6546-6548 N GAZETTE AVE 91306

Certificate Information: 6546-6548 N GAZETTE AVE 91306

Application / Permit
24014-20000-04013
Plan Check / Job No.
B24VN15720
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: CONVERT (E) ATTACHED GARAGE WITH ADDITIONS INTO A (N) 2-STORY 22'-2" x18'-2" ACCESSORY DWELLING UNIT TO COMPLY WITH LAMC 12.22 A.33(c) and (e) PER ENGINEERING
Permit Issued
Issued on 3/3/2025
Issuing Office
Current Status
CofO Issued on 1/29/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/6/2024 APPLICANT
Assigned to Plan Check Engineer 9/19/2024 ALFRED RAMIREZ
Corrections Issued 9/21/2024 ALFRED RAMIREZ
Quality Review Completed 9/25/2024 STEVEN KIM
Applicant returned to address corrections 2/18/2025 ALFRED RAMIREZ
Plan Check Approved 3/3/2025 ALFRED RAMIREZ
Issued 3/3/2025 APPLICANT
CofO in Progress 1/21/2026 ROBERT GOLD
No Progress 1/22/2026 ROBERT GOLD
CofO in Progress 1/22/2026 ROBERT GOLD
Permit Finaled 1/29/2026 MICHAEL PELHAM
CofO Issued 1/29/2026 MICHAEL PELHAM
Permit Finaled 1/29/2026 MICHAEL PELHAM

Permit Application Clearance Information

Address approval Cleared 10/19/2024 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 10/19/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 10/21/2024 BIAINA HARITUNIAN
Sewer availability Cleared 12/12/2024 ROSE MARIE SMITH

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/3/2025 Conditional Approval ALEXANDER HANDY
PLUMBING-Rough 6/3/2025 Partial Approval ALEXANDER HANDY
Footing/Foundation/Slab 6/5/2025 Approved ALEXANDER HANDY
PLUMBING-Rough 6/5/2025 Partial Approval ALEXANDER HANDY
Wood Frame 6/17/2025 Conditional Approval ALEXANDER HANDY
ELECTRICAL-Rough 7/21/2025 Approved ALEXANDER HANDY
Floor/Roof Diaphrgm/Shear Wall 7/21/2025 Corrections Issued ALEXANDER HANDY
HVAC-Rough 7/21/2025 Approved ALEXANDER HANDY
PLUMBING-Rough 7/21/2025 Approved ALEXANDER HANDY
Interior/Exterior Lathing 7/31/2025 Approved JUAN ALVARADO
Shower Pan 7/31/2025 Approved JUAN ALVARADO
BUILDING-Rough-Frame 8/1/2025 Corrections Issued ARUTYUN MADATYAN
Wood Frame 8/4/2025 Not Ready for Inspection SCOTT SOBEL
Insulation 8/11/2025 Corrections Issued SCOTT SOBEL
Insulation 8/14/2025 Approved ALEXANDER HANDY
Drywall Nailing 8/19/2025 Approved ALEXANDER HANDY
BUILDING-Rough-Frame 11/5/2025 Not Ready for Inspection ARUTYUN MADATYAN
Final 11/5/2025 Corrections Issued ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 11/5/2025 SGSOV Approved ARUTYUN MADATYAN
Smoke Detectors 11/5/2025 Approved ARUTYUN MADATYAN
BUILDING-Rough-Frame 11/19/2025 Approved JEFFREY HARTLINE
Final 11/19/2025 Corrections Issued JEFFREY HARTLINE
Final 1/5/2026 Corrections Issued MORRIS JACKSON
Service/Power Release 1/6/2026 Approved MORRIS JACKSON
Final 1/9/2026 Not Ready for Inspection GEVORK IPCHYAN
Final 1/20/2026 OK to Issue CofO ROBERT GOLD