9833 N DELCO AVE 91311
Certificate Information: 9833 N DELCO AVE 91311
- Application / Permit
- 24014-20000-03971
- Plan Check / Job No.
- B24VN15511
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Eplan: Ground floor addition to an (E) 1-Story SFD w/Attached Garage
- Permit Issued
- Issued on 2/1/2025
- Issuing Office
- Current Status
- Issued on 2/1/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/5/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/9/2024 | DAVID CASTILLO |
| Corrections Issued | 9/10/2024 | DAVID CASTILLO |
| Plan Check Approved | 1/15/2025 | DAVID CASTILLO |
| Issued | 2/1/2025 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 12/6/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 12/17/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 12/17/2024 | BIAINA HARITUNIAN |
Contact Information
| Architect | Di, Zitti, Fernando; Lic. No.: NA24587 | , |
| Contractor | J P General Building Inc; Lic. No.: 762764-B | , |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/10/2025 | Approved | KRISTEN CAUSEY |
| Excavation/Setback/Form/Re-Bar | 2/18/2025 | Approved | JEFFREY HARTLINE |
| Special/Order Compliance | 2/18/2025 | Corrections Issued | JEFFREY HARTLINE |
| Floor/Roof Diaphrgm/Shear Wall | 3/3/2025 | Partial Approval | KRISTEN CAUSEY |
| ELECTRICAL-Rough | 3/7/2025 | Approved | DAVID SCANTLIN |
| HVAC-Rough | 3/7/2025 | Corrections Issued | DAVID SCANTLIN |
| PLUMBING-Rough | 3/7/2025 | Corrections Issued | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 3/11/2025 | Approved | DAVID SCANTLIN |
| Footing/Foundation/Slab | 3/11/2025 | Partial Approval | DAVID SCANTLIN |
| Green Building Rough | 3/11/2025 | Approved | DAVID SCANTLIN |
| HVAC-Rough | 3/11/2025 | Approved | DAVID SCANTLIN |
| Shower Pan | 3/11/2025 | Approved | DAVID SCANTLIN |
| Insulation | 3/12/2025 | Approved | GEVORK IPCHYAN |
| Drywall Nailing | 3/17/2025 | Approved | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 3/17/2025 | Approved | KRISTEN CAUSEY |
| Footing/Foundation/Slab | 5/23/2025 | Approved | KRISTEN CAUSEY |
| Green Building Final | 5/23/2025 | Approved | KRISTEN CAUSEY |
| SGSOV-Seismic Gas S/O Valve | 5/23/2025 | SGSOV Approved | KRISTEN CAUSEY |
| Smoke Detectors | 5/23/2025 | Approved | KRISTEN CAUSEY |