18208 W LOS ALIMOS ST 91326

Certificate Information: 18208 W LOS ALIMOS ST 91326

Application / Permit
24014-20000-03979
Plan Check / Job No.
B24VN15544
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
**ePlan*** Conversion of (e) portion of attached garage and rear addition to create new attached bedroom to (e) SFD w/ att. Garage
Permit Issued
Issued on 10/1/2024
Issuing Office
Current Status
CofO Issued on 2/12/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/9/2024 APPLICANT
Assigned to Plan Check Engineer 9/13/2024 EDWIN ESPIN
Corrections Issued 9/16/2024 EDWIN ESPIN
Plan Check Approved 9/30/2024 DAVID CASTILLO
Issued 10/1/2024 APPLICANT
CofO in Progress 2/5/2025 DAVID SCANTLIN
Permit Finaled 2/12/2025 JOHN JANSON
CofO Issued 2/12/2025 JOHN JANSON
Permit Finaled 2/12/2025 JOHN JANSON

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 9/18/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 9/19/2024 CARLOS AGUILERA
Sewer availability Cleared 9/19/2024 CARLOS AGUILERA

Contact Information

Architect Dembsky,, Amit; Lic. No.: NA30383       ,
Contractor Preferred Home Builders Inc; Lic. No.: 773147-B       ,

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/22/2024 Approved DAVID SCANTLIN
ELECTRICAL-Rough 11/26/2024 Not Ready for Inspection DAVID SCANTLIN
Pre-Inspection 11/26/2024 Not Ready for Inspection DAVID SCANTLIN
PLUMBING-Rough 12/9/2024 Partial Approval KRISTEN CAUSEY
BUILDING-Rough-Frame 12/11/2024 Partial Approval DAVID SCANTLIN
Insulation 12/11/2024 Partial Approval DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 12/18/2024 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 12/23/2024 Approved DAVID SCANTLIN
ELECTRICAL-Rough 12/23/2024 Approved DAVID SCANTLIN
Green Building Rough 12/23/2024 Not Ready for Inspection DAVID SCANTLIN
PLUMBING-Rough 12/23/2024 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 12/26/2024 Approved KRISTEN CAUSEY
Green Building Rough 12/26/2024 Approved KRISTEN CAUSEY
Interior/Exterior Lathing 12/26/2024 Partial Approval KRISTEN CAUSEY
Insulation 12/30/2024 Approved DAVID SCANTLIN
Drywall Nailing 1/3/2025 Corrections Issued SCOTT SOBEL
Drywall Nailing 1/8/2025 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 1/8/2025 Partial Approval CHRIS CHRISTENSEN
Shower Pan 1/8/2025 Approved CHRIS CHRISTENSEN
Final 2/4/2025 OK to Issue CofO DAVID SCANTLIN
Green Building Final 2/4/2025 Approved DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 2/4/2025 SGSOV Approved DAVID SCANTLIN
Smoke Detectors 2/4/2025 Approved DAVID SCANTLIN