYAN
Green Building Rough 10/28/2025 Not Ready for Inspection KEVIN BERBERYAN
PLUMBING-Rough 10/28/2025 Approved KEVIN BERBERYAN
Sewer 10/28/2025 Corrections Issued KEVIN BERBERYAN
Underground Mechanical 10/28/2025 Corrections Issued KEVIN BERBERYAN
Wood Frame 10/28/2025 Not Ready for Inspection KEVIN BERBERYAN
BUILDING-Rough-Frame 5/12/2026 Corrections Issued MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 5/12/2026 Partial Inspection MICHEL ABAJAN
Green Building Rough 5/12/2026 Not Ready for Inspection MICHEL ABAJAN
Interior/Exterior Lathing 5/12/2026 Approved MICHEL ABAJAN
Sewer 5/12/2026 Partial Approval MICHEL ABAJAN
Shower Pan 5/12/2026 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 5/26/2026 Corrections Issued KEVIN BERBERYAN
Green Building Rough 5/26/2026 Not Ready for Inspection KEVIN BERBERYAN
Insulation 5/26/2026 Corrections Issued KEVIN BERBERYAN
Wood Frame 5/26/2026 Not Ready for Inspection KEVIN BERBERYAN
Insulation 5/28/2026 Corrections Issued KEVIN BERBERYAN